PROPINSI
JAWA TENGAH
KABUPATEN
0.30 KENDAL
PLASTERAN 1:4 KECAMATAN
KALIWUNGU
DESA
NOLOKERTO
LOKASI
SULING- SULING
RT 1 RW 1
0.30
JENIS SARANA
0.50 PAS. BATU BELAH 1:5
Saluran Drainase
0.20 GAMBAR
PASIR URUG
POTONGAN
0.05
DIBUAT OLEH
KADES
Kabupaten KENDAL Jenis Prasaran Saluran Drainase
Kecamatan KALIWUNGU Take Off Sheet Lokasi RT 1 RW 1
Desa NOLOKERTO Volume 100 M
d Volume plesteran
Talud no. 1 P= 100m
Panjang = 100.00 m
Lebar = 0.30 m
Volume plesteran
(0,1 + 0.3) x 100 = 40.0 m²
Talud no. 2 P= 100m
Panjang = 100.00 m
Lebar = 0.30 m
Volume plesteran
(0,1 + 0.3) x 100 = 40.0 m²
Volume plesteran total = 80.0 m²
f Langsiran material
Pekerja langsiran (1 m³ = 0,5 HOK)
Bahan = 64.3 m³
Pekerja = 32.1 HOK
Rincian Pendanaan
Alat 216,000
Cetok 1.0 Set 14,000 14,000
Ember plastik (5 liter) 2.0 Buah 10,000 20,000
Sekop 1.0 Buah 91,000 91,000
Cangkul 1.0 Buah 91,000 91,000
JUMLAH 87,129,000
Nolokerto,