Review
a r t i c l e i n f o a b s t r a c t
Article history: This paper is a second of two presenting a review of research results in underground cable transmis-
Received 4 November 2014 sion obtained by the Department of Energy Technology, Aalborg University ET/AAU and Danish TSO
Received in revised form 12 May 2016 Energinet.dk within the last six years. The main core of the results are obtained by PhD students research-
Accepted 27 May 2016
ing electrical engineering topics related to using underground cables for power transmission at EHV level
Available online xxx
and including the 420 kV level. The research topics were laid down by ET/AAU and Energinet.dk in the
DANPAC (DANish Power systems with Ac Cables) research project. The main topics are discussed on the
Keywords:
basis of 39 references published by ET/AAU and Energinet.dk.
Underground cable transmission
Time domain simulations
Part I of the paper explains the events that lead to the research project, reactive power compensation,
Electromagnetic transients modelling for transient studies, including field measurements and improvements to the existing models,
Cable modelling and temporary overvoltages due to resonances.
Insulation coordination Part II covers transient phenomena, harmonics in cables, system modelling for different phenomena,
Fault location main and backup protections in cable-based networks, online fault detection and future trends.
© 2016 Elsevier B.V. All rights reserved.
Contents
1. Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
2. Transient phenomena . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
2.1. Cable energisation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
2.2. Zero-missing phenomenon . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
3. Harmonics in cable based systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
4. Cable system modelling and harmonic studies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
4.1. Modelling depth . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
4.1.1. Switching phenomena . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
4.1.2. Resonance phenomena . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
4.2. Systematic method for simulating switching transients . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
5. Protection of cable systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
5.1. Main protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
5.2. Backup protection – ground loop impedance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
5.3. Summary of protection of cable systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
6. Fault location in cable based transmission network . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
6.1. Introduction to fault location in cable-based transmission networks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
6.2. Methods for online fault locations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
6.2.1. Impedance-based method for fault location . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
6.2.2. Travelling wave-based fault location methods . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
6.2.3. Design of a fault locator for cross-bonded cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
6.2.4. Verification and accuracy of fault locator . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00
∗ Corresponding author.
E-mail address: clb@et.aau.dk (C.L. Bak).
http://dx.doi.org/10.1016/j.epsr.2016.05.035
0378-7796/© 2016 Elsevier B.V. All rights reserved.
Please cite this article in press as: C.L. Bak, F. Faria da Silva, High Voltage AC underground cable systems for power transmission – A
review of the Danish experience: Part 2, Electr. Power Syst. Res. (2016), http://dx.doi.org/10.1016/j.epsr.2016.05.035
G Model
EPSR-4719; No. of Pages 10 ARTICLE IN PRESS
2 C.L. Bak, F. Faria da Silva / Electric Power Systems Research xxx (2016) xxx–xxx
Please cite this article in press as: C.L. Bak, F. Faria da Silva, High Voltage AC underground cable systems for power transmission – A
review of the Danish experience: Part 2, Electr. Power Syst. Res. (2016), http://dx.doi.org/10.1016/j.epsr.2016.05.035
G Model
EPSR-4719; No. of Pages 10 ARTICLE IN PRESS
C.L. Bak, F. Faria da Silva / Electric Power Systems Research xxx (2016) xxx–xxx 3
1 1
0.5 0.5
Current [pu]
Current [pu]
0 0
-0.5 -0.5
-1 -1
0 0.005 0.01 0.015 0.02 0.025 0.03 0.035 0.04 0.045 0.05 0 0.005 0.01 0.015 0.02 0.025 0.03 0.035 0.04 0.045 0.05
Time [s] Time [s]
Fig. 2. Currents during the energisation for 75% reactive power compensation. Left: Switching at zero voltage (0◦ ); Right: Switching angle of 70◦ ; Dashed-dotted line: AC
current in the cable; Dotted line: AC Current in the shunt reactor; Dashed line: DC current in the shunt reactor; Solid Line: Total current through the circuit breaker.
equal to zero for a switching at peak voltage. The time constant 1000
1980 kV
depends on the system resistance and inductance.
Fig. 2 shows the energisation of a cable with 75% of reactive 800
power compensation for two different switching angles. The cable
Voltage [kV]
is switched for zero voltage in the first case, resulting in maximum 600
DC component and it has zero-missing, as the DC component is
larger than the AC. In the second case, a switching angle of 70◦ 400
is used and zero-missing is no longer present. Several counter-
measures can be used to avoid zero-missing. The reactive power 200
compensation may be done by more than one shunt reactor with
less than 50% of the reactive power being compensated by a shunt 0
0 5000 10000 15000
reactor connected directly to the cable, and the rest by shunt reac- Frequency [Hz]
tors connected via a circuit breaker. This approach is especially
suitable for long cables requiring compensation in the order of Fig. 3. Voltage at cable receiving end for a 134.5 kV peak voltage at the cable sending
end. Solid line: Both-ends bonding; Dashed line: One major-section; Dotted line:
several hundreds of MVar. However, this may not always possible,
Two major-sections.
because of the rated capacitive switching current values of circuit
breakers and the voltage rise limits [17].
Pre-insertion resistor in the circuit breaker [18] or a resistance and minimum magnitude also shift and are for different frequen-
in series with the shunt reactor [2] can damp the DC component cies. As the number of major-sections increases, this effect becomes
in one cycle. However, the former increases the costs of the circuit more visible as observed in Fig. 3.
breaker, whereas the latter increases the losses. A method for the
calculation of the ideal value of the pre-insertion resistor in function 4. Cable system modelling and harmonic studies
of the cable is available in [18]. If single-phase circuit breakers are
available, synchronised switching may be applied and the switch- 4.1. Modelling depth
ing angle selected so that the DC component is inferior to the AC
component [2,19]. The modelling depth, i.e., the number of busbars behind the node
of interest included in the simulation model, may have a strong
influence on the simulation results. Ideally, the model would con-
3. Harmonics in cable based systems tain as many busbars as possible, however, this would be too time
consuming both when setting up the model and when running the
The resonance frequency is lower for cables than for OHLs of simulation.
equal length, because of the larger capacitance of the former. As As a result, modelling guidelines suggesting a required mod-
a result, the excitation of the resonance points by low frequency elling depth would be helpful. The detail level depends on the
harmonics is more likely to occur in a cable-based network than phenomenon under study [2,16] and it can be separated into two
in an OHL-based network, and it may result in TOVs. However, it main groups: Switching phenomena and resonance phenomena.
is important to refer that the X/R ratio of a cable can be an order
of magnitude lower than the X/R ratio of an equivalent OHL [20], 4.1.1. Switching phenomena
which results in a larger damping at the resonance point, when Several possibilities exist for simulating the switching transient
compared with a resonance at a same frequency in an OHL. of a cable. The cable may be connected to a lumped equivalent
The cable bonding influences both the magnitude and the fre- source, which typically overestimates the overvoltage [1] and does
quency of the resonance points. Fig. 3 shows the voltage at the not show accurate waveforms, as it does not consider the prop-
receiving end of a cable in function of the frequency for two bond- agation of the waves into the adjacent lines. The inclusion of the
ing configurations: both-ends bonding and cross-bonding with one surrounding area in the model improves the accuracy. The standard
major section. The behaviour of a cable with both ends bonded is [22] suggests including only the network of same voltage level up
similar to an OHL: a constant decrease in magnitude of the parallel to one or two busbars behind the node of interest, with the rest of
resonance points as the frequency increases. One cross-section is the network being modelled by an equivalent Thévenin. Although
sufficient to change this behaviour. The resonance frequency shifts it is a good rule, this method is not accurate for all cases, mainly
and more resonance points appear, due to the bonding at the minor not when energising a long cable surrounded by shorter cables or
sections [21]. These points are characterised by a low magnitude for OHLs. For such cases, the method described in [23] can be used to
both parallel and resonance frequencies. The points of maximum decide the modelling depth.
Please cite this article in press as: C.L. Bak, F. Faria da Silva, High Voltage AC underground cable systems for power transmission – A
review of the Danish experience: Part 2, Electr. Power Syst. Res. (2016), http://dx.doi.org/10.1016/j.epsr.2016.05.035
G Model
EPSR-4719; No. of Pages 10 ARTICLE IN PRESS
4 C.L. Bak, F. Faria da Silva / Electric Power Systems Research xxx (2016) xxx–xxx
In normal conditions, the largest overvoltage during the tran- The drawback of this method is the need for a reference detailed
sient occurs at the receiving end of the cable being energised, network model. For example, [26] already had a full model of the
assuming no resonances. Typically, it corresponds to the moment 400 kV French grid in EMTP-RV which used to obtain the FDNE. Such
when the wave generated at switching reaches the receiving end of detailed models may not exist or it may be too time consuming to
the cable for the second time. In other words after being reflected develop them for a project. Moreover, the process is not always
at the receiving end and posteriorly at the sending end of the cable, direct and vector fitting techniques must be used [25].
happening in a total time corresponding to 3, where is the trav- Another possibility is to use an empirical approach consisting
elling time of the coaxial mode in the cable. of:
Depending on the relative lengths of the cable being energised
and the neighbour cables/OHLs, the transient voltage waves that
• Designing a detailed system up to a distance of two or three bus-
propagate in the surrounding cables/OHLs at switching can be
bars from the point of interest and use an equivalent network
reflected at the end of the cable/OHL and/or bonding sections. It is
(50/60 Hz) for the rest of the grid;
then refracted to the cable being energised and reach its receiving
• Repeating the previous point, but increasing the modelling depth
before a time period of 3, influencing the peak overvoltage.
of the detailed area in one busbar;
The simulation model is divided into three zones, each with dif-
• Comparing the frequency spectrums for both systems;
ferent levels of modelling detail. The first area includes the nodes
• Repeating the process until the difference between the spectrums
close to the busbar of interest, it is modelled in detail using FD-
is minimum around the frequencies of interest;
models and it contains all minor cross-sections if present. This level
of detail is required because of the reflections at the end of the
minor-sections and at the end of the cables/OHLs, which may reach The simulation of a cable requires more computation time than
the receiving end of the cable being energised before a period of 3. the simulation of an OHL and this process may be time consuming
The area contains all the lines reached in a period of time equal to if many cables are included in the model. A possible adaption of this
by a wave travelling at intersheath-mode speed. The second area method for grids or areas with a large number of cables is suggested
continues to use FD-models, but it is not necessary to include all in [16]. Here, the model is divided in two levels of detail, a first
the cross-bonded sections, it is sufficient to consider one major- level close to the area of interest using FD-models for the cables
section. This area contains all the lines reached in a period of time and/or OHLs and a second level using lumped-parameters models
equal to by a wave travelling at the coaxial-mode speed. connected to the equivalent network.
The third and last area represents the cables and/or OHLs by The first iteration considers one/two busbars depth with FD-
means of lumped parameters models and it has a modelling depth models and three or more with lumped-parameters. The model
of one busbar, and is then connected to an equivalent network. Fig. 4 continues to be augmented until the frequency scan stops changing.
shows an example of the three areas. This approach allows having FD-models only for the cables close to
the point of interest, reducing the computational time.
The theoretical origin of the resonance frequencies have been
4.1.2. Resonance phenomena thoroughly studied in [27] and a derivation of theoretical formulas
An exact estimation of the frequency and magnitude of the res- of the frequency component contained in the overvoltage related
onance points are necessary for a proper assessment of the TOV to long EHV cables is developed. This method is proven to agree
[24]. Ideally, frequency scans of the network would be available and very well with EMTP type simulation results, Fig. 5.
the admittance of the equivalent network would be modelled by a
Frequency-Dependent Network Equivalents (FDNE). For practical
reasons this is not normally possible, and approximations must be 4.2. Systematic method for simulating switching transients
made using simulation models.
One possible method is to design a detailed network model and A systematic method for the simulation of switching transients
to extract the frequency domain response of the node(s) of interest is given in [5]. The method divides the phenomena into resonance
which is fitted into a rational-function model of appropriate order and switching phenomena, with the latter subdivided into energi-
to obtain the FDNE [25]. A practical example of the use and accuracy sation and de-energisation; the modelling of which also depends
of this method is given in [26]. on the network configuration and connected equipment.
Please cite this article in press as: C.L. Bak, F. Faria da Silva, High Voltage AC underground cable systems for power transmission – A
review of the Danish experience: Part 2, Electr. Power Syst. Res. (2016), http://dx.doi.org/10.1016/j.epsr.2016.05.035
G Model
EPSR-4719; No. of Pages 10 ARTICLE IN PRESS
C.L. Bak, F. Faria da Silva / Electric Power Systems Research xxx (2016) xxx–xxx 5
Please cite this article in press as: C.L. Bak, F. Faria da Silva, High Voltage AC underground cable systems for power transmission – A
review of the Danish experience: Part 2, Electr. Power Syst. Res. (2016), http://dx.doi.org/10.1016/j.epsr.2016.05.035
G Model
EPSR-4719; No. of Pages 10 ARTICLE IN PRESS
6 C.L. Bak, F. Faria da Silva / Electric Power Systems Research xxx (2016) xxx–xxx
Fig. 6. Compensated ground loop impedance (left and middle) and k0 (right) for cross-bonded cables with one major section [29].
Table 1
Largest discontinuity of ground loop reactance at cross-bonding points (cable with one major section) [29].
Cable layouts (1) Flat w/o transposition (2) Flat w transposition (3) Trefoil (4) Tunnel
zone setting, it causes an error in the calculation of the ground loop k0 . Since this difference will affect the calculated ground loop
impedance, see Fig. 6, right. impedance, it is necessary to know which phase conductor ground-
Furthermore, grounding practice at the substation and end of ing was selected for the field measurements of Zl0 [33]. It is clear
the major section together with cable laying (formation) play a role from Fig. 7 and Table 2 that knowledge of the actual substation
for the variations in the ground loop impedance. This is described grounding design is necessary in order to be able to model the
by analysing two layouts by means of measurements. The ground- EMTP type simulations correctly. This means that phase conduc-
ing of phase conductors is close to the grounding of cable heads in tor grounding (1) is more appropriate for the field measurements
phase conductor grounding (1). As shown in the lower left of Fig. 7, of Zl0 , considering that the value is used for the impedance relay
the sheath return current can go back to the source without going setting. If the field measurements are conducted with phase con-
through the substation grounding resistance in this case. In con- ductor grounding (2), the results need to be modified using EMTP
trast, the grounding of phase conductors is far from the grounding simulations [29]. If we consider a cable consisting of several major
of cable heads in phase conductor grounding (2). As shown in the sections, i.e. a cable of a length 5–10 fold of one major section, the
lower right of Fig. 7, the sheath/earth return current needs to go discontinuous impedance becomes less predominant when com-
through the substation grounding resistance in this case [33]. pared to a shorter cable. This is illustrated in Fig. 8 by assessing
It is therefore expected that Zl0 obtained by the setup with phase the impedance of the 500 kV 40 km Shin-Toyosu cable line in Japan
conductor grounding (1) has a smaller real part. Table 2 compares [29]. As can be seen from Fig. 8, the longer the cable, the less pro-
Zl0 and k0 with the substation grounding resistance 1 ohm. It is nounced the discontinuities, and the measured (as by a distance
known that Zl1 is not affected by the phase conductor grounding relay) impedance looks almost linear, leading to the conclusion
or substation grounding resistances, but this is also shown in the that distance protection can be applied without communication
table just to confirm it. The calculation results show that the phase for cables of a reasonable length. The actual operation of the pro-
conductor grounding has a significant effect on both Zl0 and tection relays with regards to the dynamic behaviour of cable based
Please cite this article in press as: C.L. Bak, F. Faria da Silva, High Voltage AC underground cable systems for power transmission – A
review of the Danish experience: Part 2, Electr. Power Syst. Res. (2016), http://dx.doi.org/10.1016/j.epsr.2016.05.035
G Model
EPSR-4719; No. of Pages 10 ARTICLE IN PRESS
C.L. Bak, F. Faria da Silva / Electric Power Systems Research xxx (2016) xxx–xxx 7
Please cite this article in press as: C.L. Bak, F. Faria da Silva, High Voltage AC underground cable systems for power transmission – A
review of the Danish experience: Part 2, Electr. Power Syst. Res. (2016), http://dx.doi.org/10.1016/j.epsr.2016.05.035
G Model
EPSR-4719; No. of Pages 10 ARTICLE IN PRESS
8 C.L. Bak, F. Faria da Silva / Electric Power Systems Research xxx (2016) xxx–xxx
Fig. 9. 245 kV electrical connection of the Anholt offshore wind farm [47].
Fig. 10. Modal velocities for first minor section of the Anholt cable evaluated from 1 Hz to 1 MHz. C denotes coaxial modes, I denotes Intersheath ECC modes and G denotes
the ground mode [47].
frequencies above 10 kHz, and, at the same time, they are faster 200
Measured core voltage at Joint 0 and 33
than intersheath and ground modes. This makes the initial fault 100
Measured voltage Joint 0
wave approaching a fault location device inherently being a coax- Measured voltage Joint 33
Voltage [V]
0
ial wave and a common wave velocity can be used for all three -100
phases and be independent of the fault location all along the entire -200
length of cable. -300
A validated method for measuring the electromagnetic pulse -400
propagation velocity to be used for fault location is presented in -6 -4 -2 0 2 4 6
(a) Time [ms]
[47]. The method relies on injecting a 3 kV lightning surge from
-240 -220
a portable lightning surge generator. It is shown to be sufficient
to conduct sending end voltage and current measurements with -260 -240
Voltage [V]
Voltage [V]
terminal method can be written as (b) Time [µs] (c) Time [µs]
Fig. 11. (a) Low resolution zoom of the core voltage at Joint 0 and 33 after a single
phase to sheath fault is applied at Joint 27, (b) high resolution of the core voltage at
l − (A − B ) · vC
x= (1) Joint 33 and (c) at Joint 0 [38].
2
Please cite this article in press as: C.L. Bak, F. Faria da Silva, High Voltage AC underground cable systems for power transmission – A
review of the Danish experience: Part 2, Electr. Power Syst. Res. (2016), http://dx.doi.org/10.1016/j.epsr.2016.05.035
G Model
EPSR-4719; No. of Pages 10 ARTICLE IN PRESS
C.L. Bak, F. Faria da Silva / Electric Power Systems Research xxx (2016) xxx–xxx 9
Fig. 12. Fault locator system for fault location in cross-bonded cable systems [51].
Table 3
Obtained accuracy of fault location system for cross-bonded cable [38].
Fault Cable length Fault location Fault location Fault location Fault location
resistance [] [km] error at 5% [m] error at 35% [m] error at 60% [m] error at 90% [m]
0 18 37 30 28 43
36 56 50 41 61
60 85 75 60 81
10 18 39 31 28 42
36 60 54 43 63
60 86 85 61 84
6.2.4. Verification and accuracy of fault locator 8. Future trends in cable transmission systems
Three 150 kV cross-bonded cable systems with lengths of 18 km,
36 km and 60 km are implemented in PSCAD/EMTDC. Single core At the time of submission (autumn 2014), several papers report
to sheath to ground faults are applied at 5%, 35%, 60% and 90%. All a progress in both the intentions of installing underground cables,
minor sections are 2 km long, resulting in cable systems with three, onshore and offshore as well as the actual installed systems. An
six and ten major sections. The model details can be found in [38]. example is the Cigré 2014 General session, where SC B1 holds 33
The fault resistance varies from 0 to 10 and the fault inception publications within isolated cables. Many obstacles have been over-
angle is set as 45◦ , 55◦ and 90◦ . The sheath currents measured at come by research carried out by the research community so far, but
both ends are used as input to the fault locator system. The obtained as cable transmission systems are still in their youth, operational
accuracy for 45◦ is shown in Table 3. experience as well as continued research uncovers needs for fur-
ther research in the years to come. Some key research issues are
identified as:
6.3. Summary of fault location methods for cross-bonded cables
• Three phase submarine cables, modelling of losses. It is of major
Cross-bonded cable systems pose challenges as compared to
interest to be able to assess the losses of a submarine cable for
overhead lines with respect to locating faults. This is shown to
e.g. network connection of an offshore wind farm. Present loss
be overcome by using a two-terminal synchronised fault location
calculation models overestimate losses[53,54] when compared
system, employing a semi-manual assessment of automatically
with the reference IEC standard [55], which in turn leads to an
recorded travelling waves from each end of the line. Such a system
overly expensive cable installation, making the widespread use
has an even better accuracy compared to already existing systems
of offshore wind power less favourable.
used for overhead lines [52].
• Resonance forming in large interconnected transmission
networks employing comprehensive share of cables. Both series
7. Conclusions and parallel resonances can form unintendedly and become
excited by transmission voltage harmonics originating from
The overall conclusions are that underground cables for power HVDC converters and other sources.
transmission is both a possible and very good solution, although a • Transmission cable system maintenance and assessment of esti-
number of technical issues highly different from their counterparts mated lifetime. As more and more transmission lines become
for overhead lines must be complied with in the design phase. For undergrounded, there will be a need for being able to assess
underground transmission cables of a realistic length, it is recom- the fidelity of these “invisible” and difficult to access power sys-
mended to follow a design practice such as for instance described tem components in order to plan maintenance and replacement
in Cigré Power System Technical Performance Issues Related to the philosophies as well as to ascertain reliability.
Application of Long HVAC Cables: Cigré Technical brochure WG
C4.502, Cigré 2013 [2]. Proper time domain simulations must be Acknowledgements
conducted to reveal switching as well as the electrical behaviour of
lightning and it must be borne in mind that lightning overvoltage Danish TSO Energinet.dk is acknowledged for providing funding
actually can enter parts of the transmission system above ground for 5 PhD students and supervision of numerous masters’ student
and enter into cables and their connection to substations. thesis works as well as having always played a very professional
This review paper, part 1 and part 2 have covered the main role in researching the topics of undergrounding the transmis-
challenges when facing a governmental decision to underground sion system. The opportunity to perform real measurements upon
almost the entire transmission system. transmission cable systems during their installation has been of
Please cite this article in press as: C.L. Bak, F. Faria da Silva, High Voltage AC underground cable systems for power transmission – A
review of the Danish experience: Part 2, Electr. Power Syst. Res. (2016), http://dx.doi.org/10.1016/j.epsr.2016.05.035
G Model
EPSR-4719; No. of Pages 10 ARTICLE IN PRESS
10 C.L. Bak, F. Faria da Silva / Electric Power Systems Research xxx (2016) xxx–xxx
especially great value in validating the findings and methods of the [26] Y. Vernay, B. Gustavsen, Application of Frequency-Dependent Network Equiv-
research conducted. alents for EMTP Simulation of Transformer Inrush Current in Large Networks,
IPST, 2013.
The PhD students are acknowledged for enabling a major [27] T. Ohno, C.L. Bak, A. Ametani, W. Wiechowski, T.K. Sørensen, Derivation of the-
research success in each of the individual research works con- oretical formulas of the frequency component contained in the overvoltage
ducted. Finally, Dr. Wojciech Wiechowski for having grasped the related to long EHV cables, IEEE Trans. Power Deliv. 17 (April) (2012).
[28] C.L. Bak, C.F. Jensen, Distance Protection of Cross-Bonded Transmission Cable-
challenge from the beginning of the project and made possible the Systems, DPSP, 2014.
progress by involving Energinet.dk. [29] T. Ohno, C.L. Bak, T.K. Sørensen, Ground loop impedance of long EHV cable lines,
in: Western Protective Relay Conference, 2012.
[30] A. Khanna, Application of Differential Protection to Long Power Cables – Cable
References Modelling and Charging Current Compensation Methods, DPSP, 2014.
[31] B. Kasztenny, I. Voloh, J.G. Hubertus, Applying distance protection to cable
[1] T. Ohno, Dynamic Study on the 400 kV 60 km Kyndbyværket – Asnæsværket circuits, in: 57th Annual Conference for Protective Relay Engineers, 2004.
Line (PhD thesis), Aalborg University – Department of Energy Technology, 2012. [32] R. Benato, L. Caciolli, Sequence impedances of insulated cables: measurements
[2] W.G. Cigré, C4.502, Power System Technical Performance Issues Related to the versus computations, IEEE-PES T&D, 2012.
Application of Long HVAC Cables, Cigré, 2013. [33] G. Ziegler, Numerical Distance Protection, Principles and Application, 3rd edi-
[3] A.I. Ibrahim, H.W. Dommel, A Knowledge Base for Switching Surge Transients, tion, Siemens Publicis Corporate Publishing, 2008.
IPST, 2005. [34] G. Ziegler, Numerical Differential Protection, 1st edition, Siemens Publicis Cor-
[4] W.G. Cigré, 13.02, Switching Overvoltages in EHV and UHV Systems with Spe- porate Publishing, 2005.
cial Reference to Closing and Reclosing Transmission Lines, Electra, 1973. [35] C.L. Bak, M. Sztykiel, S. Dollerup, Line differential protection scheme modelling
[5] F. Faria da Silva, C.L. Bak, Electromagnetic Transients in Power Cables, 1st edi- for underground 420 kV cable systems, EMTDC/PSCAD relays modelling, in:
tion, Springer, 2013. International Protection Testing Symposium, 2011.
[6] D.J. Wilcox, K.J. Lawler, Transient phenomena in crossbonded cable systems: [36] M. Sztykiel, C.L. Bak, S. Dollerup, Line differential protection scheme modelling
analytical results, Proc. IEE 125 (10) (1978). for underground 420 kV cable systems, J. Energy Power Eng. (2011).
[7] F. Faria da Silva, C.L. Bak, P.B. Holst, Switching Restrikes in HVAC Cable Lines [37] IEEE Std 1234-2007, IEEE Guide for Fault Locating Techniques on Shielded
and Hybrid HVAC Cable/OHL Lines, IPST, 2011. Power Cable Systems, 2007.
[8] N. Nagaoka, A. Ametani, Transient calculations on crossbonded cables, IEEE [38] C.F. Jensen, Online Location of Faults on AC Cables in Underground Transmission
Trans. Power Apparat. Syst. 102 (4) (1983). Systems, Aalborg University – Department of Energy Technology, 2013 (PhD
[9] T. Ohno, C.L. Bak, A. Ametani, W. Wiechowski, T.K. Sørensen, Statistical distri- thesis).
bution of energization overvoltages of EHV cables, IEEE Trans. Power Deliv. 28 [39] S.H. Kang, J.K. Park, S.W. Min, S.R. Nam, W.K. Park, Fault Location Algorithm for
(July (3)) (2013). Underground Power Cables Using Analytical Method, Cigre Session, 2006.
[10] T. Oh, A. Ametani, C.L. Bak, W. Wiechowski, T.K. Sørensen, Analysis of the Sta- [40] S.-H. Kang, S.-W. Min, S.-R. Nam, J.-K. Park, Fault location algorithm for cross-
tistical Distribution of Energization Overvoltages of EHV Cables and OHLs, IPST, bonded cables using the singularity of the sheath impedance matrix, Electr.
2013. Eng. 89 (7) (2007) 525–533.
[11] IEEE Std. C37.12-2005, IEEE Application Guide for Capacitive Switching for AC [41] C.K. Junk, J.B. Lee, X.H. Wang, Y.H. Song, A Study on the Fault Location Algorithm
High-Voltage Circuit breakers, 2005. on Underground Power Cable System, IEEE-PES GM, 2005.
[12] F. Faria da Silva, C.L. Bak, Energization of long HVAC cables in parallel – analysis [42] C.K. Jung, J.B. Lee, Fault Location Algorithm on Underground Power Cable Sys-
and estimation formulas, Electr. Power Syst. Res. 96 (March) (2013). tems Using ISE Cancellation Technique IEEE-PES T&D, 2008.
[13] J. Kessel, V. Atlason, C.L. Bak, J. Lund, Lightning simulation of a combined [43] C.F. Jensen, U.S. Gudmundsdottir, C.L. Bak, State of the Art Analysis of Online
overhead line/cable connected GIS, in: International Conference on Lightning Fault Location on AC Cables in Underground Transmission Systems, NORD-IS,
Protection, 2008. 2011.
[14] C.L. Bak, J. Kessel, V. Atlason, J. Lund, Risk assessment of 170 kV GIS connected [44] D.A. Tziouvaras, J. Needs, Protection of Mixed Overhead and Underground Cable
to combined cable/OHL network, in: Nordic Insulation Symposium, 2009. Lines, DPSP, 2014.
[15] R. Benato, D. Napolitano, State-space model for availability assessment of [45] L.W. Wedepohl, D.J. Wilcox, Transients analysis of underground power-
EHV-UGC mixed power transmission link, Electr. Power Syst. Res. 99 (June) transmission systems – system-model and wave-propagation characteristics,
(2013). Proc. IEE 120 (2) (1973).
[16] F. Faria da Silva, Analysis and Simulation of Electromagnetic Transients in HVAC [46] W.G. Cigré, C4.501, Guideline for Numerical Electromagnetic Analysis Method
Cable Transmission Grids (PhD thesis), Aalborg University – Department of and Its Application to Surge Phenomena, Cigré, 2013.
Energy Technology, 2011. [47] C.F. Jensen, U.S. Gudmundsdottir, C.L. Bak, A. Abur, Field test and theoretical
[17] IEC 32271-100, High-Voltage Switchgear and Controlgear – Part 100: High- analysis of electromagnetic pulse propagation velocity on crossbonded cable
Voltage Alternating-Current Circuit Breakers, Edition 1.1, 2003. systems, IEEE Trans. Power Deliv. 29 (June) (2014).
[18] F. Faria da Silva, C.L. Bak, U.S. Gudmundsdottir, W. Wiechowski, Use of a [48] Christian.F. Jensen, O.M.K.K. Nanayakkara, A. Rajapakse, U.S. Gudmundsdot-
Pre-insertion Resistor to Minimize Zero-Missing Phenomenon and Switching tir, C.L. Bak, Online Fault Location on AC Cables in Underground Transmission
Overvoltages, IEEE-PES GM, 2009. Systems Using Screen Currents, IPST, 2013.
[19] F. Faria da Silva, C.L. Bak, U.S. Gudmundsdottir, W. Wiechowski, M.R. [49] C.F. Jensen, K. Nanayakkarab, A. Rajapakse, U.S. Gudmundsdottir, C.L. Bak,
Knardrupgård, Methods to minimize zero-missing phenomenon, IEEE Trans. Online fault location on AC cables in underground transmission systems using
Power Deliv. 25 (October) (2010). sheath currents, Electr. Power Syst. Res. 115 (October) (2014).
[20] W.G. Cigré, B1.30, Cable Systems Electrical Characteristics, Cigré, 2013. [50] A. Borghetti, S. Corsi, C.A. Nucci, M. Paolone, L. Peretto, R. Tinarelli, On the use of
[21] F. Faria da Silva, C.L. Bak, P.B. Holst, Study of Harmonics in Cable-based Trans- continuous-wavelet transform for fault location in distribution power systems,
mission Networks, Cigré Session, 2012. Electr. Power Energy Syst. 28 (2006).
[22] IEC 60071-4 Insulation Co-ordination – Part 4: Computational Guide of Insula- [51] C.F. Jensen, U.S. Gudmundsdottir, C.L. Bak, Online Fault Location on Cross-
tion Co-ordination and Modelling of Electrical Networks, 2004. bonded AC Cables in Underground Transmission Systems, Cigré Session, 2014.
[23] F. Faria da Silva, C.L. Bak, P.B. Holst, Estimation of the required modeling depth [52] C.F. Jensen, Online Location of Faults on AC Cables in Underground Transmission
for the simulation of cable switching in a cable-based network, IEEE Trans. Systems, Springer Theses Series, 2014.
Power Deliv. 27 (October) (2012). [53] D. Palmgren, J. Karlstrand, G. Henning, Armour Losses in Three-Core Submarine
[24] F. Palone, M. Rebolini, S. Lauria, M. Schembari, J. Vassallo, Frequency Domain XLPE Cables, Jicable, 2011.
Studies for the Malta-Sicily Interconnector, Cigré Session, 2014. [54] M.M. Hatlo, J.J. Bremnes, Current Dependent Armour Loss in Three-Core Cables:
[25] U.D. Annakage, N.K.C. Nair, Y. Liang, A.M. Gole, V. Dinavahi, B. Gustavsen, T. Comparison of FEA Results and Measurements, Cigré Session, 2014.
Noda, H. Ghasemi, A. Monti, M. Matar, R. Iravani, J.A. Martinez, Dynamic sys- [55] IEC 60287-1-1, Electric Cables – Calculations of the Current Rating – Part
tem equivalents: a survey of available techniques, IEEE Trans. Power Deliv. 27 1-1 Current Rating Equations (100% Load Factor) and Calculation of Losses,
(January) (2012). 2006.
Please cite this article in press as: C.L. Bak, F. Faria da Silva, High Voltage AC underground cable systems for power transmission – A
review of the Danish experience: Part 2, Electr. Power Syst. Res. (2016), http://dx.doi.org/10.1016/j.epsr.2016.05.035