by Maya Payne Smart

BOLTS
FROM
THE BLUE
Poorly managed economic
risks can strike down
projects at lightning speed.

54 PM NETWORK MAY 2010 WWW.PMI.ORG


MAY 2010 PM NETWORK 55
B
Beneath the gauzy layer of optimism basis. “You never plan beyond what you’ve
that the worst is over, danger lurks. got defined because the world is going to
Economic fortunes may be picking change,” Mr. Alleman says. “That’s the
up—but not everyone’s prepared for the only way to survive, and it drives the
risks resulting from the rollercoaster ride financial folks crazy. They have to figure
of change wrought by the recession. out how to live within this profile.”
No shocker here: Many of the Even governments aren’t immune to
threats are tied to the fickle financing project threats presented by new budget
sparked by the downturn. Scarce access crackdowns.
to capital and diminished cash flow “The [U.K.] Ministry of Defence
mean companies may not know where has a multibillion-pound budgetary
the money for projects is coming from, black hole, which it is trying to fix with
or when. Some projects are put on hold, a ‘save now, pay later’ approach,” Amyas
while others face shortened or Morse, head of the National Audit
stretched-out timelines. Office, said in a statement. “This gives
“I would say the number-one risk a misleadingly negative picture of how
that we face is instability of funding,” well some major projects in the
says Glen Alleman, vice president of pro- Ministry of Defence are managed, rep-
gram planning and controls at Lewis & resents poor value for the money and
Fowler, a project management consult- heightens the risk that the equipment
ing firm in Englewood, Colorado, USA. our armed forces require will not be
The volatility in budgets has forced available when it is needed or in the
shorter-term, iterative planning processes quantities promised.”
into play across many sectors.
Defense contractors, for one, have A NEW WAY OF THINKING
tackled the tumult with “rolling waves,” Cautiousness prevails even in places such
allocating budgets on a six- to nine-month as Australia that weren’t hit as hard by the

Savoir-Faire in Low Supply


Sometimes the risk comes from In some cases, companies are inexperience puts proper project
within, as talent shortfalls put com- turning to outside help. Aerospace execution at risk.
panies and their projects in danger. firms, for example, are increasingly “It’s a new way of doing things,”
In many parts of the world, there relying on contractors from engi- says Murtaza Hassanali, PMI-RMP,
are insufficient numbers of veteran neering or program management PMP, Integral Energy, Huntingwood,
project and program managers, consultancies. New South Wales, Australia.
says Glen Alleman, Lewis & Fowler, “What companies have done is “We’re entering a complex phase.
Englewood, Colorado, USA. spread their risk by having a smaller Intellectual property becomes your
“That’s a risk [because] the core cadre and then having specialty competitive edge, and that’s going to
younger managers are all very contracting firms,” Mr. Alleman be scarce. Rather than only relying on
smart, but they haven’t lived says. “Usually, it’s less expensive consultants, project managers are
through hard times or difficult pro- because they don’t have to pay working more collaboratively and
grams,” he explains. “They are retirement and other benefits.” finding new ways of solving problems.
lacking the experience about what In the energy sector, heightened “Some of the ways of operating
to do in the face of disaster. If you environmental consciousness has in this new era mean project teams
haven’t lived through one downcy- increased pressure on utility com- sometimes have to develop their
cle, you are always optimistic.” panies to deliver power more effi- own innovations. If a project man-
Younger project managers have ciently. Many electricity networks ager hits an obstacle, there is little
certainly learned some tough les- are being upgraded to a smart grid, opportunity to seek assistance and
sons recently, but it may not be and the needed expertise is only expertise from outside of his or
enough. just starting to mature. Simply put, her typical resource pool.”

56 PM NETWORK MAY 2010 WWW.PMI.ORG


MOUNT ROYAL UNIVERSITY
Continuing Education
>TIP (QYLVLRQ \RXU
Not everyone may IXWXUH
spot a danger point, VHH ZKDW
so be ready to make
your case. “If your RWKHUV GRQ·W
boss takes a stand and is
Project Management & Applied Project Management
immovable, that becomes a
constraint that you have to Earn a Project Management Certificate, classroom or online programs available. Curriculum based
work within,” says David on A Guide to the Project Management Body of Knowledge (PMBOK® Guide).
http://conted.mtroyal.ca/projectmanagement
Hillson, PhD, PMP, Risk
The Applied Project Management Certificate has been designed for Project Management
Doctor & Partners, Petersfield, Professionals (PMP®s) and graduates of the Project Management program who work in complex
project environments and wish to further develop their project management skills.
Hampshire, England. http://conted.mtroyal.ca/pmapplied
To secure executive buy-in
on a risk-management plan, PMP, PMBOK and the PMI Registered Education Provider logo are
registered trademarks of the Project Management Institute, Inc.
share case studies, show
how other organizations are Information: 403.440.8937
Toll-free 1.888.392.3655
handling similar situations or E-mail cebusiness@mtroyal.ca
and forward news stories www.mtroyal.ca/conted
that pertain to the economy
or other trends.

PM
financial crisis, says Murtaza Hassanali,
PMI-RMP, PMP, IT program manager,
Integral Energy, Huntingwood, New
South Wales, Australia.
“It’s not that there is a lack of funding,”
he says, “but [companies] are very conser-
vative in how they spend their capital.”
That stance brings longer invest-
ment decision-making and heightened
monitoring.
When you plan a project based on
historical experiences, you might base
it on a three-month timeline, for
example. But now it takes twice as long Take Advantage of PM Network’s Pass-Along Value!
to accommodate “stronger stakeholder
engagement, emphasis on business Have you found an article in PM Network® you’d like to use as
change and transformation to cater to a presentation tool? Would you like to distribute a project
the new thinking in investments,” Mr. management article as part of a newsletter? Contact the
Hassanali says. Project Management Institute (PMI) for information on reprinting
The rules have changed. articles (pmipub@pmi.org) and permission to distribute them
“We’re entering a new phase after (permissions@pmi.org).
the global financial crisis where there

MAY 2010 PM NETWORK 57


one on guard. Project managers and
their teams must look far beyond the
Running the traditional confines of their proj-
ects—yet such a wide view doesn’t
Risks always come easy.
“Project managers tend to deny that
Here’s a rundown of what to risk will occur on their projects,” says
watch out for this year, according David Hulett, PhD, president, Hulett &
to the World Economic Forum:
Associates, a project risk consultancy in
> Economic Risks Los Angeles, California, USA. “But if
pressed about risks, they will generally
Oil price spikes
focus on technical and engineering risks
Major fall of the U.S. dollar
because they often come from an engi-
Slowing Chinese economy
neering background. Technical risks are
Asset price collapse
often some of the least important risks
Retrenchment from globalization
to a project.”
Burden of regulation
Too many project managers are
Underinvestment in infrastructure
silent, oblivious or in denial when it
> Geopolitical Risks comes to other risks, particularly exter-
nal or organizational ones, that can
Transnational crime and corruption
affect project outcomes. “They are
International terrorism
smart enough to recognize them,” he
Nuclear proliferation
says. “They just don’t think about them
Global governance gaps
very often.”
> Environmental Risks It’s up to program and portfolio man-
agers to get project managers thinking.
Extreme weather
They should also be on the lookout for a
Water scarcity
possible whitewash. “Often, project
Natural catastrophes
managers are biased in wanting their
Air pollution
project to look good to management and
Biodiversity loss
customers, so they whitewash the project
> Societal Risks risk by denying it may occur or by down-
playing risks’ significance to the project,”
Pandemics and diseases
Migration
says Dr. Hulett.
Those at the top level need to coor-
> Technological Risks dinate communication and action
among all the project players affected,
Critical information
infrastructure breakdown says David Hillson, PhD, PMP, Risk
Data fraud/loss Doctor & Partners, Petersfield, Hamp-
shire, England.
SOURCE: GLOBAL RISKS 2010 All too often, project managers are
left to uncover major risks on their
own when others within their organi-
are less existing textbook approaches zation could have proffered warnings.
or expert knowledge available,” he “Project management is an increas-
says. “When you talk about dealing ingly mature discipline with a proven
with the new environment or new risk track record and because it is succeed-
mitigation, you have to combine what ing people are pushing it to do more,”
you learned in school with experi- he says.
ences and new innovative methods.” There are limits, however.
To truly master the altered risk “I would be resistant to breaching the
environment, companies need every- project scope boundary,” Dr. Hillson says.

58 PM NETWORK MAY 2010 WWW.PMI.ORG


“ofThe effectiveness
risk management
is very patchy.
The key indicator
is whether people
are being proactive
or reactive. The
majority of project
managers are still
in reactive mode.
—David Hillson, PhD, PMP

Project managers shouldn’t have to such as planning issues, as well as exter-
worry about how other business deci- nal risks, such as regulatory shifts.
sions will affect their organization as a Brainstorming around the various
whole. If, for example, a new business is sources of risk to identify and categorize
acquired, they can’t be concerned about risks in greater detail helps project man-
risks to the relevance, funding and agers develop more sophisticated views
staffing of a given project. of the context in which their projects
“Business managers should com- succeed or fail. Oftentimes, bringing in
municate downward to project man- outside experts with varying discipli-
agers, ‘Here’s what’s happening, how nary backgrounds results in a more
it affects you and what I want you to inclusive list of potential risks. Project
do,’” Dr. Hillson says. managers may also benefit from main-
Such efforts may require significant taining checklists of risks encountered
time and several meetings, though in in similar projects, Dr. Hulett says.
many cases a simple policy directive Threats don’t always fall into neat
will suffice. Dr. Hillson recently wit- categories that can be fully predicted
nessed a senior management team send or controlled, of course, but that’s no
project managers a new set of guide- excuse for a lack of due diligence.
lines after it recognized the implica- “The effectiveness of risk management
tions of a country’s political shift for its is very patchy,” says Dr. Hillson. “The key
projects. indicator is whether people are being
A risk breakdown structure can also proactive or reactive. The majority of proj-
help project managers think more broad- ect managers are still in reactive mode.”
ly about potential problems—examining Companies that can’t change that
endemic project management risks, philosophy may be in danger. PM