ITEM PARTIDAS UND METRADO P.U. PARCIAL Valorizar OBSERVACIONES
*01 ESTRUCTURAS
*01.01 OBRAS PROVISIONALES
01.01.01 CONSTRUCCIONES PROVISIONALES
01.01.01.02 SSHH portátiles de obra mes 8.00 240.00 1,920.00 2.00 480 25.00% 0.00 0.00 0.00% 2.00 480.00 25.00% 75.00%
01.01.01.03 Caseta, guardianía y almacén un 1.00 1,300.00 1,300.00 1.00 1300 100.00% 0.00 0.00 0.00% 1.00 1300.00 100.00% 0.00%
01.01.02 INSTALACIONES PROVISIONALES
01.01.02.04 Cerco de obra g/b 1.00 1,300.00 1,300.00 1.00 1300 100.00% 0.00 0.00 0.00% 1.00 1300.00 100.00% 0.00%
01.01.02.05 Transporte de equipos y herramientas vje 3.00 500.00 1,500.00 1.00 500 33.33% 0.00 0.00 0.00% 1.00 500.00 33.33% 66.67%
01.01.02.05 Transporte de equipos y herramientas adicional vje 1.00 500.00 500.00 1.00 500 100.00% 0.00 0.00 0.00% 1.00 500.00 100.00% 0.00%
01.01.02.06 Implementacion de seguridad en la obra g/b 1.00 6,000.00 6,000.00 0.50 3000 50.00% 0.00 0.00 0.00% 0.50 3000.00 50.00% 50.00%
01.01.03 SERVICIOS
01.01.03.01 Seguridad para el Personal de la Obra u 1.00 6,000.00 6,000.00 0.50 3000 50.00% 0.00 0.00 0.00% 0.50 3000.00 50.00% 50.00%
*01.02 TRABAJO PRELIMINARES
01.02.01 LIMPIEZA DEL TERRENO
01.02.01.01 Limpieza del Terreno m2 252.00 2.00 504.00 252.00 504 100.00% 0.00 0.00 0.00% 252.00 504.00 100.00% 0.00%
01.02.01.02 Limpieza Permanente de la Obra m2 1512.00 4.00 6,048.00 302.40 1209.6 20.00% 0.00 0.00 0.00% 302.40 1209.60 20.00% 80.00%
01.02.02 ELIMINACION DE OBSTRUCCIONES
01.02.03 REMOCIONES
01.02.03.01 Desmontaje de Aparatos Sanitarios u 3.00 20.00 60.00 3.00 60 100.00% 0.00 0.00 0.00% 3.00 60.00 100.00% 0.00%
01.02.03.02 Retiro de Tableros de Distribucion u 1.00 20.00 20.00 1.00 20 100.00% 0.00 0.00 0.00% 1.00 20.00 100.00% 0.00%
01.02.03.03 Desmontaje de Puertas de Madera u 23.00 20.00 460.00 23.00 460 100.00% 0.00 0.00 0.00% 23.00 460.00 100.00% 0.00%
01.02.03.04 Desmontaje de Mamparas y Ventanas de Madera u 21.00 20.00 420.00 21.00 420 100.00% 0.00 0.00 0.00% 21.00 420.00 100.00% 0.00%
01.02.04 DEMOLICIONES
01.02.04.01 Demolicion Masiva con Maquinaria m3 350.00 45.00 15,750.00 350.00 15750 100.00% 0.00 0.00 0.00% 350.00 15750.00 100.00% 0.00%
01.02.05 TRAZO, NIVEL Y REPLANTEO
01.02.05.01 Trazo, Nivel y Replanteo m2 252.00 2.75 693.00 252.00 693 100.00% 0.00 0.00 0.00% 252.00 693.00 100.00% 0.00%
01.02.05.03 Trazo, Nivel y Replanteo durante el proceso m2 1512.00 1.30 1,965.60 378.00 491.4 25.00% 0.00 0.00 0.00% 378.00 491.40 25.00% 75.00%
*01.03 MOVIMIENTO DE TIERRAS
01.03.01 NIVELACION DEL TERRENO
01.03.01.01 Nivelacion del Terreno m2 252.00 3.85 970.20 0.00 0 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 100.00%
01.03.02 EXCAVACIONES
01.03.02.01 Excavacion Masiva con Equipo m3 290.00 7.00 2,030.00 250.00 1750 86.21% 0.00 0.00 0.00% 250.00 1750.00 86.21% 13.79%
01.03.02.02 Excavacion para Zanjas de Cimientos m3 44.00 30.00 1,320.00 22.00 660 50.00% 0.00 0.00 0.00% 22.00 660.00 50.00% 50.00%
01.03.02.03 Excavacion de Zanjas para Zapatas m3 8.00 30.00 240.00 6.50 195 81.25% 0.00 0.00 0.00% 6.50 195.00 81.25% 18.75%
01.03.02.04 Excavacion de Camara de Sumidero m3 6.00 30.00 180.00 0.00 0 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 100.00%
01.03.02.06 Excavación para calzadura de terreno m3 0.00 0.00 0.00 0.00 0 0.00 0.00 100.00%
01.03.02.07 Excavación vertical parcial para reforzamiento de cimentación m3 45.00 52.00 2,340.00 45.00 2340 100.00% 0.00 0.00 0.00% 45.00 2340.00 100.00% 0.00%
01.03.03 RELLENOS
01.03.03.01 Relleno compactado c/equipo, con Material Propio m3 154.00 17.00 2,618.00 0.00 0 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 100.00%
01.03.04 ELIMINACION DE MATERIAL EXCEDENTE
01.03.04.01 Eliminacion de Material Excedente a 30 m de Distancia m3 145.00 25.00 3,625.00 54.00 1350 37.24% 0.00 0.00 0.00% 54.00 1350.00 37.24% 62.76%
01.03.04.02 Eliminacion de Material con Maquinaria m3 136.00 17.00 2,312.00 136.00 2312 100.00% 0.00 0.00 0.00% 136.00 2312.00 100.00% 0.00%
01.03.05 NIVELACION Y APISONADO
01.03.05.01 Nivelacion Interior y Apisonado m2 185.00 5.00 925.00 0.00 0 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 100.00%
*01.04 OBRAS DE CONCRETO SIMPLE
01.04.01 CIMIENTOS CORRIDOS
01.04.01.01 Cimientos Corridos - Concreto m3 23.00 275.00 6,325.00 0.00 0 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 100.00%
01.04.02 CALZADURAS
01.04.02.01 Calzadura - Concreto f c= 140 kg/cm2 m3 0.00 0.00 0.00 0 0.00
01.04.02.01.01 Reforzamiento de cimentación - Subcimineto - Concreto f c= 140 kg/cm2 m3 45.00 200.00 9,000.00 45.00 9000 100.00% 0.00 0.00 0.00% 45.00 9000.00 100.00% 0.00%
01.04.02.01.02 Reforzamiento de cimentación - Subcimineto - Piedra de canto rodado grande de 10" m3 10.00 70.00 700.00 10.00 700 100.00% 0.00 0.00 0.00% 10.00 700.00 100.00% 0.00%
01.04.02.02 Calzaduras - Encofrado y Desencofrado m2 0.00 0.00 0.00 0 0.00
01.04.02.02.01 Reforzamiento de cimentación - Encofrado y Desencofrado de cimiento vecino m2 85.00 36.00 3,060.00 85.00 3060 100.00% 0.00 0.00 0.00% 85.00 3060.00 100.00% 0.00%
01.04.02.02.02 Reforzamiento de cimentación - Acero de 1/2" kg 450.00 4.50 2,025.00 450.00 2025 100.00% 0.00 0.00 0.00% 450.00 2025.00 100.00% 0.00%
01.04.02.02.03 Reforzamiento de cimentación - Encofrado y Desencofrado de Subcimiento. m2 40.00 35.00 1,400.00 40.00 1400 100.00% 0.00 0.00 0.00% 40.00 1400.00 100.00% 0.00%
*01.05 OBRAS DE CONCRETO ARMADO
01.05.01 CIMIENTOS REFORZADOS
01.05.01.01 Cimientos Reforzados - Concreto f c= 210 kg/cm2 m3 27.05 310.00 8,385.50 27.05 8385.5 100.00% 0.00 0.00 0.00% 27.05 8385.50 100.00% 0.00%
01.05.01.02 Cimientos Reforzados - Acero kg 223.21 4.50 1,004.45 223.21 1004.445 100.00% 0.00 0.00 0.00% 223.21 1004.45 100.00% 0.00%
01.05.02 ZAPATAS
01.05.02.01 Zapatas - Concreto fc=210kg/cm2 m3 10.95 310.00 3,394.50 9.5 2945 86.76% 1.45 449.50 13.24% 10.95 3394.50 100.00% 0.00%
01.05.02.02 Zapatas - Encofrado y Desencofrado m2 40.00 35.00 1,400.00 36 1260 90.00% 4.00 140.00 10.00% 40.00 1400.00 100.00% 0.00%
01.05.02.03 Zapatas - Acero kg 148.00 4.50 666.00 133.4 600.3 90.14% 14.60 65.70 9.86% 148.00 666.00 100.00% 0.00%
01.05.03 MUROS REFORZADOS
01.05.03.01 Muros Reforzados - Concreto f c= 210 kg/cm2 m3 44.91 400.00 17,964.00 44.91 17964 100.00% 0.00 0.00 0.00% 44.91 17964.00 100.00% 0.00%
01.05.03.02 Muros Reforzados - Encofrado y Desencofrado m2 174.15 40.00 6,966.00 174.15 6966 100.00% 0.00 0.00 0.00% 174.15 6966.00 100.00% 0.00%
01.05.03.03 Muros Reforzados - Acero kg 1,246.00 4.50 5,607.00 1246 5607 100.00% 0.00 0.00 0.00% 1246.00 5607.00 100.00% 0.00%
01.05.03.04 Placas - Concreto f c= 210 kg/cm2 m3 31.50 340.00 10,710.00 10.5 3570 33.33% 0.00 0.00 0.00% 10.50 3570.00 33.33% 66.67%
01.05.03.05 Placas - Encofrado y Desencofrado m2 337.50 40.00 13,500.00 104.2 4168 30.87% 0.00 0.00 0.00% 104.20 4168.00 30.87% 69.13%
01.05.03.06 Placas - Acero kg 3,144.00 4.50 14,148.00 2072 9324 65.90% 0.00 0.00 0.00% 2072.00 9324.00 65.90% 34.10%
01.05.04 COLUMNAS
01.05.04.01 Columnas - Concreto f c= 210 kg/cm2 m3 43.70 340.00 14,858.00 8.74 2,971.60 20.00% 8.74 2971.60 20.00% 80.00%
01.05.04.02 Columnas - Encofrado y Desencofrado m2 636.00 40.00 25,440.00 63.60 2,544.00 10.00% 63.60 2544.00 10.00% 90.00% SUSTENTAR CON PLANILLA DE METRADO
01.05.04.03 Columnas - Acero kg 6,165.00 4.50 27,742.50 1233.00 5,548.50 20.00% 1233.00 5548.50 20.00% 80.00% SUSTENTAR CON PLANILLA DE METRADO
01.05.08 CISTERNAS SUBTERRANEAS
01.05.08.01 Cisterna - Concreto f c= 210 kg/cm2 m3 19.85 450.00 8,932.50 0.00 0.00 0.00% 0.00 0.00 0.00% 100.00%
01.05.08.02 Cisterna - Encofrado y Desencofrado m2 156.96 40.00 6,278.40 117.72 4,708.80 75.00% 117.72 4708.80 75.00% 25.00% SUSTENTAR CON PLANILLA DE METRADO
01.05.08.03 Cisterna - Acero kg 815.00 4.50 3,667.50 611.25 2,750.63 75.00% 611.25 2750.63 75.00% 25.00%
COSTO DIRECTO
GASTOS GENERALES (6%)
UTILIDAD (6%)
SUBTOTAL
IGV (18%)
COSTO TOTAL
VALORIZACION DE OBRA
:EDIFICIO RESIDENCIAL "LAS AZUCENAS"
: JIRÓN LAS AZUCENAS
: VALLE HERMOSO
: SANTIAGO DE SURCO
: LIMA
: JOSB CONSTRUCTORES SAC
: ING JUAN JAIME EGÚSQUIZA DE LA CRUZ CIP. 127947
MONTO
METRADO % METRADO MONTO SOLES
METRADO P.U. PARCIAL SOLES
841.68 95 79959.6 0
720 17 12240 0
175.758 65 11424.27 0
360 65 23400 0
600 17 10200 0
8 4500 36000 0
8 6000 48000 0
24 2400 57600 0
24 450 10800 0
116 300 34800 0
3 5000 15000 0
1 7000 7000 0
1 21000 21000 0
342.62 250 85655 102.786 25696.5
7500 13 97500 2625 34125
1 15000 15000
1 1800 1800
2175320.35 1503630.46
130519.221 90217.8276
130519.221 90217.8276
2436358.792 1684066.12
438544.58256 303131.900736
2874903.37 1987198.02
ZACION ACTUAL VALORIZACION ACUMULADA
% por
% METRADO MONTO SOLES %
Valorizar
03.01.02.CAMARAS DE INSPECCION M3
03.01.02.Cajas de Desague de 12" x 24" M2
KG
03.01.02.ACCESORIOS PARA REDES
03.01.02.ADITAMENTOS VARIOS M3
03.01.02.Suministro e Instalacion de Registros de 2" M2
Registro roscado colgado tipo dado 3" KG
Registro roscado colgado tipo dado 4"
Registro roscado de bronce de 4" M3
Registro roscado colgado tipo dado 6" M2
Sumideros cromado de bronce de 2" KG
Sumideros cromado de bronce de 4"
Sombrero de ventilación de 2" M3
Sombrero de ventilación de 4" M2
*03.02 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO KG
03.02.01 SALIDA DE AGUA FRIA
Salidas para agua fría PN-10 de 1/2" M3
Salidas para agua fría PN-10 de 3/4" para calentador eléctrico M2
03.02.02 REDES DE DISTRIBUCION DE AGUA KG
03.02.02.Tuberia PVC SAP Clase 10 SP 1/2" empotrada
03.02.02.Tuberia PVC SAP Clase 10 SP 3/4" empotrada M3
03.02.02.Tuberia PVC SAP Clase 10 SP 1" empotrada M2
03.02.02.Tuberia PVC SAP Clase 10 SP 1-1/2" colgada KG
03.02.02.Tuberia PVC SAP Clase 10 SP 1-1/2" montante UND
03.02.03 ACCESORIOS PARA REDES
03.02.04 LLAVES Y VALVULAS M3
03.02.04.Válvula esférica de bronce de 1/2" M2
03.02.04.Válvula esférica de bronce de 3/4" KG
Válvula esférica de bronce de 3/4" llenado de cisterna
03.02.04.Válvula esférica de bronce de 1" control de departamento M2
Válvula esférica de bronce de 2" KG
Válvula de paso de 2"
03.02.04.Suministro e Instalacion de Llave de Jardin 1/2" M2
03.02.04.Suministro e Instalacion de Valvula Flotadora de 3/4" M2
M2
03.02.05 CAMARAS DE INSPECCION M2
03.02.05.Medidor General M2
03.02.05.Medidor por Departamento M2
03.02.05.Batería para medidores de 3/4" ML
MONTO
METRADO % METRADO MONTO SOLES
METRADO P.U. PARCIAL SOLES
841.68 95 79959.6 0
720 17 12240 0
175.758 65 11424.27 0
360 65 23400 0
600 17 10200 0
8 4500 36000 0
8 6000 48000 0
24 2400 57600 0
24 450 10800 0
116 300 34800 0
3 5000 15000 0
1 7000 7000 0
1 21000 21000 0
342.62 250 85655 102.786 25696.5
7500 13 97500 2625 34125
1 15000 15000
1 1800 1800
2391720.35 1545630.46
143503.221 92737.8276
143503.221 92737.8276
2678726.792 1731106.12
482170.82256 311599.100736
3160897.61 2042705.22
ZACION ACTUAL VALORIZACION ACUMULADA
% por
% METRADO MONTO SOLES %
Valorizar
COSTO DIRECTO
GASTOS GENERALES (6%)
UTILIDAD (6%)
SUBTOTAL
IGV (18%)
COSTO TOTAL
VALORIZACION DE OBRA
:EDIFICIO RESIDENCIAL "LAS AZUCENAS"
: JIRÓN LAS AZUCENAS
: VALLE HERMOSO
: SANTIAGO DE SURCO
: LIMA
: JOSB CONSTRUCTORES SAC
: ING JUAN JAIME EGÚSQUIZA DE LA CRUZ CIP. 127947
MONTO
METRADO % METRADO MONTO SOLES
METRADO P.U. PARCIAL SOLES
531869.27 519869.27
31912.1562 31192.1562
31912.1562 31192.1562
595693.5824 582253.58
107224.844832 104805.644832
702918.43 687059.23
ZACION ACTUAL VALORIZACION ACUMULADA
% por
% METRADO MONTO SOLES %
Valorizar
COSTO DIRECTO
GASTOS GENERALES (6%)
UTILIDAD (6%)
SUBTOTAL
IGV (18%)
COSTO TOTAL
VALORIZACION DE OBRA
:EDIFICIO RESIDENCIAL "LAS AZUCENAS"
: JIRÓN LAS AZUCENAS
: VALLE HERMOSO
: SANTIAGO DE SURCO
: LIMA
: JOSB CONSTRUCTORES SAC
: ING JUAN JAIME EGÚSQUIZA DE LA CRUZ CIP. 127947
MONTO
METRADO % METRADO MONTO SOLES
METRADO P.U. PARCIAL SOLES
103921.5 91921.50
6235.29 5515.29
6235.29 5515.29
116392.08 102952.08
20950.5744 18531.3744
137342.65 121483.45
ZACION ACTUAL VALORIZACION ACUMULADA
% por
% METRADO MONTO SOLES %
Valorizar
GASTOS
GENERALES Y
ITEM DESCRIPCION COSTO DIRECTODSCTO 1.20% SUBTOTAL UTILIDAD TOTAL S/IGV
12%
1 ESTRUCTURAS 0.00 0.00 0.00 - -
2 ARQUITECTURA 0.00 0.00 0.00 - -
3 INSTALACIONES SANITARIA 0.00 0.00 0.00 - -
4 INSTALACIONES ELECTRICA 0.00 0.00 0.00 - -
5 INSTALACIONES GAS 0.00 0.00 0.00 - -
- -
- -
- -
- -
- -
0.00 0.00