PROJECT: EPC TO INSTALL TWO (2) TURBOGENERATOR IN SUBSTATION BARINAS I - CORPOELEC WEEKLY REPORT No.

62
PES - DERWICK CONTRACT No: NA (PES Proposal No T-1003) FROM 29-Apr-13
TO 5-May-13

PROJECT SUMMARY SUMMARY PER ACTIVITIES


DESCRIPTION % PAST WEEK % ADVANCE % Progress Expected End Date
1.- Project Progress: EPC 98.03%, Engineering 100.00%, Procurement 99.99% and Construction 96.79%. Barinas EPC 98.01% 98.03% 0.02% 19-Jul-13
2.- Conduits Installation in Progress. ENGINEERING 100.00% 100.00% 0.00%
3.- BOPs cables pull, fix, testing & termination in progress. CIVIL 100.00% 100.00% 0.00%
4.- Pipe and supports painting in progress. MECHANICAL 100.00% 100.00% 0.00%
5. Fabrication of Cable tray in GSU 2 in progress ELECTRICAL 100.00% 100.00% 0.00%
6. Modification of GSU´s Fire Protection System in progress CONT & INST 100.00% 100.00% 0.00%
7.- CTG 100´s Control Room cables labelling in progress PROCUREMENT 99.99% 99.99% 0.00%
8.- Doors installation in progerss in Water Treatment Building and Switchgear Building MECHANICAL 99.99% 99.99% 0.00%
9.- Lighting System installation inside and oustide of Water Treatment Building in progress. ELECTRICAL 100.00% 100.00% 0.00%
10. Manual station for Fire Protection System installation in progress (unloading area) CONT & INST 100.00% 100.00% 0.00%
11.- Alignment of pumps for Raw Water System STRUCTURAL 100.00% 100.00% 0.00%
12.- Commisioning in progress CONSTRUCTION 96.77% 96.79% 0.02% 19-Jul-13
13.- P&W MVSW2 maintenance in progress (Derwick) BOP 96.72% 96.74% 0.02% 17-Jun-13
CTG's 100 &200 99.06% 99.06% 0.00% 11-Jun-13
COMISS. & START UP 3.14% 3.61% 0.47% 3-Jul-13

OUTSTANDING EVENTS
ENGINEERING

NOTES:
Attachments
a) EPC Schedule
b)Engineering Schedule
PROCUREMENT c)Procurement Schedule
Waiting for arrival of GSU2 LV terminations material from USA d) Construction Schedule
Water Well Pump Pipes receaved at site. e) Primary Float Path
Cable 500Kmcm brought to site. f) "S" Curve (EPC, Engineering, Procurement and Construction)
g) EHS / SIAHO statistic

CONSTRUCTION
1.-P&W MVSW2 in hold for connection and testing.
2.- GSU2 Dress up in hold

CORRECTIVE ACTIONS

EHS / SIAHO
Attached PES - EHS / SIAHO Statistic