A Study
Presented to
Professor
College of Engineering
In Partial Fulfillment
By
Demdam, Donabel
April 2019
Table of Contents
EXECUTIVE SUMMARY 3
LIST OF TABLES Error! Bookmark not defined.
LIST OF FIGURES Error! Bookmark not defined.
ABBREVIATIONS Error! Bookmark not defined.
CHAPTER 1: INTRODUCTION Error! Bookmark not defined.
1.1 Background Error! Bookmark not defined.
1.2 Scope and objectives Error! Bookmark not defined.
1.2.1 Scope Error! Bookmark not defined.
1.2.2 Objectives Error! Bookmark not defined.
1.3 Terms of Reference Error! Bookmark not defined.
CHAPTER 2: PROJECT DESCRIPTION Error! Bookmark not defined.
2.1 Site location Error! Bookmark not defined.
2.2 Site status Error! Bookmark not defined.
2.3 Nature of the project Error! Bookmark not defined.
2.4 Site Ownership Error! Bookmark not defined.
2.5 Project Activities Error! Bookmark not defined.
2.6 Operational activities Error! Bookmark not defined.
2.7 The Abandonment phase Error! Bookmark not defined.
2.8 Project Budget Error! Bookmark not defined.
CHAPTER 3: BASELINE CONDITIONS Error! Bookmark not defined.
3.1 Introduction Error! Bookmark not defined.
3.2 Environmental setting Error! Bookmark not defined.
3.2.1 Flora and fauna Error! Bookmark not defined.
3.3 Geographical setting Error! Bookmark not defined.
3.3.1 Topography Error! Bookmark not defined.
3.3.2 Climatic conditions Error! Bookmark not defined.
3.3.3 Geology and soils Error! Bookmark not defined.
3.3.4 Water Quality Error! Bookmark not defined.
3.4 Socio-economic setting Error! Bookmark not defined.
3.4.1 Demography Error! Bookmark not defined.
3.4.2 Land Use and Socio-economic settingError! Bookmark not
defined.
3.4.3 Poverty Error! Bookmark not defined.
CHAPTER 4: LEGAL AND INSTITUTIONAL FRAMEWORKError! Bookmark
not defined.
4.1 Institutional Framework Error! Bookmark not defined.
1
4.2 Legislative Framework in Philippine Related to This Project Error!
Bookmark not defined.
4.3 Environmental Regulations Error! Bookmark not defined.
4.4 Policy framework Error! Bookmark not defined.
CHAPTER 5: ANALYSIS OF ALTERNATIVES Error! Bookmark not defined.
CHAPTER 6: PUBLIC PARTICIPATION AND SITE VISITSError! Bookmark
not defined.
6.0 Introduction Error! Bookmark not defined.
6.1 Site Visit Documentation Error! Bookmark not defined.
CHAPTER 7. PROJECTED IMPACTS AND MITIGATION MEASURES Error!
Bookmark not defined.
7.1 Impact Identification Error! Bookmark not defined.
7.2.1 Operation Phase Error! Bookmark not defined.
7.2 Impact Prediction & Evaluation Error! Bookmark not defined.
CHAPTER 8. ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP)
AND MITIGATING MEASURES Error! Bookmark not defined.
8.1 Mitigating Measures/Enhancement PlanError! Bookmark not
defined.
8.2 Environmental Monitoring Plan Error! Bookmark not defined.
CHAPTER 9. CONCLUSIONS AND RECOMMENDATIONSError! Bookmark
not defined.
9.1 Conclusions Error! Bookmark not defined.
9.2 Recommendations Error! Bookmark not defined.
REFERENCES Error! Bookmark not defined.
ANNEXES 36
2
EXECUTIVE SUMMARY
In this paper, the proponents will present and discuss the data gathered
from the conducted EIA of a proposed 40 hectares Banana Plantation and
Production Facility of JJD FARMS located at Barangay Concepion, Maco,
Compostella Valley Province. The study was conducted from February to
March 2019.
3
LIST OF TABLES
4
LIST OF FIGURES
5
ABBREVIATIONS
6
CHAPTER 1: INTRODUCTION
1.1 Background
The banana industry is one of the main economic drivers for the Davao
Region. The area has vast and rich lands suitable for growing export-quality
bananas. The province of Davao del Norte is even dubbed as the “Banana
Capital of the Philippines”. Though this big-scale banana industry continues
to be major economic player for Davao region, threats continue to emerge this
year from the various competitors our banana industry faces in the global
market.
7
1.2.1 Scope
The study will focus on the key issues and concerns and the impact of
the project to the community and to the environment. The EIA scope of study
shall be only limited to the parameters stated on the Terms of Reference.
1.2.2 Objectives
● To determine the significant impacts of the project both the positive and
negative impacts.
The EIA study aims to determine and assess the direct and indirect
environmental impacts of the development projects prior to its
implementation so that proper mitigating measures may be formulated.
The general approach of the conduct of the EIA study shall be based on
the annotated outline for IEE Report as presented in the Revised
Procedural Manual for DAO 03-30, Annex 2_15.
Attachments, Annexes, Appendices to the IEER shall follow the
Procedural Manual DAO 03-30
The IEER shall comply with the DENR EIA Review Criteria
The IEER shall cover IEA study on the Physical, Biological and Social
aspect affected by the project
Policy, Legal and Administrative Framework
8
The Environmental Impact Assessment (EIA) is conducted pursuant to
Presidential Decree No. 1586 or the Philippine Environmental Impact
Statement System (PEISS), the main law that governs EIA in the country.
In the course of the review of the EIA study, there are certain existing
laws and legal orders that should be considered. Among these are the
following:
9
CHAPTER 2: PROJECT DESCRIPTION
MACO
Brgy.
Concepcio
n
10
2.2 Site status
The company leased the land from various landowners in the locality,
it occupies approximately 40 hectares of land. In this scheme, the company
takes the full responsibility of the operation of the plantation from land
preparation to packing of the fruits.
There are two components of banana production. These are planting and
packing.
1. Planting
JJD Farms occupies a total land area of approximately 40
hectares broken down as follows: 38 hectares planted and 3 hectares
allocated for facilities and access road.
The company leased the land from various landowners in the
locality. In this scheme, the company takes the full responsibility of the
operation of the plantation from land preparation to packing of the
fruits. The objective of this scheme is to maximize the potential of the
land at minimum cost. This strategy is covered by a contract/agreement
that is binding between the Company and the landowners.
11
The activities done are typical of any agricultural undertaking –
planting, maintenance and harvesting. JJD Farms observed less
chemical farming. That is, supplementing the operation with chicken
dung and plant compost to reduce use of chemical fertilizer.
Planting, maintenance and harvesting are being done by the
contract workers. JJD Farms uses boom spray in lieu of aerial spraying
because of the terrain. Boom spraying is done daily. It is being
conducted in the morning between 5:30 a.m. and 9:00 a.m.
2.1.2 Sources of Materials
Majority of the materials to be used in the plantation such as
fertilizers, chemicals, plastics, and other inputs will be sourced locally.
2.1.3. Chemical Used
Due to the stringent requirement imposed by the global market
on the chemical residues on the fruits, JJD Farms regulated the use of
synthetic chemicals. Organic chemicals are being used to supplement
the former. Chicken dung and compost are used to supplement the
synthetic fertilizers like 14-14-14. Table 2.1 reflects the different
chemicals used in the plantation operation with the corresponding
dosage, method of application and the frequency of application.
Aside from using it in boom spray, dithiane is also used as bunch
spray at a concentration of 18.00 gram per gallon of solution. A bunch
is sprayed with 130 cc of solution at an interval of 4 to 5 sprays.
12
2.1.4. Buffer Zone
In compliance with the occupational health and safety standards,
a buffer zone of about 10 meters around the plantation will be
established and maintained throughout the operation of the plantation.
Spraying within the 10 meters buffer zone will be done manually.
Growers will be advised to do manual spraying.
2. Banana Packing
13
In the selection tank fine trimming of bunches and hands are
being done. Quality-check with respect to appearance and minute
damages. Bunches not passing the quality checks are also rejected.
While bunches passed the quality-check, are put in a tray, weighed and
packed. The standard packing weight is 13.5 kilograms per box.
Figure 2.2 shows the schematic diagram of packing bananas
Method of
Chemicals Concentration Application
1. Alum 10.00 grams/li of water Cascade
2. Chlorine 0.20 grms/li of water Cascade
14
2.2.3.Utilities
The water to be used in the process is ground water. Process
water is also recycled to save consumption and chemicals. Electricity is
being supplied by DANECO
15
CHAPTER 3: BASELINE CONDITIONS
3.1 Introduction
The dominant vegetation covers in the project area are coconut, grasses
and weeds, which are not rare species. The first provincial-wide survey of
Odonata was conducted in Compostela Valley Province (Comval).
Opportunistic and segmented line transect method was employed in all fluvial
systems visited between March and September 2014. A total of 2,883
individuals belonging to 12 families 24 genera and 32 species were recorded.
Seventeen (17) out of 32 species or 53% belongs to suborder Anisoptera
(dragonfly) while 15 species or 47% are Zygopterans. Compostela Valley
province exhibits 56% endemism, one of the highest endemism records in
Mindanao. An immediate conservation effort to fluvial systems containing
high endemism and species quality is recommended.
The project site is within an almost flat, alluvial plain that is generally
characterized by depression and natural levee or alluvial highs, which were
formed from fluvial action of an almost east-west trending ephemeral creek.
Elevation ranges from 20 to 40 meters. Tagsawa Creek is the main natural
drainage system traversing the property
16
3.3.1 Topography
17
3.3.3 Geology and soils
18
3.4.1 Demography
According to the 2015 Census, the age group with the highest
population in Concepcion is 15 to 19, with 819 individuals. Conversely, the
age group with the lowest population is 75 to 79, with 20 individuals.
Population Population
Age group Age group
(2015) (2015)
Under 1 64 40 to 44 186
1 to 4 339 45 to 49 191
5 to 9 455 50 to 54 139
10 to 14 448 55 to 59 109
15 to 19 819 60 to 64 75
20 to 24 376 65 to 69 51
25 to 29 371 70 to 74 40
30 to 34 328 75 to 79 20
35 to 39 260 80 and over 21
Total 4,292
19
3.4.2 Land Use and Socio-economic setting
The existing land use is agricultural. The area is planted to coconut,
banana and other cash crops.
3.4.3 Poverty
20
CHAPTER 4: LEGAL AND INSTITUTIONAL FRAMEWORK
The EIA study should abide to the requirements of the drafted terms of
reference. The proposed banana plantation and production facility should
also abide to the existing policies of Barangay Concepcion, Maco, Compostella
Valley.
21
CHAPTER 5: ANALYSIS OF ALTERNATIVES
No action alternative
Alternative site(s)
22
CHAPTER 6: PUBLIC PARTICIPATION AND SITE VISITS
6.0 Introduction
The proponents of the EIA study conducted a site visit last February
22, 2019. During the site visit a joint meeting was participated by Mr. John
Jerry L. Demelino of JJD Farms, the local government unit of Brgy.
Conception represented by the Brgy. Captain, the EIA proponents and some
residents of the barangay.
Discussion were made regarding the purpose of the proposed project
and the components and the activities during the land development and
operation of the project. Furthermore, the overall effect of the project to the
barangay, significant impacts to the environment, mitigating measures for the
significant impacts, and possible methods of environment monitoring during
operation phase was also discussed to the residents of the barangay.
The following are the documentations taken last February 22, 2019
during the proponents’ site visit and public consultation.
Figure 6.1: Ocular Inspection in the Area of the Proposed 40 Hectares Banana
Plantation with Production Facility (JJD Farms)
23
Figure 6.2: Existing Site Condition
24
Figure 6.3: Public Consultation
25
CHAPTER 7. PROJECTED IMPACTS AND MITIGATION MEASURES
Based on the site characterization made and on the process flow, the
potential impacts of the projects were identified. Each activity involved during
the land preparation, planting and packing were examined. The potential
emissions to the environment for each activity were determined and the
possible effects to the geophysical, socio-cultutral and biophysical
environment were identified. The summary of the impact identification is
presented in Table 7.1.
Water Pollution
1. Fertilizer and pesticide Uncontrolled surface run-off will pollute
applications. the water in Tagsawa creek.
26
Sources of Impacts Potential Environmental Impact
Solid Waste
1. Empty Chemical containers, Chemical containers and empty
fertilizer bags. fertilizer bags are hazardous since this
might contain chemical residues.
3. Papers and other office related Adds to the solid waste problem of the
wastes barangay.
Noise Pollution
1. Noise will be generated during land The noise level of the vicinity will
preparation and boom spraying of increase.
fungicides.
Chemical Application to Land Domesticated animals will be poisoned.
1. Unregulated application of
chemicals to land
Soil Degradation
1. Mono – culture practice and Render the soil infertile and deficient of
excessive use of fertilizer & minerals.
pesticides.
Socio-Economic
1. Increase value of adjacent property. Improvement of the quality of life.
2. More employment and livelihood The plantation could help (directly and
3. Increase of business enterprise. indirectly) solve the unemployment
4. Population growth due to migration. problem.
5. Reduction of surface area for
rainwater absorption Increase in population will result to
overcrowding. This is a negative impact.
Air Quality
During boom spraying, marginal and acute increase in the
concentration of fungicide residue in the vicinity is expected. The fungicide
residues pose greater risks to the residents and domestic animals in the
plantation sites. Incidence of skin diseases associated with the spraying of
fungicide is already established in other parts of the country. The fungicides
27
suspended in the air will contaminate the rainwater. Air suspended
particulate is also expected to increase associated with the hauling of fruits
and other farms implements. Carbon dioxide, carbon monoxide, oxides of
nitrogen and oxides of sulfur are also emitted to the atmosphere by the land
vehicles.
Water Quality
Earthworks in the project site such as soil grubbing although minimal
could loosen the soils and transport of these materials to surface waters would
result in the siltation of Tagsawa creek, which is the direct out-fall of
plantation drainage. Moreover, fertilizers that go with the surface run-off will
pollute the creek.
Noise
The operation of equipment during the site development and the boom
spraying will increase the noise level in the project site and its immediate
vicinity. The nuisance will be high considering the area is rural. However its
impact to human is not very significant because the immediate vicinity is
sparsely inhabited
Solid Waste
Vegetal wastes such banana trunks, leaves, flowers, etc constitute the
majority of the solid waste generated. Other solid wastes generated are plastic,
twine and empty containers of chemicals.
Other land contaminants include fuel that leaks from the vehicles and grease
used in the maintenance
Health Impact
Boom spraying of fungicide will endanger the health of the people living
within the plantation and in the vicinity. Fungicide residues will contaminate
the rainwater and the air. The direct health impacts will be skin irritation and
stomach upset from drinking contaminated rainwater. The method of
pesticide and fungicide application to the buds and fruits using knapsack is
also hazardous. The laborers administering the chemicals to bananas are
exposed. Health problems are associated with nausea, skin irritation, etc.
The laborers working in the packinghouse are also exposed to the risk
of chlorine and alum. Chlorine being a bleaching agent is a strong chemical.
It can damage skin. In addition, laborer tasked to prepare the solution will be
subjected to chlorine fumes, which is carcinogenic. The reaction of alum is
slightly acidic, hence it is corrosive. It can also cause skin irritation.
Socio-economic
The project will generate both positive and negative socio-economic
impacts. Definitely with the project, the value of the adjacent property is
expected to increase. The attractiveness of the site will be enhanced with the
improved road network, thus attracting more investors. The economic activity
will no longer be confined to agriculture specifically banana growing. Trading
and other enterprises will start to boom.
28
With improved economic status and road network, the residents will be
able to avail of services like health care, education and other social services.
The negative impact foreseen is the increase in population due to in-
migration. Overcrowding will become a problem. Problems associated to
overcrowding and increase in population such as crime, are anticipated to
rise.
The project will generate both negative and positive impacts. The
negative impacts as reflected in Table 7.3 are towards the physical
environment and human health. Water pollution is very likely to happen. The
source will be surface run-off contaminated with fertilizer. Air pollution from
boom spraying of fungicide is also a significant impact considering the area is
rural. Residues of the chemicals used in spraying will contaminate the air as
well as the rainwater.
29
Banana plantations generate a considerable volume of solid waste, both
organic and synthetic in nature. The impact is significant because of the
volume that will be generated. In addition, secondary impacts like health
problems are likely to occur. Soil degradation is a significant impact because
mono-culture is the farming system being practiced. Also, chemical inputs
such as fertilizer will eventually render the soil acidic. This impact is
irreversible. Most of the positive impacts are associated to economics –
increase in income, more government revenue, etc.
30
CHAPTER 8. ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
(ESMP) AND MITIGATING MEASURES
The project is already partially operating therefore, the impacts presented and
the mitigating measures are those expected in relation to the operation of
banana plantation. The management who is also the proponent of this study
will implement the mitigating measures for each negative impact. Table 8.1
presents the matrix of the environmental management plan to be adopted.
31
Potential Manner of
Environmental Mitigating Measures Implementation Schedule
Impacts
Unimpregnated plastic bag will plant for the
be recycled. vegetal waste.
Banana rejects will be
distributed to barangay folks to
be used as animal feed
supplement.
The company will establish
drop – off points of rejected
fruits to facilitate pick-up.
Banana trunks, leaves, flowers,
etc will be spread in the field for
decomposition. The compost
will be used to reduce the
synthetic potassium fertilizer.
Establish a compost plant
within the plantation to handle
vegetal wastes, which are very
difficult to decompose.
5. Noise Pollution Avoid simultaneous use of Management to During
due to heavy equipment ensure the proper project
operation of Maintain vehicle speed to 20 implementation. operation
packinghouse. kph
Maintenance of green belt zones
and vegetation
6. Traffic Con- Coordinate with the Barangay Management to During
gestion traffic management office. ensure the proper project
Increase resources so that implementation operation
congestion in primary roads is
reduced.
Putting up appropriate traffic
signs in strategic areas to avoid
traffic accidents.
7. Pop Increase Prohibition of residential Mgt to ensure the During
establishment within the strict project
plantation implementation operation
Coordinate with LGU on in-
migration control
8. Employment. The residents of the two Management to During
Barangays will be given the hire local labors. project
priority in the hiring of laborers. LGU officials operation.
should ensure
that local
constituents are
given priority.
9. Chemical Schedule of chemical Management to During
Poisoning application will be disseminated implement project
to the residents operation
The compound will be fenced
10. Environ-mental Management to provide Management to During the
and Health protective equipment such as ensure health and project
Hazard. chemical resistant gloves, safety of the operation.
mask, coverall goggles or face workers in the
shields, apron, etc to field field.
workers.
32
Potential Manner of
Environmental Mitigating Measures Implementation Schedule
Impacts
Observe dirty man in - clean
man out principles.
Provide wash rooms.
33
CHAPTER 9. CONCLUSIONS AND RECOMMENDATIONS
9.1 Conclusions
The use of the legal framework and technologies will enable the project
proponent to mitigate most of the serious environmental impacts identified by
the experts and the people living in the area. These technologies were
integrated into the designing of the plantation establishment.
9.2 Recommendations
Majority of the surrounding community has accepted the project. But they
are keen on the project activities because most of them are use water from
the sources which are located within the project site. Therefore, coordination
with the community is strongly recommended.
The monitoring program suggested in this EIA report should be complied with
extreme care and attention to ensure the effective implementation of
mitigation measures.
Taking all these factors into consideration, the EIA team suggested the project
subject to the effective implementation of the mitigation and monitoring plan.
34
REFERENCES
DAO 96-37
DAO 34
DAO 35
35
ANNEXES
36
37
38
39
40
A2. EIA Coverage and Screening Requirements Checklist
41
42
43
44
45
Chapter Assignments:
46