Anda di halaman 1dari 6

KEGIATAN

SALURAN DRAINASE RT 1 RW 1 PEMBANGUNAN SARANA


PRASARANA DESA TA
PANJANG (M): 100.0
2017

PROPINSI
JAWA TENGAH
KABUPATEN
0.30 KENDAL
PLASTERAN 1:4 KECAMATAN
KALIWUNGU
DESA
NOLOKERTO
LOKASI
SULING- SULING
RT 1 RW 1
0.30
JENIS SARANA
0.50 PAS. BATU BELAH 1:5
Saluran Drainase

0.20 GAMBAR
PASIR URUG
POTONGAN
0.05
DIBUAT OLEH

0.35 PELAKSNA KEGIATAN


DIPERIKSA OLEH

DETAIL SALURAN DRAINASE CARIK


DIKETAHUI OLEH

KADES
Kabupaten KENDAL Jenis Prasaran Saluran Drainase
Kecamatan KALIWUNGU Take Off Sheet Lokasi RT 1 RW 1
Desa NOLOKERTO Volume 100 M

a Volume galian tanah


Talud no. 1 P= 100m
Panjang = 100.00 m
Lebar = 0.35 m
Tebal = 0.20 m
Volume galian
= 100 X 0.35 X 0.2 = 7.0 m³
Talud no. 2 P= 100m
Panjang = 100.00 m
Lebar = 0.35 m
Tebal = 0.20 m
Volume galian
= 100 X 0.35 X 0.2 = 7.0 m³
Volume galian total = 14.0 m³

b Volume urugan pasir


Talud no. 1 P= 100m
Panjang = 100.00 m
Lebar = 0.35 m
Tebal = 0.05 m
Volume urugan
= 100 X 0.35 X 0.05 = 1.8 m³
Talud no. 2 P= 100m
Panjang = 100.00 m
Lebar = 0.35 m
Tebal = 0.05 m
Volume urugan
= 100 X 0.35 X 0.05 = 1.8 m³
Volume urugan total = 3.5 m³

c Volume batu belah


Talud no. 1 P= 100m
Panjang = 100.00 m
Lebar atas = 0.30 m
Lebar bawah = 0.35 m
Tinggi talud = 0.30 m
Tinggi pondasi = 0.20 m
Volume batu belah
{(0.3 + 0.35)/2} x 0.3 x 100 = 9.8 m³
0.35 x 0.2 x 100 = 7.0 m³
Talud no. 2 P= 100m
Panjang = 100.00 m
Lebar atas = 0.30 m
Lebar bawah = 0.35 m
Tinggi talud = 0.30 m
Tinggi pondasi = 0.20 m
Volume batu belah
{(0.3 + 0.35)/2} x 0.3 x 100 = 9.8 m³
0.35 x 0.2 x 100 = 7.0 m³
Volume total = 33.5 m³

d Volume plesteran
Talud no. 1 P= 100m
Panjang = 100.00 m
Lebar = 0.30 m
Volume plesteran
(0,1 + 0.3) x 100 = 40.0 m²
Talud no. 2 P= 100m
Panjang = 100.00 m
Lebar = 0.30 m
Volume plesteran
(0,1 + 0.3) x 100 = 40.0 m²
Volume plesteran total = 80.0 m²

f Langsiran material
Pekerja langsiran (1 m³ = 0,5 HOK)
Bahan = 64.3 m³
Pekerja = 32.1 HOK

Tanggal Survei : Dibuat oleh : TPK


PERHITUNGAN VOLUME PEKERJAAN, ANALISA HARGA SATUAN & BIAYA
Uraian Pekerjaan Volume Satuan Harga Satuan Total Biaya

I Pekerjaan galian tanah 14.0 m³


(Analisa P.02.a)
0.563 Pekerja 7.9 HOK 55,000 433,510
0.025 Mandor 0.4 HOK 60,000 21,000
Total biaya 454,510

II Pekerjaan urugan pasir 3.5 m³


(Analisa T.14.c)
1.2 Pasir urug 4.2 m³ -
0.4 Pekerja 1.4 HOK 55,000 77,000
0.04 Mandor 0.14 HOK 60,000 8,400
Total biaya 85,400

III Pasangan batu belah 1 : 5 33.5 m³


(Analisa P.01.C.a.1)
1.17 Batu belah 39.2 m³ 290,000 11,366,550
2.352 Semen 50 Kg 78.8 Zak 63,000 4,963,896
0.5654 Pasir muntilan 18.9 m³ 360,000 6,818,724
1.18 Pekerja 39.5 HOK 55,000 2,174,150
0.59 Tukang 19.8 HOK 75,000 1,482,375
0.1 Kepala tukang 3.4 HOK 80,000 268,000
0.1 Mandor 3.4 HOK 60,000 201,000
Total biaya 27,274,695

IV Plesteran 1 PC : 4 PS, 15 mm 80.0 m²


(SNI 03 - 2837 - 2008)
0.125 Semen 50 Kg 10.0 Zak 63,000 630,000
0.024 Pasir muntilan 1.9 m³ 360,000 691,200
0.3 Pekerja 24.0 HOK 55,000 1,320,000
0.15 Tukang 12.0 HOK 75,000 900,000
0.015 Kepala tukang 1.2 HOK 80,000 96,000
0.015 Mandor 1.2 HOK 60,000 72,000
Total biaya 3,709,200
REKAP KEBUTUHAN BAHAN, ALAT DAN UPAH
No Uraian Volume Satuan

1 Pasir urug 4.2 = 5.0 m³


2 Batu belah 39.2 = 40.0 m³
3 Semen 50 Kg 88.8 = 89.0 Zak
4 Pasir muntilan 20.9 = 21.0 m³
5 Pekerja 72.8 = 73.0 HOK
6 Tukang 31.8 = 32.0 HOK
7 Kepala tukang 4.6 = 5.0 HOK
8 Mandor 5.0 = 6.0 HOK
9 Pekerja langsiran 32.1 = 33.0 HOK
RENCANA ANGGARAN BIAYA
DESA NOLOKERTO KECAMATAN KALIWUNGU
TAHUN ANGGARAN 2017

Bidang : Pelaksanaan Pembangunan Desa


Kegiatan : Saluran Drainase
Waktu Pelaksanaan :
Sumber dana :
Output :

Rincian Pendanaan

Harga Satuan Jumlah


No Kode Rekening Uraian Volume Satuan
Rp Rp

Saluran Drainase RT 1 RW 1 Vol= 100 m 35,143,000

Belanja Barang dan Jasa 8,990,000


Upah Tenaga Kerja 8,990,000
Pekerja 73.0 HOK 55,000 4,015,000
Tukang 32.0 HOK 75,000 2,400,000
Kepala tukang 5.0 HOK 80,000 400,000
Mandor 6.0 HOK 60,000 360,000
Pekerja langsiran 33.0 HOK 55,000 1,815,000

Belanja Modal 26,153,000


Matrial 25,617,000
Pasir urug 5.0 m³ 170,000 850,000
Batu belah 40.0 m³ 290,000 11,600,000
Semen 50 Kg 89.0 Zak 63,000 5,607,000
Pasir muntilan 21.0 m³ 360,000 7,560,000

Alat 216,000
Cetok 1.0 Set 14,000 14,000
Ember plastik (5 liter) 2.0 Buah 10,000 20,000
Sekop 1.0 Buah 91,000 91,000
Cangkul 1.0 Buah 91,000 91,000

Sewa molen Hari 250,000 -


Prasasti 1.0 Ls 300,000 300,000
Papan Proyek 1.0 Ls 20,000 20,000

JUMLAH 87,129,000

Nolokerto,

Disetujui/ Mengesahkan Telah Verifikasi Pelaksana Kegiatan


Kepala Desa Sekretaris Desa

KADES CARIK PELAKSNA KEGIATAN