I PEKERJAAN PENDAHULUAN
II PEKERJAAN GALIAN / URUGAN
III PEKERJAAN PONDASI
IV PEKERJAAN BETON BERTULANG
V PEKERJAAN DINDING / PLESTERAN
VI PEKERJAAN KAP / ATAP
VII PEKERJAAN PLAFOND
VIII PEKERJAAN KOSEN, PINTU , JENDELA
IX PEKERJAAN PENGGANTUNG
X PEKERJAAAN LANTAI
XI PEKERJAAN PENGECATAN
XII PEKERJAAN PLUMBING / SANITAIR
XIII PEKERJAAN LISTRIK
XIV PEKERJAAN LAIN - LAIN
JUMLAH
DIBULATKAN
ULASI RENCANA ANGGARAN BIAYA
6,100,000.00
8,314,500.00
50,390,348.00
61,573,296.47
86,890,800.00
50,484,924.50
32,181,709.03
32,392,500.00
6,450,000.00
33,034,435.10
52,264,460.99
12,003,437.00
7,200,000.00
14,795,000.00
454,075,411.09
454,075,000.00
ROZIQIN
RENCANA ANGGARAN BIAYA
PROYEK : PEMBANGUNAN KAWASAN PERKEBUNAN
PEKERJAAN : PEMBANGUNAN KANTOR KARYAWAN
LOKASI : BATU AMPAR KUTAI KARTANEGARA
Harga
No. Uraian Pekerjaan Sat Volume Satuan
( Rp. )
I PEKERJAAN PENDAHULUAN
1 Pengukuran dan Bowplank m² 390.000
SUB TOTAL
II PEKERJAAN GALIAN / URUGAN
1 Galian Tanah Pondasi m³ 73.313
2 Urugan Tanah Kembali m³ 18.328
3 Urugan TanahTambahan m³ 38.250
4 Urugan Pasir Bawah Pondasi, t = 10 Cm m³ -
5 Urugan Pasir Bawah Lantai, t = 5 Cm m³ 7.710
SUB TOTAL
III PEKERJAAN PONDASI
1 Pekerjaan Pancang Ulin 10/10 - 2m ttk 53.875
2 Pekerjaan Kalang Ulin 5/20 m³ 0.065
3 Pekerjaan Sunduk Ulin 5/10 m³ 0.014
4 Pekerjaan Pondasi Batu Gunung 1:4 (Pagar Keliling) m³ 6.160
5 Pekerjaan Aanstamping Batu Gunung m³ 14.663
6 Pekerjaan Pondasi Roolag m' 6.500
SUB TOTAL
IV PEKERJAAN BETON & STRUKTUR KAYU ULIN
1 Cor Lantai Kerja 1 : 3 : 5, t = 8 cm m³ 15.794
2 Sloof (15/25), Besi dia. 12 SNI sengkang dia. 8 SNI m³ 2.000
3 Sloof (30/60), Besi D16 SNI sengkang D10 SNI m³ 2.933
4 Sloof (15/25), Pagar Keliling Besi dia. 12 SNI sengkang dia. 8 SNI m³ 2.838
5 Kolom K1 (13/30), Besi dia. 12 SNI Sengkang 8 SNI m³ 2.730
6 Kolom K2 (13/15), Besi dia. 12 SNI sengkang dia. 8 SNI m³ 0.200
7 Kolom K3 (15/25), Besi dia. 12 SNI sengkang dia. 8 SNI m³ 0.200
8 Kolom K4 (20/40), Besi D16 SNI sengkang dia. 10 SNI m³ 0.200
9 Kolom Praktis, Pagar Keliling, Besi dia. 10 SNI Sengkang 8 SNI m³ 0.304 -
10 Ring Balk, Pagar Keliling, Besi dia. 10 SNI Sengkang 8 SNI m³ 0.828
11 Balok Latei (13/20), Besi dia. 12 SNI Sengkang 8 SNI m³ 0.378
12 Balok 15/40, Besi 12 SNI Sengkang 8 SNI m³ 0.500
13 Balok 25/60, Besi D16 SNI, Besi 12 SNI, Sengkang 10 SNI m³ 0.200
14 Balok 20/40, Besi D16 SNI Sengkang 10 SNI m³ 0.300
15 Balok 20/30, Besi D16 SNI Sengkang 10 SNI m³ 0.300
16 Balok 15/20, Besi 12 SNI Sengkang 8 SNI m³ 0.300
17 Balok 15/25, Besi 12 SNI Sengkang 8 SNI m³ 0.960
10 Ring Balk,Besi dia. 12 SNI Sengkang 8 SNI m³ 2.933
18 Plat Lantai Beton Bertulang, t=12cm m³ 0.500
19 Kanopi Beton Bertulang m³ -
SUB TOTAL
V PEKERJAAN DINDING / PLESTERAN
1 Pasangan Bata Ringan Hebel tebal 7,5 cm m² 305.032
2 Pasangan Batu bata 1 : 4, Pagar Keliling m² 76.000
3 Pasangan Bata Ringan Hebel tebal 7,5 cm 1 : 2 Trasram m² -
4 Plesteran dinding hebel 1 : 4 m² 600.064
5 Plesteran dinding bata 1 : 4, Pagar Keliling m² 152.000
6 Plesteran dinding hebel 1 : 2 m² -
SUB TOTAL
RAB halaman 3/ 78
Harga
No. Uraian Pekerjaan Sat Volume Satuan
( Rp. )
VI PEKERJAAN KAP / ATAP
1 Pekerjaan Rangka Atap Baja Ringan Setara "Taso" m² 315
2 Pasangan Atap Genteng Metal Sakura Roof m² 315
3 Pasangan Bubungan Metal m' 68.560
4 Pekerjaan Lisplank GRC m' 75.897
5 Pekerjaan Talang Seng m' 16.760
SUB TOTAL
VII PEKERJAAN PLAFOND
1 Plafond Gypsum polos 9mm + Rangka m² 251.780
2 List Plafond Gypsum m' 419.780
SUB TOTAL
VIII PEKERJAAN KUSEN, PINTU,JENDELA DAN KUNCI
1 Pintu Tipe P1 Dikurangkan dengan kusen yang sudah dibikin Unit 5.00
include: Engsel 4", Handel Pintu, dan Kunci Lidah
2 Pintu Tipe P1 Tambahan Unit 2.00
include: Engsel 4", Handel Pintu, dan Kunci Lidah
3 Pintu Tipe P2 Dikurangkan dengan kusen yang sudah dibikin Unit 4.00
include: Engsel 4", Handel Pintu, dan Kunci Lidah
4 Pintu Tipe P2 Tambahan Unit 2.00
include: Engsel 4", Handel Pintu, dan Kunci Lidah
5 Pintu Tipe P3 Dikurangkan dengan kusen yang sudah dibikin Unit 1.00
include: Engsel 4", Handel Pintu, dan Kunci Lidah
6 Pintu Tipe PJ1 Perubahan Model Unit 1.00
include: Engsel 4", Engsel 3", Hak Angin, Handel Jendela, Grendel Jendela,
Grendel Pintu, Kaca Bening 5 mm, Handel Pintu, dan Kunci Pelor
7 Pintu Tipe PJ2 Perubahan Model Unit 1.00
include: Engsel 4", Engsel 3", Hak Angin, Handel Jendela, Grendel Jendela,
Grendel Pintu, Kaca Bening 5 mm, Handel Pintu, dan Kunci Pelor
8 Pintu Tipe PJ3 Tambahan Unit 1.00
include: Engsel 4", Engsel 3", Hak Angin, Handel Jendela, Grendel Jendela,
Grendel Pintu, Kaca Bening 5 mm, Handel Pintu, dan Kunci Pelor
9 Jendela J1 = J3 Unit 3.00
include: Engsel 3", Hak Angin, Handel Jendela, Grendel Jendela, Kaca Bening 5 mm
10 Jendela J2 = J4 Unit 1.00
include: Engsel 3", Hak Angin, Handel Jendela, Grendel Jendela, Kaca Bening 5 mm
11 Jendela J3 = J1 Unit 2.00
include: Engsel 3", Hak Angin, Handel Jendela, Grendel Jendela, Kaca Bening 5 mm
12 Jendela J4 = J1 Unit 2.00
include: Engsel 3", Hak Angin, Handel Jendela, Grendel Jendela, Kaca Bening 5 mm
13 Jendela J5 Unit 1.00
include: Engsel 3", Hak Angin, Handel Jendela, Grendel Jendela, Kaca Bening 5 mm
14 Jendela J6 Unit 1.00
include: Engsel 3", Hak Angin, Handel Jendela, Grendel Jendela, Kaca Bening 5 mm
15 Glass Block Unit 64.00
16 Bovenlist (BV) Kamar Mandi Unit 5.00
SUB TOTAL
IX PEKERJAAN LANTAI
1 Pas. Keramik Lt Teras Depan 50x50 Setara Roman m² 15.520
2 Pas. Keramik Lt Teras Belakang 50x50 Setara Roman m² #REF!
3 Pas. Keramik Lt Halaman 50x50 Setara Roman m² 75.500
4 Pas. Keramik Lantai Ruangan 60x60 Setara Cove Granite Tile m² 215.500
5 Pas. Keramik Lantai km/wc, R.Cuci 20 x 20 Setara Roman m² -
6 Pas. Keramik Dinding km/wc 20 x 40 Setara Roman m² 9.440
7 Pas. Keramik Carport 50x50 Setara Roman m² 75.480
8 Pek. Plint Lantai Keramik (60x8) Setara Cove Granite Tile m' 100.350
9 Pas. Keramik Dinding Luar 40x40 Setara Roman m² 17.600
10 Pas. List Dinding Luar 10x40 Setara Roman m' 44.440
SUB TOTAL
X PEKERJAAN PENGECATAN
1 Pek. Cat dinding Luar (Mowilex Weather Coat) m² 199.170
2 Pek. Cat dinding Luar Pagar Keliling (Mowilex Weather Coat) m² 221.000
RAB halaman 4/ 78
Harga
No. Uraian Pekerjaan Sat Volume Satuan
( Rp. )
3 Pek. Cat dinding Dalam (Setara Mowilex) m² 296.150
4 Pek. Cat Plafond (Setara Mowilex) m² 261.780
5 Pek. Ducco Daun Pintu Panel bh 10.000
6 Pek. Ducco Daun Pintu Kaca bh 4.000
7 Pek. Ducco Daun Jendela bh 21.000
8 Pek. Ducco Kusen Pintu dan Jendela m' 106.380
9 Pek. Cat Minyak Lisplank m' 75.897
SUB TOTAL
XI PEKERJAAN PLUMBING / SANITAIR
1 Pasang Pipa Air kotor PVC type AW Ø 4" m' 28.50
2 Pasang Pipa Air Drainase PVC type AW Ø 4" m' 58.50
3 Pasang Pipa Air bekas PVC type AW Ø 3" m' 26.00
4 Pasang Pipa Air bekas PVC type AW Ø 2" m' 16.00
5 Pasang Pipa Instalasi Air Bersih type AW Ø 1/2" m' 115.00
6 Pasang Stop Kran 1/2" + instalasi (Setara Toto) Bh 6.00
7 Pekerjaan Septictank pas.bata + resapan Bh 2.00
8 Closet Duduk (setara Toto) Bh 5.00
9 Kran + Shower Flexsible Bh 6.00
10 Jet Shower Bh 5.00
11 Closet Jongkok (Setara Toto) Bh 1.00
12 Pasang Kran Leher Angsa 1/2" + instalasi (Setara Toto) Bh 1.00
13 Pasang Floor Drain Bh 6.00
SUB TOTAL
XII PEKERJAAN LISTRIK
1 Pek. Pasang Stop kontak (Broco) + instalasi (Kabel NYM) ttk 33.000
2 Pek. Titik Lampu Downlight + instalasi (Kabel NYM) ttk 34.000
3 Pek. Titik Lampu Biasa + Instalasi (Kabel NYM) ttk 7.000
4 Pek. Instalasi Lampu Dinding ttk 7.000
5 Pek. Instalasi Lampu Gantung ttk 4.000
6 Pek. Pasang Saklar Tunggal dan Ganda (Kabel NYM) ttk 28.000
7 Pek. Box MCB (Kabel NYY) group 24.000
8 Pek. Instalasi AC (Kabel NYM) ttk 5.000
9 Pasang Arde ttk 1.000
10 Terminal TV Kabel + instalasi ttk 3.000
11 Stop Kontak / Instalasi Telepon ttk 1.000
SUB TOTAL
XIII PEKERJAAN LAIN - LAIN
1 Pembersihan Akhir Lapangan Ls 400.000
2 Pembongkaran Bangunan Lama Ls 1.000
3 Pekerjaan Meja Dapur (Beton) Ls 1.000
4 Pekerjaan pas. Batu alam Candi Polos fin. Coating m2 8.300
5 Pekerjaan pas. Batu alam Batu Paras Jogja fin. Coating m2 7.000
6 Pekerjaan pas. Batu alam Batu Candi Sisir fin. Coating m2 3.900
7 Pekerjaan Kaca Tempered t= 8 mm m2 3.360
8 Pekerjaan Bak Kontrol Bh 10.000
9 Pekerjaan Benangan dan profil dinding Ls 1.000
10 Pekerjaan Water Proofing Dak m2 -
SUB TOTAL
Samarinda, 26 April 2
Dibuat oleh,
RAB halaman 5/ 78
A ANGGARAN BIAYA
Jumlah
Harga
( Rp. )
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
RAB halaman 6/ 78
Jumlah
Harga
( Rp. )
-
-
-
-
-
-
-
-
-
-
-
-
-
#REF!
-
-
-
-
-
-
-
-
#REF!
-
-
RAB halaman 7/ 78
Jumlah
Harga
( Rp. )
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
RAB halaman 8/ 78
RENCANA ANGGARAN BIAYA
PROYEK : PEMBANGUNAN KAWASAN PERKEBUNAN
PEKERJAAN : PEMBANGUNAN KANTOR KARYAWAN
LOKASI : BATU AMPAR KUTAI KARTANEGARA
Harga
No. Uraian Pekerjaan Sat Volume Satuan
( Rp. )
I PEKERJAAN GALIAN / URUGAN
1 Galian Tanah Pondasi m³ 2.870 102,375.00
2 Urugan Tanah Kembali m³ 0.718 34,125.00
3 Urugan Pasir Bawah Pondasi, t = 10 Cm m³ 0.359 116,783.33
SUB TOTAL
II PEKERJAAN PONDASI
1 Pekerjaan Pancang Ulin 10/10 - 2m ttk 2.243 192,617.50
2 Pekerjaan Kalang Ulin 5/20 m³ 0.065 5,850,000.00
3 Pekerjaan Sunduk Ulin 5/10 m³ 0.014 4,940,000.00
4 Pekerjaan Pondasi Batu Gunung 1:4 (Pagar Keliling) m³ 1.413 1,113,450.00
5 Pekerjaan Aanstamping Batu Gunung m³ 0.718 680,441.67
SUB TOTAL
III PEKERJAAN BETON & STRUKTUR KAYU ULIN
1 Sloof (15/25), Besi dia. 12 SNI sengkang dia. 8 SNI m³ 0.168 6,967,608.87
2 Sloof (15/25), Pagar Keliling Besi dia. 12 SNI sengkang dia. 8 SNI m³ 0.150 6,967,608.87
3 Balok Latei (13/20), Besi dia. 12 SNI Sengkang 8 SNI m³ 0.026 7,638,063.84
4 Ring Balk,Besi dia. 12 SNI Sengkang 8 SNI m³ 0.146 7,638,063.84
SUB TOTAL
IV PEKERJAAN DINDING / PLESTERAN
1 Pasangan Bata Ringan Hebel tebal 7,5 cm m² 16.005 225,000.00
2 Plesteran dinding hebel 1 : 4 m² 32.010 83,050.00
SUB TOTAL
V PEKERJAAN PLAFOND
1 Plafond Gypsum polos 9mm + Rangka m² 153,097.22
2 List Plafond Gypsum m' 8.970 27,500.00
SUB TOTAL
VI PEKERJAAN PENGECATAN
1 Pek. Cat dinding Dalam (Setara Mowilex) m² 32.010 57,245.20
SUB TOTAL
VIII PEKERJAAN LAIN - LAIN
1 Pekerjaan Bongkaran Ls 1.000 2,000,000.00
SUB TOTAL
TOTAL
Samarinda, 14 Juni 2
Dibuat oleh,
RAB halaman 9/ 78
A ANGGARAN BIAYA
Jumlah
Harga
( Rp. )
293,857.20
24,488.10
41,901.86
360,247.16
431,944.74
377,419.35
68,611.11
1,573,054.32
488,284.94
2,939,314.47
1,171,864.72
1,045,141.33
198,589.66
1,113,343.28
#VALUE!
3,601,125.00
2,658,430.50
6,259,555.50
-
246,675.00
246,675.00
1,832,418.85
1,832,418.85
2,000,000.00
2,000,000.00
#VALUE!
Samarinda, 14 Juni 2017
Dibuat oleh,
Robensyah
Harga
No. Uraian Pekerjaan Sat Volume Satuan
( Rp. )
I PEKERJAAN PENDAHULUAN
1 Pembersihan lahan ls 1.000 2,500,000.00
2 Pengukuran dan Bowplank m' 48.000 75,000.00
SUB TOTAL
II PEKERJAAN GALIAN / URUGAN
1 Galian Tanah Pondasi m³ 52.800 80,000.00
2 Urugan Tanah Kembali m³ 13.200 40,000.00
3 Urugan Tanah Tambahan m³ 28.500 125,000.00
SUB TOTAL
III PEKERJAAN PONDASI
1 Pekerjaan Pancang Ulin 10/10 - 2m ttk 36.000 172,617.50
2 Pekerjaan Pondasi Roolag (Teras) m' 63.000 175,000.00
3 Pekerjaan Aanstamping Batu Gunung m' 12.000 680,441.67
4 Pekerjaan Pasangan Batu Gunung m³ 22.440 1,113,450.00
SUB TOTAL
IV PEKERJAAN BETON & STRUKTUR KAYU ULIN
1 Cor Lantai Kerja 1 : 3 : 5, t = 7 cm m³ 8.560 1,330,575.00
2 Sloof (15/20) m³ 2.650 5,968,170.71
3 Kolom K1 (15/15) m³ 1.800 6,314,324.71
4 Balok Kanopi m³ 0.268 7,480,735.23
5 Ring Balk (15/20) m³ 2.340 7,480,735.23
6 Kanopi Beton m³ 0.577 6,042,533.97
SUB TOTAL
V PEKERJAAN DINDING / PLESTERAN
ROZIQIN
Jumlah Harga
Harga Volume
( Rp. ) ( Rp. )
2,500,000.00
###
3,600,000.00
###
6,100,000.00
###
4,224,000.00
###
528,000.00
###
3,562,500.00
###
8,314,500.00
###
6,214,230.00
###
11,025,000.00
###
8,165,300.00
###
24,985,818.00
###
50,390,348.00
###
11,389,722.00
###
15,815,652.38
11,365,784.49
###
2,008,016.35
###
17,504,920.44
###
3,489,200.81
###
61,573,296.47
###
###
22,751,959.03
###
9,429,750.00
###
32,181,709.03
###
6,842,500.00
###
750,000.00
1,400,000.00
300,000.00
3,000,000.00
###
5,250,000.00
###
1,025,000.00
###
11,700,000.00
###
2,125,000.00
32,392,500.00
###
1,250,000.00
###
70,000.00
70,000.00
###
980,000.00
700,000.00
###
420,000.00
30,511,579.50
###
2,522,855.60
###
33,034,435.10
###
31,123,225.12
###
7,748,137.82
###
694,098.05###
5,635,000.00
###
4,500,000.00
###
2,184,000.00
###
380,000.00
###
52,264,460.99
###
upah
1,350,000.00
###
4,500,000.00
###
150,000.00
###
200,000.00
###
450,000.00
###
3,000,000.00
###
439,700.00
###
281,700.00
###
242,037.00
###
1,390,000.00
###
12,003,437.00
###
2,925,000.00
###
1,800,000.00
###
220,000.00
###
1,375,000.00
###
13,200,000.00
14,795,000.00
###
bata
Samarinda, 8 JanuariSamarinda,
2019 17 Desember 2016
Dibuat oleh, Dibuat oleh,
###
Bak kontrol
bata
plester
ROZIQIN Anis Kurnia Mi'raji
###
Kolom Lantai 1
Ukuran Luas Jumlah Tinggi
K1 0.15 0.15 0.02 30.00 3.30
K2 -
K3 -
K4 -
Balok Panjang
Ukuran Luas Bx By
B. latei
Rbalk 1 0.15 0.20 0.03 45.00 52.75
Rbalk 2
Balok B1
Balok B2 -
Balok -
Balok -
Balok -
Gewel 0.15 0.20 0.03
luas Volume
Plat Lt 2 tebal 0.12 m - -
Dak tebal 0.10 m -
Lantai 1
Teras Depan
Teras Samping
Ruang Rapat
Ruang Tamu
Ruang GM
Ruang Direktur
Ruang 3
Ruang Kerja
Gudang
Pantry
Toilet 1
Plafon luar
LANTAI
DINDING Pas Bata 1 : 4
Luar
Keliling 49.00
Tinggi 3.30
Sub Luas 161.70
Kamar Mandi
Tinggi Kamar Mandi
Sub Luas -
Luas 161.70
Gewel
Jumlah Tinggi Total
6.00 1.50 2.430
-
-
-
Panjang
Total Volume
-
97.75 2.933
- -
- -
- -
- -
- -
- -
22.00 0.660
- Urug
Luas Tnh Hlmn Tanah Psr Bwh Lti
154.20 150.60 (46.26) 38.25 7.71
154.200 150.600 - 38.25 7.71
6.000 3.000 1.20 0.30
1.200 0.600 0.30 0.06
22.000 5.50 1.10
9.000 2.25 0.45
9.000 2.25 0.45
14.000 3.50 0.70
9.000 2.25 0.45
67.000 16.75 3.35
9.000 2.25 0.45
6.125 1.53 0.31
1.875 0.47 0.09
- -
- - -
- -
- - - -
133.65 - - - -
120.84 - - - -
-
0.10
-
Dalam Luar Dalam Luar Dalam
11.25 - - - -
1.56 - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
-
12.81 - - - -
Beton
- 4,308,811.44 -
- 4,000,000.00 -
- 4,500,000.00 -
29.081 -
23,000,000.00
Pagar Keliling
Kubik Panjang 23.50
Batang Kalang 47.00 11.75 Lembar
Batang Pancang - batang
Kubik Panjang 23.50
Batang Kalang 47.00 11.75 Lembar
Batang Pancang 11.75 batang
Sunduk 11.75 1.18 batang
Plafond List
Lantai Kerja Plywood Calsiboard Lumbersiring Gypsum Kayu
10.79 214.78 - - 271.78 -
10.79 214.78 - - 271.78 -
0.42 6.00 - 12.00 -
0.08 - -
1.54 22.00 19.00
0.63 9.00 12.00
0.63 9.00 12.00
0.98 14.00 14.00
0.63 9.00 12.00
4.69 67.00 35.00
0.63 9.00 12.00
0.43 6.13 12.00
0.13 1.88 5.50 -
- -
- -
- 61.78 126.28 -
-
- -
- - 23.30
46.50
4.68
-
15.20
-
-
30.00
-
-
-
-
-
-
96.38
Listrik
Biasa Saklar Stop kontak
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
ANALISA HARGA SATUAN PEKERJAAN
PROYEK : PEMBANGUNAN KAWASAN PERKEBUNAN
PEKERJAAN : PEMBANGUNAN KANTOR KARYAWAN
LOKASI : BATU AMPAR KUTAI KARTANEGARA
HARGA
HARGA SATUAN
NO URAIAN PEKERJAAN
(Rp.) UPAH (Rp.) BAHAN (Rp.)
1 10 M² Pembersihan Lapangan
0.850 OH Pekerja 130,000.00 110,500.00
0.030 OH Mandor 195,000.00 5,850.00
1 m2 = 1/10 x JUMLAH 116,350.00
2 10 M' Pasang Bowplank
0.060 m3 Papan 2,000,000.00 120,000.00
0.025 m3 Tiang 5/7 2,000,000.00 50,000.00
0.100 kg Paku 20,000.00 2,000.00
0.400 OH Tk. Kayu 162,500.00 65,000.00
0.080 OH Kepala Tukang 169,000.00 13,520.00
0.280 OH Pekerja 130,000.00 36,400.00
0.014 OH Mandor 195,000.00 2,730.00
1 m2 = 1/10 x JUMLAH 117,650.00 172,000.00
3 1 M³ Galian Tanah
0.750 OH Pekerja 130,000.00 97,500.00
0.025 OH Mandor 195,000.00 4,875.00
JUMLAH 102,375.00
4 1 M³ Urugan Tanah Kembali
0.500 OH Pekerja 130,000.00 65,000.00
0.025 OH Mandor 195,000.00 4,875.00
JUMLAH 69,875.00
5 1 M3 Urugan Pasir
1.000 m3 Pasir Urug 75,833.33 75,833.33
0.300 OH Pekerja 130,000.00 39,000.00
0.010 OH Mandor 195,000.00 1,950.00
JUMLAH 40,950.00 75,833.33
6 1 M3 Urugan Tanah
1.000 m3 Tanah Urug 31,666.67 31,666.67
0.500 OH Pekerja 130,000.00 65,000.00
0.025 OH Mandor 195,000.00 4,875.00
JUMLAH 30,000.00 31,666.67
7 1 M3 Pasang Aanstamping
1.100 m3 Bt. Gunung 390,000.00 429,000.00
0.500 m3 Pasir 75,833.33 37,916.67
1.530 OH Pekerja 130,000.00 198,900.00
0.075 OH Mandor 195,000.00 14,625.00
JUMLAH 213,525.00 466,916.67
8 1 M³ Pasangan Batu Gunung (1:4)
1.100 m3 Bt. Gunung 390,000.00 429,000.00
3.000 zak Semen Pc @ 50kg 84,500.00 253,500.00
0.600 m3 Pasir pasang 211,250.00 126,750.00
1.750 OH Pekerja 130,000.00 227,500.00
0.100 OH Mandor 195,000.00 19,500.00
0.300 OH Tk. Batu 162,500.00 48,750.00
0.050 OH Kep. tukang 169,000.00 8,450.00
JUMLAH 304,200.00 809,250.00
9 1 Titik Tiang Pancang 10/10 - 1m
0.010 m3 Ky. Balok ulin 4,940,000.00 49,400.00
0.105 OH Tk. Kayu 162,500.00 17,062.50
0.011 OH Kep. Tukang 169,000.00 1,859.00
0.580 OH Pekerja 130,000.00 75,400.00
0.015 OH Mandor 195,000.00 2,925.00
1.000 Alat bantu 10,000.00 10,000.00
JUMLAH 107,246.50 49,400.00
Analisa hal 41 / 78
HARGA
HARGA SATUAN
NO URAIAN PEKERJAAN
(Rp.) UPAH (Rp.) BAHAN (Rp.)
10 1 Titik Tiang Pancang 10/10 - 2m
0.020 m3 Ky. Balok ulin 4,940,000.00 98,800.00
0.145 OH Tk. Kayu 162,500.00 23,562.50
0.020 OH Kep. Tukang 169,000.00 3,380.00
0.400 OH Pekerja 130,000.00 52,000.00
0.025 OH Mandor 195,000.00 4,875.00
1.000 Alat bantu 10,000.00 10,000.00
JUMLAH 93,817.50 98,800.00
11 1 Titik Tiang Pancang Ulin 10/10 - 4m
0.040 m3 Ky. Balok ulin 4,940,000.00 197,600.00
0.100 OH Tk. Kayu 162,500.00 16,250.00
0.029 OH Kep. Tukang 169,000.00 4,901.00
0.500 OH Pekerja 130,000.00 65,000.00
0.039 OH Mandor 195,000.00 7,605.00
1.000 Alat bantu 10,000.00 10,000.00
JUMLAH 20,000.00 197,600.00
12 1 Titik Tiang Pancang Ulin 10/10 - 8m
0.080 m3 Ky. Balok ulin 4,940,000.00 395,200.00
0.100 OH Tk. Kayu 162,500.00 16,250.00
0.029 OH Kep. Tukang 169,000.00 4,901.00
0.500 OH Pekerja 130,000.00 65,000.00
0.039 OH Mandor 195,000.00 7,605.00
1.000 Alat bantu 10,000.00 10,000.00
JUMLAH 20,000.00 395,200.00
13 1 M3 Beton 1 : 3 : 5
4.000 zak Semen Pc @ 50kg 84,500.00 338,000.00
0.950 m3 Kerikil 585,000.00 555,750.00
0.570 m3 Pasir beton 211,250.00 120,412.50
0.500 OH Tk. Batu 162,500.00 81,250.00
0.050 OH Kepala tukang 169,000.00 8,450.00
1.500 OH Pekerja 130,000.00 195,000.00
0.025 OH Mandor 195,000.00 4,875.00
JUMLAH 300,000.00 1,014,162.50
14 1 M3 Beton 1 : 2 : 3
6.000 zak Semen Pc @ 50 Kg 84,500.00 507,000.00
0.700 m3 Kerikil 585,000.00 409,500.00
0.540 m3 Pasir beton 211,250.00 114,075.00
1.500 OH Pekerja 130,000.00 195,000.00
0.250 OH Mandor 195,000.00 48,750.00
0.600 OH Tukang Batu 162,500.00 97,500.00
0.030 OH Kepala Tukang 169,000.00 5,070.00
Catatan :
1.000 jam Molen 30,000.00
1.000 jam Vibrator 25,000.00
1.000 Alat Bantu 10,000.00
JUMLAH 300,000.00 1,030,575.00
15 1 M3 Stuut Werk
0.220 m3 Kayu Stuut 2,000,000.00 440,000.00
2.000 kg Paku 32,500.00 65,000.00
2.000 OH Tukang kayu 162,500.00 325,000.00
0.400 OH Kepala tukang 169,000.00 67,600.00
3.000 OH Pekerja 130,000.00 390,000.00
0.020 OH Mandor 195,000.00 3,900.00
JUMLAH 786,500.00 505,000.00
16 100 kg besi
100.000 kg Besi beton 16,900.00 1,690,000.00
2.000 kg Kawat 32,500.00 65,000.00
0.850 OH Tukang besi 162,500.00 138,125.00
0.150 OH Kepala tukang 169,000.00 25,350.00
0.750 OH Pekerja 130,000.00 97,500.00
260,975.00 1,755,000.00
1 kg besi = 1/100 x JUMLAH 2,609.75
Analisa hal 42 / 78
HARGA
HARGA SATUAN
NO URAIAN PEKERJAAN
(Rp.) UPAH (Rp.) BAHAN (Rp.)
17 10 m2 Begisting (dipakai 2x)
0.400 m3 Kayu 2,000,000.00 800,000.00
1.100 m2 plywood 6 mm 156,000.00 171,600.00
4.000 kg Paku 32,500.00 130,000.00
4.000 OH Tukang kayu 162,500.00 650,000.00
0.500 OH Kepala tukang 169,000.00 84,500.00
2.000 OH Pekerja 130,000.00 260,000.00
0.100 OH Mandor 195,000.00 19,500.00
Bongkar Siram
3.000 OH Pekerja 130,000.00 390,000.00
1,404,000.00 1,101,600.00
1 m2 = 1/20 x JUMLAH 70,200.00 55,080.00
18 1 M2 Pasangan batu bata 1:4
67.000 bh Batu bata 1,105.00 74,035.00
0.531 zak PC semen @ 50 kg 84,500.00 44,869.50
0.093 m3 Pasir pasang 211,250.00 19,646.25
0.200 OH Tukang batu 162,500.00 32,500.00
0.600 OH Pekerja 130,000.00 78,000.00
0.030 OH Mandor 195,000.00 5,850.00
0.020 OH Kepala tukang 169,000.00 3,380.00
JUMLAH 119,730.00 138,550.75
18 1 M3 Pasangan batu bata 1:4
1,302.083 bh Batu bata 1,105.00 1,438,802.08
2.090 zak PC semen @ 50 kg 84,500.00 176,605.00
0.406 m3 Pasir pasang 211,250.00 85,767.50
1.250 OH Tukang batu 162,500.00 203,125.00
1.750 OH Pekerja 130,000.00 227,500.00
0.100 OH Mandor 195,000.00 19,500.00
0.080 OH Kepala tukang 169,000.00 13,520.00
JUMLAH 463,645.00 1,701,174.58
18 1 M2 Pasangan bata Hebel 1 : 4 tebal 7,5 cm
0.075 m3 Hebel 7,5 cm 1,200,000.00 90,000.00
0.063 zak Perekat Bata Ringan 150,000.00 9,450.00
Mortar Perekat 40 kg
1.000 ls Alat Batu 5,000.00 5,000.00
0.100 OH Tukang batu 162,500.00 16,250.00
0.200 OH Pekerja 130,000.00 26,000.00
0.010 OH Mandor 195,000.00 1,950.00
0.010 OH Kepala tukang 169,000.00 1,690.00
JUMLAH 45,890.00 104,450.00
19 1 M2 Pasangan batu bata 1:2
67.000 bh Batu bata 1,105.00 74,035.00
0.870 zak PC semen @ 50 kg 84,500.00 73,515.00
0.080 m3 Pasir pasang 211,250.00 16,900.00
0.200 OH Tukang batu 162,500.00 32,500.00
0.600 OH Pekerja 130,000.00 78,000.00
0.030 OH Mandor 195,000.00 5,850.00
0.020 OH Kepala tukang 169,000.00 3,380.00
JUMLAH 119,730.00 164,450.00
20 1 M' Parit Pasangan batu bata 1:4
30.000 bh Batu bata 1,105.00 33,150.00
0.120 zak PC semen @ 50 kg 84,500.00 10,140.00
0.120 m3 Pasir pasang 211,250.00 25,350.00
0.150 OH Tukang batu 162,500.00 24,375.00
0.400 OH Pekerja 130,000.00 52,000.00
0.020 OH Mandor 195,000.00 3,900.00
0.015 OH Kepala tukang 169,000.00 2,535.00
JUMLAH 82,810.00 68,640.00
21 1 M2 Plasteran t. = 25 mm 1:4
0.130 zak PC semen @ 50 kg 84,500.00 10,985.00
0.020 m3 Pasir pasang 211,250.00 4,225.00
0.100 OH Tukang batu 162,500.00 16,250.00
0.010 OH Kepala tukang 169,000.00 1,690.00
Analisa hal 43 / 78
HARGA
HARGA SATUAN
NO URAIAN PEKERJAAN
(Rp.) UPAH (Rp.) BAHAN (Rp.)
Analisa hal 44 / 78
HARGA
HARGA SATUAN
NO URAIAN PEKERJAAN
(Rp.) UPAH (Rp.) BAHAN (Rp.)
23 1 M2 Acian
0.065 zak PC semen @ 50 kg 84,500.00 5,492.50
0.100 OH Tukang batu 162,500.00 16,250.00
0.010 OH Kepala tukang 169,000.00 1,690.00
0.150 OH Pekerja 130,000.00 19,500.00
0.008 OH Mandor 195,000.00 1,560.00
JUMLAH 39,000.00 5,492.50
24 1 M2 Afwerking beton
0.192 zak PC semen @ 50 kg 84,500.00 16,224.00
0.009 m3 Pasir pasang 211,250.00 1,901.25
0.200 OH Tukang batu 162,500.00 32,500.00
0.020 OH Kepala tukang 169,000.00 3,380.00
0.400 OH Pekerja 130,000.00 52,000.00
0.020 OH Mandor 195,000.00 3,900.00
JUMLAH 91,780.00 18,125.25
24 1 M3 Pekerjaan Struktur Kayu Ulin 10/10
1.200 m3 Balok Kayu Ulin 4,940,000.00 5,928,000.00
5.600 Kg Paku ulin 32,500.00 182,000.00
20.000 OH Tukang kayu 162,500.00 3,250,000.00
2.000 OH Kepala tukang 169,000.00 338,000.00
6.000 OH Pekerja 130,000.00 780,000.00
0.300 OH Mandor 195,000.00 58,500.00
4,426,500.00
upah x0.5 JUMLAH 4,426,500.00 6,110,000.00
25 1 M2 Rangka Atap Genteng
0.040 m3 Kayu Bengkirai 4,940,000.00 197,600.00
0.250 kg Paku 32,500.00 8,125.00
0.300 OH Tukang kayu 162,500.00 48,750.00
0.010 OH Kepala tukang 169,000.00 1,690.00
0.100 OH Pekerja 130,000.00 13,000.00
0.005 OH Mandor 195,000.00 975.00
JUMLAH 128,446.73 205,725.00
25 1 M2 Atap genteng metal
1.840 lbr Genteng 47,000.00 86,480.00
- m2 Alumunium Foil 10,165.57 -
0.200 OH Tukang kayu 162,500.00 32,500.00
0.022 OH Kepala tukang 169,000.00 3,718.00
0.150 OH Pekerja 130,000.00 19,500.00
0.005 OH Mandor 195,000.00 975.00
JUMLAH 56,693.00 86,480.00
26 1 M' Bubungan beton
2.000 bh Bubungan beton 25,000.00 50,000.00
0.167 bag Mortar Compound - -
0.067 bag Pigment - -
- m3 Pasir Pasang 211,250.00 -
- zak Semen 84,500.00 -
0.100 OH Tukang kayu - -
0.010 OH Kepala tukang 169,000.00 1,690.00
0.050 OH Tukang batu 162,500.00 8,125.00
0.200 OH Pekerja 130,000.00 26,000.00
0.005 OH Mandor 195,000.00 975.00
JUMLAH 36,790.00 50,000.00
27 1 Unit Pintu P1
5.100 m' Kusen Alum. 4" 143,000.00 729,300.00
1.000 unit Daun pintu 1,200,000.00 1,200,000.00
1.500 set Engsel pintu 84,500.00 126,750.00
1.000 set Kunci 2 slag setara SES 585,000.00 585,000.00
0.700 OH Tukang kayu 162,500.00 113,750.00
0.150 OH Kepala tukang 169,000.00 25,350.00
0.400 OH Pekerja 130,000.00 52,000.00
0.075 OH Mandor 195,000.00 14,625.00
JUMLAH 205,725.00 2,641,050.00
28 1 Unit Pintu P2
4.900 m' Kusen Alum. 4" 143,000.00 700,700.00
1.000 unit Daun pintu 1,200,000.00 1,200,000.00
1.500 set Engsel pintu 84,500.00 126,750.00
1.000 set Kunci bulat 585,000.00 585,000.00
Analisa hal 45 / 78
ISA HARGA SATUAN PEKERJAAN
JUMLAH HARGA
(Rp.)
11,635.00
24,700.00
102,375.00
69,875.00
116,783.33
61,666.67
680,441.67
1,113,450.00
156,646.50
Analisa hal 46 / 78
JUMLAH HARGA
(Rp.)
192,617.50
217,600.00
415,200.00
1,314,162.50
1,330,575.00
1,291,500.00
2,015,975.00
20,159.75
Analisa hal 47 / 78
JUMLAH HARGA
(Rp.)
2,505,600.00
125,280.00
258,280.75
2,164,819.58
150,340.00
284,180.00
151,450.00
Analisa hal 48 / 78
JUMLAH HARGA
(Rp.)
63,050.00
65,965.25
Analisa hal 49 / 78
JUMLAH HARGA
(Rp.)
44,492.50
109,905.25
10,536,500.00
334,171.73
143,173.00
86,790.00
2,846,775.00
Analisa hal 50 / 78
DAFTAR HARGA SATUAN UPAH DAN BAHAN TH. 2010
PROYEK : PEMBANGUNAN KAWASAN PERKEBUNAN
PEKERJAAN : PEMBANGUNAN KANTOR KARYAWAN
LOKASI : BATU AMPAR KUTAI KARTANEGARA
H. SATUAN BARU
NO. URAIAN SATUAN
(Rp.)
I. SPESIFIKASI UPAH :
89 Pasang Stop kran Leher angsa untuk Kitchen Zinc + instalasi Bh 250,000.00
90 Pasir Beton ( Palu ) M³ 275,000.00
91 Pasir Pasang / Tenggarong ( Rp. 250.000 / Rit / 2 M3 ) M³ 125,000.00
92 Pasir Urug Mahakam ( Rp. 175.000 / Rit / 2 M3 ) M³ 115,000.00
93 Paving Block m2 86,000.00
94 Pigment bh 32,500.00
95 Pipa PVC Dia 1/2" M1 3,750.00
96 Pipa PVC Dia 2 " M1 8,500.00
97 Pipa PVC Dia 3 " M1 17,000.00
98 Pipa PVC Dia 3 /4" M1 5,500.00
99 Pipa PVC Dia 4 " M1 20,000.00
100 Pipa Sambungan Pancang Bh 20,000.00
101 Pompa Sanyo Bh 340,000.00
102 Pompa Sanyo Bh 975,000.00
103 Pompa Simitsu Bh 385,000.00
104 Rel Pintu Garasi setara Grand Set 6,500,000.00
105 Rel Pintu Geser Set 350,000.00
106 Residu Kg 7,500.00
107 Roof Drain Bh 20,000.00
108 Sainding Sailler Kg 40,000.00
109 Semen PC ( @ 50 Kg ) Zak 62,000.00
110 Semen Putih Zak 95,000.00
111 Shower + Kran + Aksesoris Bh 225,000.00
112 Shower Screen+ Kran + Aksesoris Bh 250,000.00
113 Stop Kran 1/2" Bh 60,000.00
114 Tangki Air Fiber 700 Liter Bh 705,000.00
115 Tempat Sabun tanam (Toto) Bh 45,000.00
116 Thinner A spesial Ltr 17,500.00
117 Triplek 18 mm Lbr 105,000.00
118 Triplek 4 mm Lbr 45,000.00
119 Triplek 6 mm Lbr 60,000.00
120 Vee Ridge End Monier/ Setara Genteng Keramik bh 12,500.00
121 Vee Ridge Monier/ Setara Genteng Keramik bh 12,500.00
122 Vee Starter Monier/ Setara Genteng Keramik bh 12,500.00
123 Verge bh 12,500.00
124 Verge End bh 12,500.00
125 Washtafel Bh 245,000.00
126 Wood Filler ( Cat Dasar/ Dempul ) Kg 21,600.00
127 Wood Stain ( Pewarna ), dark brown Kg `
di buat oleh,
ROZIQIN
KETERANGAN
Rp 700,000/ rol
2kg
Rp 130,000/2,5 Kg
Rp 175,000/2,5 Kg
elephand
jaya board
jaya board
KW1
KW1
KW1
KW1
KW1
SES
15,000/ btg
Rp 34,000/ btg
68,000/btg D
Rp 22,000/ btg
Rp 80,000/ btg
125W
150W
125W
H. SATUAN
NO. URAIAN SATUAN
Rp.
I. UPAH:
II. BAHAN
-
Estimator
16
KETERANGAN
JADWAL PELAKSANAAN PEKERJAAN
PROYEK : PEMBANGUNAN KAWASAN PERKEBUNAN
PEKERJAAN : PEMBANGUNAN KANTOR KARYAWAN
LOKASI : BATU AMPAR KUTAI KARTANEGARA
IV. PEKERJAAN BETON BERTULANG 61,573,296.47 14.602 2.19 2.19 2.19 2.19 2.19 2.19 2.19 2.19 2.19 2.19 2.19 2.19 2.19 2.19 2.19
V. PEKERJAAN DINDING / PLESTERAN 86,890,800.00 20.606 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18
VI. PEKERJAAN KAP / ATAP 50,484,924.50 11.972 2.15 2.15 2.15 2.15
VII. PEKERJAAN PLAFOND 32,181,709.03 7.632 0.71 0.71 0.71 0.71 0.71
VIII. PEKERJAAN KUSEN, PINTU,JENDELA D 6,450,000.00 1.530 0.81 0.81 0.81 0.81 0.81 0.81 0.81
IX. PEKERJAAN LANTAI 33,034,435.10 7.834 0.84 0.84 0.84 0.84 0.84 0.84 0.84
X. PEKERJAAN PENGECATAN 52,264,460.99 12.394 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90
XI. PEKERJAAN PLUMBING / SANITAIR 12,003,437.00 2.847 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38
XIII. PEKERJAAN LAIN - LAIN 14,795,000.00 3.509 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62
JUMLAH 421,682,911.09 100.00 1.70 4.49 2.19 3.74 4.48 4.18 3.37 2.19 2.19 3.37 3.74 4.04 6.04 4.45 6.23 4.34 3.48 3.99 2.68 1.97 0.84 0.84 2.55 2.55 3.54 2.70 1.89 1.89 1.89 3.21
KUMULATIF 0.00 1.70 6.19 8.37 12.12 16.59 20.77 24.14 26.33 28.51 31.88 35.63 39.66 45.71 50.16 56.39 60.73 64.21 68.20 70.88 72.85 73.69 74.53 77.07 79.62 83.16 85.87 87.76 89.65 91.54 94.75
REALISASI MINGGUAN ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
REALISASI KUMULATIF
DEVIASI
Estimator
ELAKSANAAN PEKERJAAN
10
0
90
80
70
60
50
0.81 0.81 0.81
40
0,2m' 0,2m'
1.900 16.000 0.891
0,65m'
0,2m' 0,2m'
2.500 8.000 0.891
0,95m'
0,65m'
0,35
26.667 6.000 0.888
0,15
0,3
0.650 178.778 0.395
0,1
TOTAL BESI ø10 +Ø8
TOTAL BESI + 10%
PEKERJAAN PEMBESIAN SLOOF 30X60CM, BESI Ø16 & 10
PANJANG BANYAKNYA BERAT PER
NO SKET GAMBAR
(M') (BT/BH) M'
1
0,35
5.556 10.000 1.578
0,15
0,3
1.650 38.037 0.617
0,1
0,3
12.500 6.000 0.888
0,13
0,3
1.050 84.333 0.395
0,13
0,3
12.210 8.000 0.888
0,3
12.210 8.000 0.888
0,13
2
0,13
0,3
2
0,13
0,30
0,2
59.172 4.000 0.617
2
0,08
2
0,10
2
0,08
2
0,10
2
0,10
2
0,10
2
0,10
2
0,10
2
0,10
0,1
10.000 7.667 0.617
2
VOLUME
(KG)
27.086
27.086
29.795
100CM
17.820
13.543
31.363
34.500
2&8
VOLUME
(KG)
142.042
45.850
187.892
206.681
& 10
VOLUME
(KG)
87.680
38.692
126.372
139.009
12 & 8
VOLUME
(KG)
66.582
34.977
101.559
111.715
12 & 8
VOLUME
(KG)
86.716
86.716
44.265
130.982
144
12 & 8
VOLUME
(KG)
210.121
54.614
264.735
291
8&6
VOLUME
(KG)
145.917
54.675
54.675
200.592
221
12 & 8
VOLUME
(KG)
136.578
96.593
233.172
256.489
10 & 8
VOLUME
(KG)
126.462
41.688
168.149
0.000
2&8
VOLUME
(KG)
147.960
147.960
42.023
189.983
209
2&8
VOLUME
(KG)
126.259
43.426
169.685
186.653
2&8
VOLUME
(KG)
133.164
34.938
34.938
168.102
184.913
6 & 10
VOLUME
(KG)
157.824
58.749
216.573
238.230
2&8
VOLUME
(KG)
177.552
48.441
225.993
248.592
2&8
VOLUME
(KG)
142.042
45.850
187.892
206.681
Ø 10
VOLUME
(KG)
61.700
50.594
112.294
0.000
Ø 10
VOLUME
(KG)
47.265
33.497
80.762
0.000