0 Calendar of Activities

4.1 Deliverables and Milestone

4.1.1 Requirement Analysis

The group went to the community and conducted an observation and

survey. The data gathered was then analyzed and interpreted. The deliverable of

the requirement phase is the interpreted data collected through survey and the

research on the algorithms and theories that would be helpful for the study. The

delivery date is April 14, 2015.

4.1.2 Design

The design on the game world was based on the observation done during

the visit at community. The design of the objects that would serve as garbage was

also based on the garbage produced by the households. The design on the main

character was inspired by a boy scout. The deliverable of the design phase is the

game mechanics, game world and the model sheets for all the objects and

characters. The delivery date is May 10, 2015.

4.1.3 Implementation

The GUI is created and integrated into the system. The deliverable of the

implementation phase is the source code. The delivery date is July 20, 2015.
4.1.4 Testing

The deliverable of the alpha testing is the results of the tests done by the

researchers. These results include issues, errors, and bugs. The delivery date for

the alpha testing is July 30, 2015.

After the alpha test, the researchers installed and had the game tested by

the target end-users. The deliverable of the beta testing is the results of the

evaluation done by the target end-users. The delivery date for the beta testing is

August 14, 2015

4.1.5 Maintenance

The researchers organize a training session in order help the users utilize

the full functions and features of the game. The recommendation of the users is

the deliverable and also the update version and patches. The delivery date is

September 14, 2015.

4.2 Gantt Chart