RENCANA ANGGARAN BIAYA

PEKERJAAN

PEMBANGUNAN RUMAH TINGGAL 1 LANTAI TYPE -36


PERUMAHAN GRIYA ZAFIRA CIRUUM
DESA MANGKURAKYAT KECAMATAN CILAWU KABUPATEN GARUT

BANDUNG
TAHUN 2015
REKAPITULASI

RUMAH TINGGAL 1 LANTAI GRIYA ZAFIRA CIRUUM


TYPE - 36

NO URAIAN PEKERJAAN JUMLAH HARGA (RP)

1 2 3

I PEKERJAAN PERSIAPAN 3,390,000.00


II PEKERJAAN GALIAN TANAH DAN PASIR 838,755.00
III PEKERJAAN STRUKTUR BETON 5,927,870.00
IV PEKERJAAN PASANGAN 11,952,100.00
V PEKERJAAN KUSEN PINTU/JENDELA 3,612,500.00
VI PEKERJAAN LANTAI DAN DINDING 5,291,525.00
VII PEKERJAAN PLAFOND 3,240,750.00
VIII PEKERJAAN RANGKA KUDA - KUDA DAN PENUTUP ATAP 7,523,750.00
IX PEKERJAAN ALAT PENGGANTUNG KUNCI & KACA 1,233,000.00
X PEKERJAAN PENGECATAN 4,940,035.00
XI PEKERJAAN INSTALASI LISTRIK 2,350,000.00
XII PEKERJAAN INSTALASI AIR BERSIH DAN KOTOR 3,215,000.00

A) JUMLAH 53,515,285.00
B) JASA KONSTRUKSI 10 % 5,351,528.50
C) GRAND TOTAL 58,866,813.50
D) DIBULATKAN 58,866,000.00
TERBILANG : LIMA PULUH DELAPAN JUTA DELAPAN RATUS ENAM PULUH ENAM RIBU RUPIAH

NB : PEKERJAAN TIDAK TERMASUK


PENYAMBUNGAN LISTRIK ( PLN )
PENYAMBUNGAN AIR BERSIH ( PDAM )
IJIN BANGUNAN
RENCANA ANGGARAN BIAYA ( RAB )

RUMAH TINGGAL 1 LANTAI GRIYA ZAFIRA CIRUUM


TYPE - 36

HARGA SAT. JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SAT.
Rp. Rp.
1 2 3 4 5 6

I PEKERJAAN PERSIAPAN
1 Pas. Bouwplank 34.00 m1 35,000.00 1,190,000.00
2 Direksi keet 12.00 m2 100,000.00 1,200,000.00
3 Pengadaan Listrik dan Air Kerja 1.00 ls 1,000,000.00 1,000,000.00

JUMLAH PEK. I 3,390,000.00

II PEKERJAAN GALIAN TANAH DAN PASIR


1 Pek. Galian tanah pondasi batu kali 28.69 m3 20,000.00 573,750.00
2 Urugan tanah kembali 15.07 m3 6,000.00 90,405.00
3 Urugan pasir bawah pondasi batu kali tb: 5 cm 1.15 m3 60,000.00 68,850.00
4 Urugan pasir bawah lantai tb: 5 cm 1.76 m3 60,000.00 105,750.00

JUMLAH PEK. II 838,755.00

III PEKERJAAN STRUKTUR BETON


1 Pek. Sloof beton 15/20, K-175 1.15 m3 1,500,000.00 1,721,250.00
2 Pek. Kolom beton praktis uk. 15/15 cm, (KP), K-175 0.95 m3 1,400,000.00 1,323,000.00
3 Pek. Ring balk beton 15/20 cm (RB), K-175 1.34 m3 1,500,000.00 2,002,500.00
4 Pek. Plat lantai beton tb: 10 cm, K-225 0.50 m3 1,600,000.00 800,000.00
5 Pek. Canopy beton tb: 8 cm, K-175 0.06 m3 1,300,000.00 81,120.00

JUMLAH PEK. III 5,927,870.00

IV PEKERJAAN PASANGAN
1 Pas. Pondasi batu belah (1:5) 10.71 m3 150,000.00 1,606,500.00
2 Pas. Bata merah 1 : 3 18.21 m2 60,000.00 1,092,600.00
3 Pas. Bata merah 1 : 5 90.75 m2 50,000.00 4,537,500.00
4 Plester & Acian dinding 1 : 3 36.42 m2 25,000.00 910,500.00
5 Plester & Acian dinding 1 : 5 181.50 m2 20,000.00 3,630,000.00
6 Plester & ban-banan dinding 5.00 m2 35,000.00 175,000.00

JUMLAH PEK. IV 11,952,100.00

V PEKERJAAN KUSEN PINTU/JENDELA


1 Pek. Kusen pintu 5/14 kayu 0.15 m3 2,500,000.00 382,500.00
2 Pas. Daun pintu double tripleks 6.40 m2 150,000.00 960,000.00
3 Pas. Kusen jendela alumunium 5.40 m2 200,000.00 1,080,000.00
4 Pas. Daun jendela kaca rangka alumunium 4.20 m2 200,000.00 840,000.00
5 Pas. Pintu PVC Kamar Mandi/ Wc 1.00 bh 350,000.00 350,000.00

JUMLAH PEK. V 3,612,500.00

VI PEKERJAAN LANTAI DAN DINDING


1 Pas. Lantai keramik 30 x 30 cm putih polos 37.25 m2 95,000.00 3,538,750.00
2 Pas. Lantai keramik 20 x 20 cm km/wc (Corak/Warna) 2.78 m2 85,000.00 235,875.00
3 Pas. Dinding Keramik 20 x 25 cm km/wc (Corak/Warna) 8.41 m2 90,000.00 756,900.00
4 Pas. Floor Acian Lantai Carport / Parkir Mobil 9.50 m2 80,000.00 760,000.00

JUMLAH PEK. VI 5,291,525.00


VII PEKERJAAN PLAFOND
1 Pek. Rangka Plafond Kayu 50 x 70 mm 37.25 m2 50,000.00 1,862,500.00
2 Pas. Plafond GRC tb: 4 mm 37.25 m2 25,000.00 931,250.00
3 Pas. List Plafond Kayu C-5 cm 44.70 m1 10,000.00 447,000.00

JUMLAH PEK. VII 3,240,750.00

VIII PEKERJAAN RANGKA KUDA - KUDA DAN PENUTUP ATAP


1 Pas. Kuda - Kuda Baja Ringan 37.75 m2 110,000.00 4,152,500.00
2 Pas. Multi Roof 37.75 m2 65,000.00 2,453,750.00
3 Pas. Bubungan Multi Roof 6.00 m1 45,000.00 270,000.00
4 Pas. Listplank GRC 12.00 m1 35,000.00 420,000.00
5 Pas. Ban plesteran spesi 1 : 3, antara genting dan dinding 3.50 m2 65,000.00 227,500.00

JUMLAH PEK. VIII 7,523,750.00

IX PEKERJAAN ALAT PENGGANTUNG KUNCI & KACA


1 Pas. Kunci pintu double slag ex. Standart 4.00 bh 95,000.00 380,000.00
2 Pas. Engsel pintu H cabut ex. Standart 8.00 bh 35,000.00 280,000.00
3 Pas. Engsel Jendela Kupu-Kupu 6.00 bh 15,000.00 90,000.00
4 Pas. Hak angin jendela Type Kait 6.00 bh 20,000.00 120,000.00
5 Pas. Slot jendela ex. Standart 6.00 bh 15,000.00 90,000.00
6 Pas. Kaca polos bening t= 3 mm 4.20 m2 65,000.00 273,000.00

JUMLAH PEK. IX 1,233,000.00

X PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding, Kolom dan Listplank beton 222.92 m2 18,000.00 4,012,560.00
2 Pek. Pengecatan Plafond 37.25 m2 17,500.00 651,875.00
3 Pek. Pengecatan kusen pintu 7.38 m2 20,000.00 147,600.00
4 Pek. Pengecatan daun pintu 6.40 m2 20,000.00 128,000.00

JUMLAH PEK. X 4,940,035.00

XI PEKERJAAN INSTALASI LISTRIK


1 Pek. Pasang instalasi titik lampu 10.00 ttk 75,000.00 750,000.00
2 Pek. Pasang instalasi titik stop kontak + saklar standar (1 Phase) 12.00 ttk 75,000.00 900,000.00
3 Pas. Lampu TL 18 watt ex. Standart + armatur 9.00 bh 50,000.00 450,000.00
4 Pas. Stop Kontak ex. Standar 5.00 bh 25,000.00 125,000.00
5 Pas. Saklar Ganda ex. Standar (1 Phase) 2.00 bh 25,000.00 50,000.00
6 Pas. Saklar Tunggal ex. Standar (1 Phase) 5.00 bh 15,000.00 75,000.00

JUMLAH PEK. XI 2,350,000.00

XII PEKERJAAN INSTALASI AIR BERSIH DAN KOTOR


A Pekerjaan Instalasi Air di Luar Bangunan
1 Pas. Pipa Pvc 3/4'' dari sumber air ke bangunan 12.00 m1 12,000.00 144,000.00
2 Pas. Stop Kran 3/4'' ex. Standar 1.00 bh 15,000.00 15,000.00
B Pekerjaan Instalasi Air di Dalam Bangunan
1 Pas. Pipa Pvc 1/2'' dalam bangunan 12.00 m1 8,000.00 96,000.00
2 Pas. Kran 1/2'' ex. Standar 2.00 bh 20,000.00 40,000.00
3 Pas. Closet Jongkok ex. Standar 1.00 bh 850,000.00 850,000.00
4 Pas. Floor Drain ex. Standar 1.00 bh 30,000.00 30,000.00
5 Pas. Pipa Pvc 3'' ex. Standar 12.00 m1 45,000.00 540,000.00
C Pekerjaan Lain - Lain
1 Pek. Pasang Bak Mandi 1.00 ls 300,000.00 300,000.00
2 Pek. Pasang Septictank 1.00 ls 1,200,000.00 1,200,000.00

JUMLAH PEK. XII 3,215,000.00