Anda di halaman 1dari 2

RENCANA ANGGARAN BIAYA

PEMBANGUNAN RUMAH MAKAN

No. Jenis Pekerjaan Vol./Sat H.Satuan Jumlah Total


1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Pembuatan los kerja / D.keet ( 2x 3 ) 8.00 m2 100,000.00 800,000.00
2 Persiapan listrik kerja 2.00 bln 100,000.00 200,000.00
Sub total I 1,000,000.00 1,000,000.00
II PEKERJAAN TANAH
1 Galian tanah pondasi batu kali 6.10 m3 27,500.00 167,750.00
2 Urug tanah pondasi batu kali 6.10 m3 12,000.00 73,200.00
Sub total II 240,950.00 240,950.00
III PEKERJAAN PONDASI
1 Urug pasir alas pondasi t : 5 cm 0.85 m3 129,760.00 110,296.00
2 Pas, pondasi batu kali 6.10 m3 425,000.00 2,592,500.00
Sub total III 2,702,796.00 2,702,796.00
IV PEK.BETON BERTULANG / STRUKTUR
1 Beton pondasi poer 1.800 m3 1,795,000.00 3,231,000.00
2 Beton sloof -
- Uk. 15 x 30 0.64 m3 1,816,800.00 1,165,023.00
3 Beton kolom -
- Uk. 30 x 30 ( K1 ) 1.80 m3 2,100,000.00 3,780,000.00
- Uk. 15 x 15 ( Kpr ) 0.45 m3 1,686,500.00 758,925.00
4 Beton balok konstruksi -
- Uk. 30 x 25 1.07 m3 2,186,000.00 2,336,287.50
5 Beton lantai -
- Beton lantai kerja 2.10 m3 390,000.00 819,000.00
Sub total IV 12,090,235.50 12,090,235.50
V PEKERJAAN DINDING
1 Pas. Dinding bata sekat 48.00 m2 36,400.00 1,747,200.00
2 Plester & aci 114.00 m2 32,700.00 3,727,800.00
Sub total V 5,475,000.00 5,475,000.00
VI PEKERJAAN LANTAI
4 Pas.krmk Ruang Dapur Uk. 30 x 30 6.00 m2 76,620.00 459,720.00
5 Pas.krmk Ruang Makan Uk.30 x 30 102.00 m2 76,620.00 7,815,240.00
7 Pas.krmk KM/WC Uk.20 x 20 4.00 m2 70,300.00 281,200.00
Sub total VI 8,556,160.00 8,556,160.00
VIII PEKERJAAN PLAFOND
1 Pas. Rgk pipa holow + Pas Gypsum 54.21 m2 65,000.00 3,523,650.00
Sub total VIII 3,523,650.00 3,523,650.00
IX PEK.INS.LISTRIK & Acc
A. Lantai Bawah
1 Instalasi lampu penerangan 12.00 titik 115,000.00 1,380,000.00
2 Instalasi stop kontak 20.00 titik 97,000.00 1,940,000.00
Sub total A 3,320,000.00 3,320,000.00
B Acc. Pekerjaan Listrik
1 Saklar tunggal broco 2.00 bh 9,500.00 19,000.00
2 Saklar ganda broco 2.00 bh 12,500.00 25,000.00
3 Stop kontak broco 3.00 bh 15,500.00 46,500.00
4 Lampu Biasa 12.00 bh 28,000.00 336,000.00
Sub total B 426,500.00 426,500.00
X PEK. SANITARY & INST. AIR
1 Pas. Closet
- Closet duduk KM / WC 2.00 bh 1,050,000.00 2,100,000.00
2 Pembuatan bak kontrol ( 40 x 40 x 60 ) 2.00 bh 95,000.00 190,000.00
3 Pas. Kran tembok
- Kran KM / WC + tempat cuci + taman 3.00 bh 96,000.00 288,000.00
4 Pas. Pipa sal.air bersih PVC 1/2" 12.00 m' 12,000.00 144,000.00
5 Pas. Pipa sal.air bersih PVC 1 1/4" 10.00 m' 15,000.00 150,000.00
6 Pas. Pipa air kotor PVC 4" 9.00 m' 56,000.00 504,000.00
7 Pntu WC ( PVC ) 1.00 unit 550,000.00 550,000.00
8 Knee drat dia.1/2" 3.00 bh 7,500.00 22,500.00
9 Knee drat dia. 1 1/4" 4.00 bh 9,000.00 36,000.00
10 Tee dia.1 1/4" 3.00 bh 5,000.00 15,000.00
11 Vlok sock dia.1 1/4" - 1/2" 4.00 bh 6,000.00 24,000.00
12 Knee dia.4" 3.00 bh 10,000.00 30,000.00
SUB TOTAL X 4,053,500.00 4,053,500.00
XI PEKERJAAN PENGECATAN /
FINISHING
1 Pengecatan dinding Vinilex 96.00 m2 23,500.00 2,256,000.00
2 Finishing politur daun pintu ( kuas ) 6.20 m2 62,500.00 387,500.00
3 Finishing politur daun Jendela ( kuas ) 5.10 m2 62,500.00 318,750.00
4 Finishing politur kusen ( kuas ) 22.00 m' 53,000.00 1,166,000.00
SUB TOTAL XI 4,128,250.00 4,128,250.00
XII PEKERJAAN ATAP
1 Pek. Atap
a. Pasang Rangka Atap Atap baja ringan 120.00 m2 122,000.00 14,640,000.00
b. Pasang sopi -sopi baru 13.75 m2 47,600.00 654,500.00
c. Beton bertulang untuk sopi - sopi 1.07 m2 1,686,500.00 1,797,134.40
2 Pas. Genteng metal pasir 120.000 m2 20,689.00 2,482,680.00
3 Pas. Nok genteng metal pasirn 4.500 m' 46,600.00 209,700.00
Sub total X Rp19,784,014 19,784,014.40
TOTAL PEKERJAAN BANGUNAN BARU 65,301,055.90
Dibulatkan 65,301,000.00