Anda di halaman 1dari 4

BARZAN ONSHORE PROJECT CPY DOC NO: B-V-3140-002-4-346-90 REV 2

INSPECTION TEST PLAN FOR THE FIRE FIGHTING SYSTEM (BUILDING) CTR DOC NO: B-V-3140-002-4-436-90-REV 2

BARZAN ONSHORE PROJECT CPY Doc. No. : B-V-3140-002-4-346

INSPECTION & TEST PLAN CTR Doc. No. : B-V-3140-002-4-346

FIRE FIGHTING SYSTEM (BUILDING) Doc Class : 1

Quality Inspecton Requirem


Actvity

Process/Inspecton Actvity Reference Document Acceptance Criteria Frequency Verificaton


Record Doc. No SCTR QC CTR QC CPY Q

1.0 Document Verification

1.1 Check Material Receiving Inspection at Site


REFER TO ITP SUB-CONTRACTOR PURCHASED MATERIAL RECEIVING INSPECTION AT SIDE D
NO: B-V-3140-002-4-254-90
Approved
Approved BPS/ASME Every Brazer
1.2 Check BPS/PQR & Brazer Qualification BPS/ASME IX IX BPS/Brazer R R R
Qualification

2.0 Installation
2.1 Check Installation of Pipes and Fittings for Fire Water
Check Brazing Verification and Inspection of Fire Fighting
2.2 Works
2.3 Check Installation of Sprinkler System
2.4 Check Installation of Fire Hose Cabinets/Fire Hose Reels

2.5 Check Punch listing prior to Hydro Testing of the Fire


Fighting Pipe Works
BARZAN ONSHORE PROJECT CPY DOC NO: B-V-3140-002-4-346-90 REV 2
INSPECTION TEST PLAN FOR THE FIRE FIGHTING SYSTEM (BUILDING) CTR DOC NO: B-V-3140-002-4-436-90-REV 2

BARZAN ONSHORE PROJECT CPY Doc. No. : B-V-3140-002-4-346

INSPECTION & TEST PLAN CTR Doc. No. : B-V-3140-002-4-346

FIRE FIGHTING SYSTEM (BUILDING) Doc Class : 1

Quality Inspecton Requirem


Actvity

Process/Inspecton Actvity Reference Document Acceptance Criteria Frequency Verificaton


Record Doc. No SCTR QC CTR QC CPY Q

2.6 Hydrostatic Testing Package for Fire Fighting Pipe Works


2.7 Hydrostatic Testing Record Checklist
2.8 Check Dewatering after Hydro Testing

2.90 Check Water Flushing & Internal Cleaning for Fire Fighting
Pipe Works

H-HOLD W-WITNESS R-REVIEW


RFI FOR JGC TO ATTENT UNLESS RFI FOR JGC TO ATTEND
REVIEW DOCUMETNS, NO
INFORM IN WRITING NOT TO ATTEND IF NOT ATTENDED WORK TO CARY ON
BARZAN ONSHORE PROJECT CPY DOC NO: B-V-3140-002-4-346-90 REV 2
INSPECTION TEST PLAN FOR THE FIRE FIGHTING SYSTEM (BUILDING) CTR DOC NO: B-V-3140-002-4-436-90-REV 2

CPY Doc. No. : B-V-3140-002-4-346-90 Rev 2

CTR Doc. No. : B-V-3140-002-4-346-90 Rev 2

Doc Class : 1

Inspecton Requirements

CPY QC TP QC

ONTRACTOR PURCHASED MATERIAL RECEIVING INSPECTION AT SIDE DOCUMENT


NO: B-V-3140-002-4-254-90

R
BARZAN ONSHORE PROJECT CPY DOC NO: B-V-3140-002-4-346-90 REV 2
INSPECTION TEST PLAN FOR THE FIRE FIGHTING SYSTEM (BUILDING) CTR DOC NO: B-V-3140-002-4-436-90-REV 2

CPY Doc. No. : B-V-3140-002-4-346-90 Rev 2

CTR Doc. No. : B-V-3140-002-4-346-90 Rev 2

Doc Class : 1

Inspecton Requirements

CPY QC TP QC

R-REVIEW

REVIEW DOCUMETNS, NO RFI REQUIRED

Anda mungkin juga menyukai