PT.

SUPERKRANE MITRA UTAMA


PELALAWAN - RIAU

INSTALLATION ARRANGEMENT AGREEMENT


PRECAST CONCRETE WORKS FOR VANILLA PHASE 1 PROJECT
Revision_01
ORGANIZED OR SET UP
CHARGED BY
BY
NO DESCRIPTION REMARKS
CONTRACT PURCHASE CONTRACT PURCHASE
OR R OR R

1 ARRANGEMENT OF MILL SITE


1.1 Access to Mill Site X X
1.2 Access to erection location and maintenance X X
1.3 Enterance guarding X X
1.4 Contractors temporary facilities area
a) Availability X X
b) Cleaning X X
1.5 Common Areas
a) Preparation X X
b) Cleaning X X
1.6 Site Security X X X X General Security by Purchaser
1.7 Temporary Facilities
a) Offices X X
b) Toilets X X
c) Canteen ( meals ) X X
d) Warehouse X X
e) Clinic X X
1.8 Parking for Heavy Equipment X X
1.9 Fire Fighting during erection & Production X X X X
2.0 Access permit X X
2 SUPPLY, TRANSPORT & HANDLING MATERIAL
2.1 Provide Bench Mark and Reference Line X X
2.2 Provide Permanent Material and Consumable at Job Site
- Concrete X X
- Reinforced bar X X
- Wire Mesh X X
- Mortar for Screading X X
- Waterproofing Membran SIKA or Fosroc X X
- Non Shrink grout X X
- Mortar Grout X X
- Dowels incl. expansion joints X X

1 of 4
ORGANIZED OR SET UP
CHARGED BY
BY
NO DESCRIPTION REMARKS
CONTRACT PURCHASE CONTRACT PURCHASE
OR R OR R

- Raw material for embeded include dowel conduit ( GSA ) X X


- Strand Low Lak 1/2" X X

- Precast bed accessories: such AS conical jaw, conical brush, form oil etc X X

- STEEL Supporting for temporary support arrangement X X


Supply by Purchaser, Cost by
- Fuel X X X X Contractor for equipment in
contractors scope
2.3 Unloading and storing material at location X X
2.4 Protection during storage at location X X
2.5 Survey, alignment and inspection X X X X Inspection by Purchaser
2.6 Temporary Power :
a) Main installation X X
Checking and acceptance by
b) Connection to Main Installation X X
Purchaser within 100 m
c) Power supply at designated point X X
d) Power distribution incl. panels X X
e) Power distribution cabinets for tools X X
Checking and acceptance by
f) Official checking & Control of electrical installation X X X
Purchaser
2.7 Water :
a) Drinking water X X
b) Supply Water for construction at designated point X X
2.8 Tools X X
3 SUPPLY OF SUPPERVISION, MANPOWER, TOOLS AND EQUIPMENT
3.1 Providing of supervision and manpower to perform the job X X
Spinning & Viscose Building
3.2 Equipment for handling and fabrication works :
a) All cranes capacity included qualified operator, lub. oil & maintenance X X
b) All trailer capacity included qualified operator, lubricating oil & maintenance X X
c) Providing and supervision all access and area for crane during fabrication X X
d) Cables, slings, ropes, chains, shackles etc for all crane capacity X X
e) Stressing Machine Jack X X
3.3 Equipment for erection works :
a) Cranes below 50T capacity included qualified operator, lub. oil & maintenance X X
b) Cranes above and 50T included qualified operator, fuel, lubricating oil & maintenance X X
c) All trailer capacity included qualified operator, lubricating oil & maintenance X X
d) Providing and supervision all access and area for crane during construction X X
e) Cables, slings, ropes, chains, shackles etc for crane below 50T capacity X X
f) Cables, slings, ropes, chains, shackles etc for crane above 50T capacity X X

2 of 4
ORGANIZED OR SET UP
CHARGED BY
BY
NO DESCRIPTION REMARKS
CONTRACT PURCHASE CONTRACT PURCHASE
OR R OR R

Spinbath & Pipe Rack Building


3.4 Equipment for handling and fabrication works :
a) Cranes below 50T capacity included qualified operator, lub. oil & maintenance X X
b) Cranes above and 50T included qualified operator, fuel, lubricating oil & maintenance X X
c) Trailer capacity 40Tand below included qualified operator, fuel, lubricating oil & maintenance X X Standart trailer L=12 M
d) Trailer above 40T included qualified operator, fuel, lubricating oil & maintenance X X
e) Cables, slings, ropes, chains, shackles etc for crane 50T capacity and below X X
f) Cables, slings, ropes, chains, shackles etc for crane above 50T capacity X X
g) Stressing Machine Jack X X
3.5 Equipment for erection works :
a) Cranes below 50T capacity included qualified operator, lub. oil & maintenance X X
b) Cranes above and 50T included qualified operator, fuel, lubricating oil & maintenance X X
c) Trailer capacity 40Tand below included qualified operator, fuel, lubricating oil & maintenance X X
d) Trailer above 40T included qualified operator, fuel, lubricating oil & maintenance X X
e) Providing and supervision all access and area for crane during construction X X
f) Cables, slings, ropes, chains, shackles etc for crane below 50T capacity X X
g) Cables, slings, ropes, chains, shackles etc for crane above 50T capacity X X
3.6 Quality Inspection and Assurance X X X X
4 COMMUNICATION
Purchaser to assist to getting
4.1 Telephone X X X
telephone line
Purchaser to assist to getting
4.2 Telex and Fax X X X
telephone line
Purchaser to assist to getting
4.3 Mail X X X
telephone line
Contractor provide Jamsostek
5 INSURANCE X X X X and insurance for equipment
supplied by contractor
6 GENERAL
6.1 Lighting
a) Outside general mill site lighting X X
b) Construction area lighting X X X X
6.2 Safety Inspection X X X X
6.3 Construction Inspection X X X X
6.4 Cleaning of Construction areas
a) Waste cleaning X X
Disposal area shall be provided
b) Waste Removal X X by Purchaser within project
area, max 1 km
7 ENGINEERING , QUALITY CONTROL, HSSE & CONSTRUCTION
7.1 Drawing for Constuction X X 3 copy for Contractors

3 of 4
ORGANIZED OR SET UP
CHARGED BY
BY
NO DESCRIPTION REMARKS
CONTRACT PURCHASE CONTRACT PURCHASE
OR R OR R

7.2 Shop Drawing X X


7.3 as Built Drawing X X
7.4 Work Methode X X Approval by Purchaser
7.5 Safety and Quality Plan X X Approval by Purchaser

8 ENGINEERING COMUNICATION SHEET


8.1 Request for Information to Purchaser X X
8.2 Site Instruction / Construction Manager Instruction ( CMI ) X X
8.3 NCR X X X
8.4 Daily , Weekly, Monthly Report Progress X X