Anda di halaman 1dari 7

SPE 60734

Composite Coiled Tubing Solution


Terry R. Wheaton, Scott A. Berning, Dick Headrick, Mike Feechan, Clint Isennock, Halliburton Energy Services, Inc.;
Stewart H. Fowler, Fiberspar, Inc. Spoolable Products

Copyright 2000, Society of Petroleum Engineers, Inc. A simulation suggested that replacing the steel heater string
This paper was prepared for presentation at the 2000 SPE/ICoTA Coiled Tubing Roundtable with a fiberglass or CCT material with low heat loss values
held in Houston, Texas, April 5-6.
(thermal conductivity 1.92 Btu/hour/ft2-in./°F) could be a solu-
This paper was selected for presentation by an SPE Program Committee following review of tion. This method would not require any changes to the surface
information contained in an abstract submitted by the author(s). Contents of the paper, as
presented, have not been reviewed by the Society of Petroleum Engineers and are subject to equipment.
correction by the author(s). The material, as presented, does not necessarily reflect any
position of the Society of Petroleum Engineers, its officers, or members. Papers presented at
SPE meetings are subject to publication review by Editorial Committees of the Society of Validation
Petroleum Engineers. Permission to copy is restricted to an abstract of not more than 300
words. Illustrations may not be copied. The abstract should contain conspicuous acknowledg- To validate the simulation and prove that a heater string with
ment of where and by whom the paper is presented. Write Librarian, SPE, P.O. Box 833836,
Richardson, TX 75083-3836, U.S.A, fax 01-972-952-9435.
composite properties would be the solution, operators ran a
temperature log while the steel tubing string was being used and
the well was flowing. When the temperature log was compared
Abstract with the simulated results [allowing for the thermal conductivity
Depending on the application, composite coiled tubing (CCT) of steel (77.8 BTU/hour/ft2-in./ °F)], the results were compa-
may serve as a cost-effective alternative to conventional coiled rable (Fig. 2, Page 4).
tubing.1 Heater-string inlet parameters were as follows:
Gas wells in Alberta, Canada often lose production when • flow rate 16.0 gal/min
hydrates form as a result of temperature drops in gas flow. To • pressure 600 psi
reduce gas-flow temperature drop and prevent hydrates from • temperature 167°F
forming, operators commonly use a steel heater string to heat the With this information, well operators investigated the de-
annular area between the production tubing and casing. Some sign of a heater string with composite properties.
wells require more heat to reach the critical hydrate temperature
depth than others, resulting in higher costs for heating and Design Considerations
pumping equipment. The OD of any heater string would have to fit easily into the area
To reduce these costs, operators looked for a solution to between the 2 7/8-in. tubing and 7-in. casing (ID 5.9 in.). This
temperature drop, and found it in CCT. Because of its low annular space was effectively 1 ½ in. (Fig. 3, Page 4). The
thermal conductivity (heat loss), a CCT heater string can reduce minimum ID of the heater string would have to be 1 in. to
the need for upgrading or replacing surface heating and pumping maintain the required pump rate of 16 gal/min.
equipment. Fiberglass jointed tubing was considered for use, but for
fiberglass tubing to maintain a 1-in. ID, the OD of the tool joints
Introduction has to be larger than 1 ½ in. Fiberglass jointed tubing would not
In one study, continuous hydrate problems occurred in a newly fit into the annular area. Seeking another solution, operators
completed gas well in Alberta when the well was producing at its decided to test CCT.
potential (Fig. 1, Page 4). Operators inserted a 1 ¼-in. outer
diameter (OD) steel CT string into the annulus of the well to a CCT Design
depth of 4,593 ft. They then pumped water heated to 167°F down Because composite coiled tubing can be manufactured to any
the string to heat the flow of gas above 80°F, the temperature at specification, a final OD of 1.37 in. was chosen, with the ID
which hydrates form. The steel CT failed to retain enough heat remaining at 1 in. This OD would allow operators to easily install
to prevent hydrate problems. The only way operators could the string (Table 1, Page 3).
produce the well was to increase the pump rate and reduce gas The CCT string would have to withstand an operating
flow. An alternative to this costly approach would have been to pressure of 3,000 psi and a temperature of 180°F. Although there
upgrade the heating equipment, but that, too, would have been was no required compression on the string, a value of –5,000 lb
expensive.

References at the end of the paper.


2 COMPOSITE COILED TUBING SOLUTION SPE 60734

was used for design criteria, based on the possibility that the Results
string might have to be pushed into the annular area. Operators used the same injector to pull the steel tubing and run
The tensile load required to install the string was estimated the CCT string. This operation took 8 hours, including the
at 2,600 lb in air and 1,200 lb in water. For the design criteria, a nipple-down and nipple-up of the wellhead and flowlines
value of 5,000 lb was required to provide additional overpull if (Fig. 6, Page 6). Operators then heated the annular area to
it was needed. operational temperature by circulating water heated to 167°F at
16 gal/min down the string and back to the surface, and the well
Testing was put into production.
After it was manufactured, the CCT string was tested at 78°F for The well’s production (Fig. 7, Page 6) was increased in the
burst pressure and axial loading (Fig. 4, Page 5). In manufacturer’s following four increments over 6 days:
tests with no axial load, the burst pressure was 12,500 psi. With • 1.7 MMscf/D (0.5 MMscf/D above the previous production
no internal pressure, the composite string failed at an 8,500-lb rate)
axial load. • 2.1 MMscf/D
During testing, the manufacturer ran a 30-ft section of the
string in and out of the injector chains five times (five cycles) and
• 2.5 MMscf/D
pull-tested it to 5,000 lb. In addition to testing the tubing itself, • 2.8 MMscf/D (maximum allowable production rate)
this procedure also verified the integrity of the hangoff connector A temperature log was run 1 day after the well reached a
that would be used in the actual installation. production level of 1.7 MMscf/D to confirm that the temperature
During the manufacturer’s test, the pull-test clamp damaged drop through the composite heater string and flowing gas tem-
a 1-in. area of the 30-ft composite section. Because such failures perature remained comparable to that of the steel heater string.
could occur again when the heater string was actually installed The composite heater string provided a temperature differ-
and hung off, this same damaged string was later used in field ential increase above the steel string of 59°F at 4,593 ft, and
testing. increased the flowing gas temperature by 39°F at the surface
The 30-ft section (including the damaged area) was cut off (Fig. 8, Page 7). The final result was a continuous flow from the
the string and pressurized to the point of failure. The string failed well without hydrate problems, and production that more than
in the damaged area at 10,500 psi. doubled—from 1.25 MMscf/D to 2.85 MMscf/D. Because of
This testing provided the data required to ensure that the the new production level, the overall cost of the operation was
composite string met the necessary design specifications. recovered in less than 3 months.

Equipment Required for Installation Acknowledgments


Operators installed the CCT heater string in the well without The authors thank Chris Bruggencate, a student at University of
using special equipment or modifying existing equipment. British Columbia, who was employed by Petro-Canada Oil and
Because the string was installed in an isolated annulus with Gas as a summer student during this project. Chris performed
a downhole packer and a column of water, operators did not have and validated the temperature simulations that made this project
to contain pressure at the surface with a blowout preventer possible.
(BOP) or stripper.
The injector was equipped with V™ blocks ranging from 1- References
in. CT to 1 ¾-in. CT, so the unusual OD size of 1 3/8 in. required 1. Koshak, W.E, Feechan, M., Berning, S., Headrick, D., and
no special blocks or injector chains. Hampton, F.: “A Summary of Recent Successes and Challenges
in the Development of Spoolable Composite Tubulars,” paper
SPE/ICoTA 54506, presented at the 1999 SPE/ICoTA Coiled
Hangoff Connector Tubing Roundtable, Houston, May 25-26.
The CCT connector required for the hangoff was designed from
an external steel CT slip connector with an internal mandrel
added to support the external slip when it was tightened. The top
of the connector had a box thread where the wellhead hangoff
mandrel could be installed. This reusable connector could be
installed in the field. Because the connector did not have to be
installed in the wall of the composite string when it was manufac-
tured, the string could be set at a different depth during operation,
if needed. This connector also reduced hangoff time and re-
quired no specially designed wellhead equipment
(Fig. 5, Page 5).
SPE 60734 T. R. WHEATON, S. A. BERNING, D. HEADRICK, M. FEECHAN, C. ISENNOCK, S.H. FOWLER 3

Table 1—Installed Composite Coiled Tubing (CCT) Specifications


Physical Properties
Geometry
Outside diameter (in.) 1.372
Inside diameter (in.) 1
2 0.79
Inside flow area (in. )
Wall thickness (in.) 0.19
Linear weight
Air (lb/ft) 0.56
Water (lb/ft) 0.26
Specific gravity 1.86
2 192
Thermal conductivity (Btu/hr/ft -in/°F)
Resin tubing temperature 257°F
Mechanical Performance
Pressure Room Max. Operating
Temp. Temp.
(78°F) (180°F)
Maximum operating (psi) 3,000 3,000
Nominal ultimate burst (psi) 10,140 8,580
Nominal ultimate tensile load (lb) 6,533 4,583
Nominal ultimate compressive load (lb) -7,118 -5,168
Nominal utimate collapse pressure (psi) 2,800 2,050
Minimum operating bend radius (in.) 38 38
4 COMPOSITE COILED TUBING SOLUTION SPE 60734

om002600
Fig. 1—Well production before the composite coiled tubing heater string was installed.

om002602
Fig. 3—The annular area where the heater string had to be in-
stalled.
om002601

Fig. 2—Temperature log results comparing actual to simulated


with the steel coiled tubing heater installed.
SPE 60734 T. R. WHEATON, S. A. BERNING, D. HEADRICK, M. FEECHAN, C. ISENNOCK, S.H. FOWLER 5

om002603
Fig. 4—Test results and operating envelope of the composite coiled tubing heater string (analysis temperature 78°F).

om002604

Fig. 5—Composite coiled tubing hangoff connector and hangoff mandrel.


6 COMPOSITE COILED TUBING SOLUTION SPE 60734

om002605
Fig. 6—Field operations.

om002606

Fig. 7—Well production after the composite coiled tubing heater string was installed.
SPE 60734 T. R. WHEATON, S. A. BERNING, D. HEADRICK, M. FEECHAN, C. ISENNOCK, S.H. FOWLER 7

Fig. 8—Actual results vs. simulated results with the composite coiled tubing heater string installed. om002607

Anda mungkin juga menyukai