REPORT KESIAPAN REFINERY PER ELEVASI

No. Penanggung Jawab


1 Basofi Habibi
2 Puro
3 Ruli
4 Rostan
5 Azis
6 Dwi K
7 Jessy
8 Aldy
9 Pujianto
10 Bhirawa
11 Ade
12 Wahid
13 Nuha
14 Adi

Target penyelesaian pekerjaan REFINERY tiap elevasi


I Elevasi 18.000
Pekerjaan yang perlu diselesaikan
1. Join pipa di tangki A/B Mol Head Tank
2. Pemasangan drain pompa B Seed
3. Pemasangan drain B Magma Head Tank
4. Pemasangan drain Tangki Excess Magma
5. Pemasanga line fondant vakum pan A dan White

6. Pemasangn line steaming pompa C-Magma Storage tank


7. Pemasangan line steaming pompa excess magma
9. Pemasangan Washing sight glass w-cutting seed
10. Penyempurnaan chute bucket elevator W1 dan W2
II Elevasi 11.300
Pekerjaan yang perlu diselesaikan
1. Pipa Milk of Lime, Hot Water, dan Service Water
2. Pemasangan control valve pada pipa evaporator

3. Rotasi arah globe valve 8" line steaming vakum pan white
4. Pemasangan pipa kondensat plate heater pre-eva
III Elevasi 7.300
Pekerjaan yang perlu diselesaikan
piping hot water for cleaning
piping spray scrubber for dust collecting system
lantai elv 18.000 pekerjaan floor hardener pending

PU di elv. +11.300 on progress


pekerjaan Painting Pipa di elv +18.000 on progress
SIAPAN REFINERY PER ELEVASI

Tanggung Jawab Tanda tangan


Kebersihan dan pengamanan area per elevasi 1 2

Elevasi 18.000 dan Elevasi 11.300


3 4

Elevasi 7.300 dan Elevasi 0 5 6

Piping dan Insulation Kontraktor ( PT. MAS, PT. TRISULA ABADI 7 8


dan PT. ANIS JAYA )
9 10
Piping Internal Tim RMI
11 12

Penanggung jawab shif


13 14

Target penyelesaian pekerjaan REFINERY tiap elevasi


Target selesai tanggal 06 April 2019

Tim RMI finished


Tim RMI finished
PT. MAS finished
PT. MAS finished
finished

finished
PT.TRISULA ABADI
finished
finished
PT. ISS finished
Target selesai tanggal 11 April 2019

PT. MAS finished


SUTECH dan Tim RMI finished

PT. MAS

Tim RMI finished


Target selesai tanggal 15 April 2019 finished

PT. RMI finished


PT. RMI finished