Total numbers of questions = 25 Duration: 30min
Each questions contains 2marks for correct answer and -1 marks for wrong answer.
Questions
1 Cover blocks used should be…………..
a) Same grade of Concrete c) Higher grade of concrete
b) Lower grade of concrete d) Non of These
2 Dimensions of the modular concrete block shall not be differ more than …………………. for height.
a) ±1.5mm c) ±5.0mm
b) ±2.5mm d) All of these
3 Variation in vertical for cast-in-situ/bored concrete pile is………..
a) 1 in 100 c) 1 in 150
b) 1 in 200 d) All of these
4 Bentronite suspensions used to maintain …………………………….of borehole.
a) Stability c) Dimension
b) Depth d) Non of These
5 The weight of the cuttting edge shall not less than …………….. Per meter length.
a) 20 kg c) 30 kg
b) 40 kg d) All of these
6 Before pouring the concrete, formwork Panels must be
a) Cleaned c) Gap plugging
b) Application of form oil / oiling d) All of These

7 If strata below the founding level is hard rock , which type of pile will be preffered?

a) friction pile c) a & b


b) end bearing pile d) All of these
8 Maximum height of fall for concreting, if slump is collapse
a) 1.5 m c) 2.0 m
b) 2.5 m d) 3.0 m
9 Maximum layer thickness for concreting when compaction is being done with niddle vibrator
a) 350 mm c) 400 mm
b) 450 mm d) 500 mm
10 The common durability problems in concrete are
a) Sulphate and other chemical attacks of concrete c) Corrosion of steel bars or tendons
b) Alkali-aggregate reaction d) All of These
11 The property by which a body returns to its original shape after removal of the force, is called
a) Plasticity c) Ductility
Page 1 of 7 QAQC-I
b) Elasticity d) Malleability

12 Mechanical coupling can be adopted if it develops at least ………. Of the charastristic strength of the
reinforcement bar.
a) 115% c) 125%
b) 120% d) All of these
13 The process of consolidating concrete mix after placing it in position is termed as
a) curing c) compaction
b) wetting d) All of these
14 2.0 m backfilling from the RE wall shall be compacted from the machine having mass less than
a) 1.0 tone c) 1.5 tone
b) 2.0 tone d) 2.5 tone
15 variations of level of top of piles for cast-in-situ /bored concrete pile & open foundation is…………..
a) ±10mm c) ±25mm
b) ±15mm d) All of these
16 Primary cause of honeycombing
a) Low Slump concreting c) Water Cement Ratio
b) High Slump concreting d) Mixing Time
17 For well steining & well cap , the permissible variation in dimensions…………
a) + 50mm & - 10mm c) +50mm & -20mm
b) + 60mm & -20mm d) Non of These
18 Cement concrete is ……………… to moisture.
a) permeable c) impermeable
b) Drainage d) All of these
19 The surface where two successive placements of concrete meet, is known as
a) Contraction joint c) Construction joint
b) Expansion joint d) Both (a) and (b)
20 PCC is equally strong in taking
a) tensile stress c) shear stresses
b) compressive stress d) All of these
Lateral displacement of piling at the time of initial load test & routine load test shall not more than………….for
21 piles of dia more than 600mm.
a) 2mm c) 5mm
b) 3mm d) All of these
22 Which section of MoRTH is applicable for Prestressing…..…..
a) 1700 c) 1900
b) 1800 d) 2000
23 The desirable properties of grout are as
a) Fluidity, Low shrinkage & Durable c) Adequate strength after hardening
b) Minimum bleeding and segregation d) All of These
Variations in web thickness,top & bottom slab of box girder & top & bottom flage of T-Girders and slabs should
24 fall within limit of………………..
a) -2mm to +10mm c) -5mm to +10mm or ±5mm
b) -10mm to +15mm d) All of these
25 The number of initial tests on piles shall not be less than …………….
a) 2 c) 5
b) 4 d) All of these
26 Which section of MoRTH is applicable for Open Foundation…..…..
a) 1700 c) 1900
Page 2 of 7 QAQC-I
b) 1800 d) 2100
27 If strata is below the founding level is soil or ordinory rocks ,which type of pile will be preffered?
a) friction pile c) a & b
b) end bearing pile d) All of these
28 The removal of excess air after placing concrete helps in increasing strength of concrete by
a) 15 - 20% c) 30 - 50%
b) 20 - 30 % d) 50 - 70%
29 What should be the lap length, when uncoated steel is used?
a) 50 c) 72
b) 58 d) All of these
30 In a beam, what is the safest loaction of providing lap?
a) Where bending moment is minimum c) Where no bending moment
c) Where bending moment is maximum d) All of these
31 The internal angle of the well kerb shall be about………………….
a) 20°- 27° b) 40°- 47°
b) 30°- 37° d) All of these
32 The bearing capacity of a water logged soil, may be improved by
a) Grouting c) Drainage/ Granular Material
b) Chemical action d) Compaction
33 Variation in cross-sectional dimensions for cast-in-situ/bored concrete pile is………..
a) +50mm & -10mm c) +50mm & -20mm
b) +30mm & -10mm d) All of these
34 Misplacement from specified in plan in substructure is……………..
a) 5mm c) 10mm
b) 15mm d) All of these
35 Vertical sides of columns may be stripped after
a) 1- 2 Days c) 14 Days
b) 7 Days d) 21 Days
36 Minimum diameter of spacer bar shall be……………….
a) 12mm c) maximum size of coarse aggregate
b) equal to maximum dia of main reinforcement d) All of these
37 For well steining & well cap, the permissible variation of level of top piles
a) ± 20 mm c) ± 30mm
b) ± 25mm d) ± 35mm
38 Minimum depth of boaring in hard rock for sub-surface investigation shall not be less than……………
a) 5 times diameter of pile but min 6m in such rock c) 4 times diameter of pile but min 3m in such rock
b) 6 times diameter of pile but min 15m in such rock d) All of these
39 Dimensions of the modular concrete block shall not be differ more than …………………. for length.
a) ±1.5mm c) ±5.0mm
b) ±2.5mm d) All of these
40 Vertical piles deviation at piling plateform level for cast-in-situ /bored concrete pile shall be…………..
a) 25mm c) 50mm
b) 75mm d) 100mm
41 The Geo-strip shall be placed at ……………………………………... to the face of the wall
a) Inclined c) Parallel
b) Right angled d) Non of These
Page 3 of 7 QAQC-I
42 When the concrete mix is too wet, it causes
a) segregation c) excess laitance at the top
b) low density d) All of these
43 Provide only ………………………………….cut to the Geo-Composite to fix the Paraweb/Geo-strip.
a) Horizontal c) Window
b) Flap d) All of These
44 Minimum depth of boaring in soil for sub-surface investigation shall not be less than……………
a) 2.5 times estimated length of pile or 15m below the c) 1.5 times estimated length of pile or 15m below the
proposed founding level
length of pile or 15m below the proposed founding level
b) 3.5 times estimated d) All of these
proposed founding level
45 The object of compaction is to
c) ensure intimate contact between the concrete & the
a) eradicate air holes surface of reinforcement
b) give maximum density d) All of these
46 Shrinkage of concrete is defined as the contraction due to loss of …………
a) Moisture c) Aggregate
b) Cement d) All of These
47 The load applied on pile for routine pile test shall not be less than………….. Of design load.
a) 1.5 times c) 3.0times
b) 2.5 times d) All of these
48 When water level is up concreting area, following measure should be taken
a) Dewatering by making Sump c) Filling with non-cohesive Material
b) Stop the work d) Non of These
49 The permanent steel liner shall be provided for the full depth of pile in the situation of………….
a) soft soil c) ordinary rock
b) hard rock d) All of these
50 Tilt of the well shall not exceed ………………..
a) 1 in 20 c) 1 in 60
b) 1 in 40 d) 1 in 80
51 Diference between length of two diagonals & thickness of RE panel should be the within limits of……….
a) 0 - 4 mm c) 0 - 6 mm
b) 0 - 5 mm d) All of these
52 Variations from plumb over full height in substructure is……………..
a) ±5mm c) ±20mm
b) ±10mm d) All of these
53 Which section of MoRTH is applicable for Well foundations…..…..
a) 1100 c) 1200
b) 1600 d) 1300
54 Backfilling should be done behind structures with…………………….soil to get the advantage of self compaction.
a) Cohesive c) Silty
b) Non-Cohesive d) Clay
55 Variations of levels at the top in substructure is……………..
a) ±5mm c) ±20mm
b) ±10mm d) All of these
56 What should be the distance between the two section for providing laps?
a) 1.5 times of lap length c) 2.0 times of lap length
b) 1.15 times of lap length d) All of these
Length of matach-cast segment or position of shear keys should fall within the limits of …………………….. For
57 superstructure.
Page 4 of 7 QAQC-I
a) ±5mm c) ±25mm
b) ±15mm d) All of these
58 Niddle length/Height of Vibrator is
a) 400 mm c) 500 mm
b) 450 mm d) 550 mm
The fill material in RE soil zone shall have drained or effective angle of friction not less than
59
a) 30 ° c) 40 °
b) 35 ° d) 45 °
60 The load applied on pile for initial pile test shall not be less than………….. Of design load.
a) 1.5 times c) 3.0times
b) 2.5 times d) None of these
61 What is the purpose to use the bentonite ………….. In the bore hole of piles.
a) to stable the strata c) to decrease the water table
b) to maintain the water table d) All of these
62 All supports of formwork should be
a) Firm c) Continuous
b) Temporary d) Non of These
63 Layers of reinforcements shall be separated by spacer bars @ approximetly…………….intervals.
a) 1m c) 3m
b) 1.5m d) 2m
64 In cast-in-situ Pile, the permissible variation of level of top piles
a) ± 20 mm c) ± 30mm
b) ± 25mm d) ± 35mm
65 Shape of cutting edge shoud be …………………. For well foundation.
a) V c) L
b) T d) All of these
66 Stability of an existing structure may be disturbed by
a) Rising of water table c) Mining in the neighborhood
b) Vibrations caused by traffic movements d) All the above
67 Misplacement from specified positions in plan for pile cap & open foundation is……………..
a) 15mm c) 20mm
b) 25mm d) 30mm
68 The concrete can be lifted by pumps through a maximum vertical distance of
a) 10m c) 30m
b) 20m d) 50m
69 In special case what should be minimum clear cover to main reinforcement?
a) 2D of rebar c) 4D of rebar
b) 6D of rebar d)All of these
70 Shifts of the well shall not exceed ………………..
a) 120mm c) 150mm
b) 175mm d) All of these
71 Provide only …………………………………………... cut to the Geo-Composite to fix the straight strip
a) Vertical c) Horizontal
b) Window d) All of These
72 What should br the lap length, when corrosion protection coated steel is used?
a) 50 c) 72
Page 5 of 7 QAQC-I
b) 58 d) All of these
73 The number of routine tests on piles shall not be less than …………….
a) 2 or 2% of total pile whichever is higher c) 5 or 2% of total pile whichever is higher
b) 4 or 2% of total pile whichever is higher d) All of these
74 All dimension of precast RE panels should be withine the limits of………….
a) ±5mm c) ±15mm
b) ±10mm d) All of these
75 Tendom hole locations should fall within the limit of ………………..for superstructure.
a) ±5mm c) ±2mm
b) ±3mm d) All of these
76 Proper curing of cement concrete, is good for its
a) volume stability c) wear resistance
b) strength d) All of these
77 Density of bentonite suspension to use in the bore hole should be ………. g/cc.
a) 1.00 c) 1.05
b) 1.10 d) All of these
78 Concrete is a composite material composed of
a) coarse aggregate c) Cement as a Binder
b) fine aggregate d) All of These
79 Evenness of the front face of RE Panels should be within limit of………………..
a) ±5mm over 1500mm c) ±15mm over 1500mm
b) ±10m mover 1500mm d) All of these
80 The bottom plug concrete shall be provided a minimum of ………………. Above the top of the well kerb.
a) 200mm c) 400mm
b) 300mm d) All of these
Bulging (Vertical) & Bowing (Horizontal) of the erections of RE Panels with metalic templet should be within the
81 limits of ………………………
a) ±10mm in 4.5m c) ±20mm in 4.5m
b) ±15mm in 4.5m d) All of these
82 The wall constructed for the stability of a back filling portion of a road on the downhill side, is known as
a) Retaining wall c) Parapet wall
b) Breast wall d) All the above
83 In any case, providing weld lap then what should be the lap length & how welding should be provided?
a) 18 & in  alternate side stiching c) 20 & in either side stiching
a) 20 & in  alternate side stiching d) All of these
84 The first Steining shall be provided …………………….. Height of steining above the well kerb
a) 2m c) 4m
b) 3m d) All of these
85 The shrinkage occurs due to two causes
a) Loss of water from voids c) a & b
b) Reduction of volume during carbonation d) Non Of These
The pre stressed cement concrete in which high compressive stresses are artificially induced before its actual
86 use, is called
a) PCC c) Prestressed cement concrete
b) RCC d) lime concrete
87 The Geo-strip shall be placed at ………………………... to the face of the RE wall
a) Parallel c) Inclined
b) Right angled d) All of These
Page 6 of 7 QAQC-I
88 Surface unevenness measured with 3m straight edge0f all surface except bearing areas in substructure
is…………….
a) ±5mm c) ±10mm
b) ±15mm d) All of these
89 In cast-in-situ Pile, the permissible variation in cross-sectional dimensions
a) + 50mm & - 10mm c) +50mm & -20mm
b) + 60mm & -20mm d) Non of These
Minimum depth of boaring in ordinory or jointed rock for sub-surface investigation shall not be less
90 than……………
a) 15 times diameter of pile but min 15m in such rock c) 25 times diameter of pile but min 15m in such rock
b) 10 times diameter of pile but min 15m in such rock d) All of these
91 Variations in cross-sectional dimensions in substructure is……………..
a) +10mm & -5mm c) +10mm & -15mm
b)+15mm & -10mm d) All of these
92 shall be provided over the reinforcement and the speed of vehicleminimum
Before allowing the movement of vehicle over the reinforcement, compacted thickness of 150mm
shall be restricted to…………..
a) 10 Kmph c) 20 Kmph
b) 15 Kmph d) All of these
93 RCC is equally strong in taking
a) tensile & compressive stresses c) tensile, compressive & shear stresses
b) compressive & tensile shear stressed d) All of these
94 Rotary drilling is the fastest method in case of
a) Rocky soils c) Sandy soil
b) Clay soils d) All of these
95 Variation in overall depth or width or thickness of diaphragm should fall within limit for superstructure is….
a) ±5mm c) ±10mm
b) ±20mm d) All of these
Vertical Settlement of piling at the time of initial load test & routine load test shall not more than………….of pile
96 diameter for piles of dia more than 600mm.
a) 2% c) 5%
b) 3% d) All of these
97 Water used for mixing and curing shall be clean and free from injurious amounts of …..
a) Oils & Acids c) Sugar & Organic Materials
b) Alkalis & Salts d) All of These
98 Variatios of reduced levels of bearing areas in substructure is……………..
a) ±5mm c) ±20mm
b) ±10mm d) All of these
99 Steps at joint in RE panels should be within limits of…………………………
a) ±5mm c) ±20mm
b) ±10mm d) All of these
100 Minimum cover in footings is
a) 25mm c) 75mm
b) 50mm d) 100mm
101 Which section of MoRTH is applicable for Pile foundations…..…..
a) 1100 c) 1200
b) 1600 d) 1300
102 p
a) ±10mm or ±0.1% of span lenth,whichever is less c) ±10mm or ±0.2% of span lenth,whichever is less
b)±15mm or ±0.1% of span lenth,whichever is less d) All of these

Page 7 of 7 QAQC-I