BCT Schedule start end

First Group (click to rename) 02/18/19 05/31/19


BCT Car Park 02/19 05/31 Project Team

Approval From Bowshar Municipality - Finished 02/18 02/25 Project Team


Approval for from Distrait Municipality - Applicat... 02/18 03/01 Project Team
Procurement of Structure - Completed 02/18 02/20 Procurement Team
Procurement of Inverter - Completed 02/18 02/20 Procurement Team
Procurement of PV Panels - Awaiting Confirmati... 02/18 02/20 Procurement Team
Commencement of Construction activity at site 03/01 03/31 Procurement Team
Arrival of Inverter at site 03/25 04/01 Procurement Team
Arrival of BOS at site 03/25 04/01 Procurement Team
Arrival of Modules at Site 04/15 04/20 Procurement Team
DC & AC Side Cables/Earthing/Lighting/LT Pane... 04/15 04/25 Installation Team
Installation of Invertor 04/25 04/30 Installation Team
Installation of PV Panels 04/15 04/30 Installation Team
Installing the Monitoring System 05/01 05/05 Installation Team
Pre commissioning and Testing 05/05 05/11 Design Team, Execution Team, Installation Team, Project Team
Commissioning approval from MEDC 05/10 05/15 Design Team, Execution Team, Project Team
Commissioning Of Project 05/15 05/20 Design Team, Installation Team, Project Team