Anda di halaman 1dari 14

OTC 14168

Girassol: Drilling and Completion Experience gained through first 12 wells


Jean Lassus Dessus, TotalFinaElf E&P Angola/ Jorge Abreu, TotalFinaElf E&P Angola

Copyright 2002, Offshore Technology Conference • Carry out conceptual engineering as an input for field
This paper was prepared for presentation at the 2002 Offshore Technology Conference held in
• development scheme selection, including costs estimates
Houston, Texas U.S.A., 6–9 May 2002. and relevant data for project scheduling;
This paper was selected for presentation by the OTC Program Committee following review of • Provide assistance to the SPS project team for detailed
information contained in an abstract submitted by the author(s). Contents of the paper, as
presented, have not been reviewed by the Offshore Technology Conference and are subject to
engineering and preparation of subsea completion
correction by the author(s). The material, as presented, does not necessarily reflect any equipment;
position of the Offshore Technology Conference or its officers. Electronic reproduction,
distribution, or storage of any part of this paper for commercial purposes without the written • Carry out detailed well engineering, together with
consent of the Offshore Technology Conference is prohibited. Permission to reproduce in print
is restricted to an abstract of not more than 300 words; illustrations may not be copied. The
specifications for procurement of well equipment and
abstract must contain conspicuous acknowledgment of where and by whom the paper was tendering of services;
presented.
• Award rig contracts and follow up rig construction;
• Award service contracts for well equipment and all
Abstract services contracts required for the well construction phase;
The Girassol development, offshore Angola, will have 39 • Develop project documentation including manuals and
subsea wells. Development drilling and completion are being procedures; and
conducted from two dynamically positioned newbuild • Conduct operations from Luanda, Angola during the well
drillships. Twelve wells weren completed when this paper construction phase.
was completed.
The paper’s focus is on deepwater drilling and
Reservoir Description
completion activities, eg top hole and conductor jetting,
The upper Oligocene Girassol reservoir corresponds to
directional drilling, sand control, completion equipment, well distal turbidites deposited in channels extending over an area
productivity, etc. The paper also presents well construction approximately 18km long and 10km wide. Reservoirs are
performance, in terms of well durations and Non Productive shallow, the top of the reservoir being approximately 2,450m
Time, and offers insights into the success of the first below sea level, or 1,100m below the mudline.
year’s activity. The Girassol B System (Ref. 1) is made of three different
turbiditic complexes - B1, B2, B3. Eeach channel complex is
Introduction typically 50-100m thick, a few kilometers wide and many
The Girassol field was discovered in May 1996 by the kilometers long. There are also additional thin reservoirs with
GIR-1 well and appraised in 1997 by 2 additional wells. The large extension called Sheets complexes (Fig. 2). Each
field is located offshore Angola, 210km northwest of Luanda, turbiditic complex is separated from the others by regional
in water from 1,250-1,400m (Fig. 1). It is part of Block 17, seals which are correlated at a large scale over Girassol area.
awarded by Sonangol under a Production Sharing Agreement All these turbiditic complexes are normally pressured and
to the Contractor Group. were found to be oil bearing (32°API) within a regional
An integrated project team was set up early 1997 for this structural closure with common oil/water contact.
fast track project which had a very ambitious target for first After high resolution 3-D (3DHR) seismic data
oil, given the extent of the existing technological challenges. acquisition and interpretation, the Girassol architecture
The development scheme selected for Girassol is a full understanding was improved and each channel complex was
subsea development tied back to a spread moored Floating subdivided into different sequences separated by decametric
Production Storage and Offloading (FPSO) unit. The field shale prone abandonment phase which are potentially good
facilities were split into four packages for project management
vertical barriers. Each sequence is 10-30m thick, 1-2km wide
and contractual strategy considerations : the FPSO, the and a few kilometers long.
Umbilical and Flowlines (UFL), the Subsea Production Reservoir characteristics are well known from extensive
System (SPS) and the Wells Package. logging and coring data acquisition on first development
Drilling and completion (D&C) resources were mobilised wells. Fine to medium sands, generally well sorted, have very
in the first half of 1997. The scope of work given to the D&C good porosity (30-40%) and good permeability (K~1-5D),
team covers the full life-cycle of the Wells Package: medium to coarse sands have good porosity (20-30%) and
2 J. L. DESSUS, J. ABREU OTC 14168

very good permeability (3-10D), very coarse sands and guidebases and connected to the subsea network in a ‘daisy
conglomerates have fair porosity (15-20%) and fair chain’ configuration. Oil producers are connected to two-well
permeability (100mD-1D). manifolds installed on suction anchors, while injectors are
connected to tees installed with the injection lines.
All reservoirs are constituted of highly unconsolidated sands The subsea layout includes 10 production manifolds and
which required all the wells to be completed with sand control 16 injection tees. This design results in 24 different drilling
devices. centers across the field, including nine different manifold
The main complex is B3 targeted by all of the first locations and 15 locations for the injection tees. The design
development wells. The wells have high productivity, up to provides the flexibility to tie-in additional wells either by
40,000b/d) owing to the very good reservoirs characteristics. extending the subsea network, or by connecting a third well to
Pressure maintenance of the field will be achieved via sea a production manifold using a special Production Guide Base
water injection and re-injection of produced gas for a limited (PGB) arrangement.
period of time. Such a high number of drilling centers requires frequent
infield movements of the drilling units. Additionally, there is a
Main Challenges large amount of critical equipment on the seabed - 70km of
The Girassol project, owing to its water depth and to the umbilicals, 45km of production lines, 29km of injection lines,
size of the reservoir in a new geological area, represents one manifolds, tees, etc - which renders the use of moored drilling
of the most ambitious field developments underway. It units not practical. Dynamically positioned (DP) drilling units
combines a high degree of technological innovation and were therefore selected for the development.
aggressive cost and schedule targets. Production start-up took The wells are connected to manifolds or tees by rigid
place in December 2001, five and a half years after discovery jumpers (Fig. 3). The PGB has a receptacle which provides
and three and a half years after project sanction. guidance and support for the rigid jumper. The initial jumper
design with a Z-shape required a distance of 35m between
The main challenges of the Wells package were: well and manifold. An initiative was launched to reduce the
• deliver high productivity wells (20,000-40,000b/d well overall weight of the jumper and associated spreader bar to
potential), given the costs of well construction in such facilitate offshore installation. The new jumper design has a
water depths; U-shape and the well location is now 15m from the manifold.
• meet the specifics constraints required by flow assurance The rigid jumpers are assembled in Angola from
issues in the deepwater production environment (see prefabricated sections according to a subsea metrology
section below on completion design); conducted once the xmas tree has been installed. This
• design reliable well solutions in order to deliver steady jumper construction method requires tight tolerances on
production while minimizing workovers required for wellhead position :
mechanical failures,
• drill and complete about 10 wells before first oil in order to • X-Y wellhead co-ordinates : 2.5m radius
provide sufficient potential at first oil and rapid ramp up to • PGB heading: +/- 5°
production plateau (200,000b/d); • Inclination: <1° from vertical
• install complex subsea completion equipment in water • Wellhead elevation : 2-4 m above seabed.
depths where the industry has had little experience; and
• execute the drilling completion program with low Non The duration of the drilling and completion campaign for
Productive Time (NPT). It was recognized from project the 39 development wells is expected to be six rig years. In
start up that the management of NPT for subsea order to provide sufficient production capacity at first oil, it
completions was a critical area as there was a high cost was critical for the project to begin drilling approximately 18
exposure, based on anticipated rig operating costs and NPT months before the target date, ie develoment drilling had to
figures derived from industry benchmarks (Ref. 2). start end of year 1999. It was also necessary to have two
drilling units working concurrently to meet the production
The requirement to build and commission two new objectives.
drillships for this project exaggerated the schedule challenge.
The geographical spread of project participants with numerous Contractual Strategy
interfaces between the various contract packages exacerbated
the challenge. The D&C team was based in France and later in Drilling Units. The main element of the contractual strategy
Luanda, Angola. The SPS package was manufactured in for the Wells package was related to drilling units. A market
Norway and the rigs were constructed in Korea. survey conducted in early 1997 concluded that there were a
limited number - approximately 20 - of rigs technically
Field Architecture suitable for the water depth of the Girassol environment and of
The 39 subsea wells –23 producers, 14 water injectors these units, many were under long-term contracts. It was
and 2 gas injectors - are to be drilled from standalone decided to issue a call for tender early in the project phase to
OTC 14168 GIRASSOL: DRILLING AND COMPLETION EXPERIENCE GAINED THROUGH FIRST 12 WELLS 3

provide sufficient time to build new units and extend the through a learning/debugging period with the sophisticated
choice beyond the limited existing fleet. subsea completion equipment and associated tooling. This
Three rig contracts for newbuild units were awarded by strategy was devised to allow a build-up of confidence with
TotalFinaElf Angola between September 1997 and March conventional downhole solutions in the areas of equipment
1998 for exploration and development work on Block 17. The and tooling, procedures and offshore crew experience before
construction schedules for these units - from 18 to 23 months intelligent completions would be implemented.
- were ambitious with expected deliveries between August and The existing vision of the development is that a few
November 1999. One rig contract was eventually cancelled ‘intelligent’ completions will be installed in the last
due to late delivery. The two units, which would operate on development wells.
Girassol, were built in South Korea and were delivered with
about a six-month delay. This delay did not affect the project Equipment Testing Cycle. The importance of a thorough
as other packages had also faced similar delays. The testing cycle in this deepwater environment was recognized as
completion of the required number of wells was still expected the cost exposure can escalate quickly to millions of dollars.
by first oil. This is particularly relevant for downhole completion and
An operator team dedicated to the follow-up of the rig subsea equipment due to the level of technical complexity and
construction was mobilised. The main objectives of this team lack of relevant field experience for prototypes developed for
was to make sure that the delivery schedule remained in line the project. This issue is less critical in the drilling area which
with project expectations and that technical capabilities were utilizes more conventional equipment.
according to contract and project specifications. A testing strategy was developed with the aim to avoid
Construction and start-up of newbuild units within a tight ‘infant mortality’, ie early failures in equipment life, and high
schedule was recognized as a challenge and a risk element due non productive time (NPT) created by basic issues, such as
to the potential impact on project objectives, ie cost, schedule poor equipment interfaces or ‘dumb iron’ which does not
and production ramp-up. screw together.
Special emphasis was therefore placed on preparation of Besides the factory acceptance testing (FAT) which is
rig commissioning and acceptance in order to avoid a long and part of the quality program for procurement of every
difficult ‘shakedown’ period (Ref. 3 ) equipment item, the testing strategy incorporated the
following program:
Wellhead Equipment. This equipment was included in the
scope of supply of the SPS to be delivered by the subsea • Qualifications tests: For components developed
supplier. The project recognized that there are critical specifically for this project or for existing equipment
interfaces between the wellhead and subsea completion which had undergone modifications in size, rating or
equipment, eg tubing hanger and xmas tree. These interfaces functionalities. Conducted on one representative
are made more significant in the Girassol case by the vertical equipment item;
tree design which requires accurate orientation of the tubing
hanger and xmas tree. • Integration tests: Conducted to verify the interfaces
It was decided that a single supplier would deliver both the between various subassemblies and test the various
subsea completion equipment and the wellhead equipment components as a single system. Conducted on one set
allowing better management of these interfaces and reducing of equipment;
associated risks.
• Stack-up testing: To verify interfaces between different
Design and Testing Philosophy systems; and

Design philosophy. The high well costs which occur in the • Deepwater trials: Conducted at specified operating
deepwater play quite often drives the well design towards depth (1,800m) to verify functionality under actual
complex solutions. Multizone completions with selective operating conditions.
production from various intervals is frequently desired from
these expensive wells. The purpose of this paper is not to provide an exhaustive
Without adding the complexity of ‘intelligent’ solutions, list of the various tests. This philosophy was adopted to a large
Girassol completions were recognized as a technological extent for the subsea completion equipment (Ref. 2). A few
challenge due to the water depth and to the ‘fast-track’ examples relevant to the Wells package are given as
approach allowing little time for engineering and qualification an illustration
of tools and equipment.
It was decided to address all requirements, in particular • Qualification tests were conducted on several completion
flow assurance issues, but to avoid complexity. Installation of components, for instance the 5-½in tubing retrievable
an ‘intelligent’ completion would not be allowed during the surface-controlled subsurface safety valve (TRSCSSV),
first year of operations. The philosophy was to address basic the 10-¾in completion packer, the encapsulation of
engineering issues in the limited time frame available and go
4 J. L. DESSUS, J. ABREU OTC 14168

auxiliary lines to verify compatibility with the gelled oil Final conductor design was established at 36in OD by 2in
packer fluid, etc. wall thickness for the first 25m meters and 36in OD by 1in
wall thickness for the joints set deeper. A setting depth of 60-
• An integration test was conducted on an onshore test well 65m below the mudline was engineered in order to withstand
to simulate a real completion. This involved running and the axial loads generated during well construction.
stacking a gravel pack assembly, an isolation valve and an
upper completion. The equipment was subsequently Top Hole Section. There are no specific hazards associated
retrieved to allow the testing of intervention and retrieving with the top hole section, ie no shallow gas or water flow. The
tools required for workover or contingency scenarios. top hole section can be drilled safely down to 600m below the
Some equipment modifications resulted from this mudline riserless.
integration test. In addition to the technical value of such a Installation of the 36in conductor utilizes conventional
test, there are added benefits, such as training and team jetting technique with a downhole motor and a drill ahead tool.
building of contractor and operator personnel. The PGB is run together with the conductor pipe. Once the
required conductor penetration has been reached, the drill
A good example of a stack-up test is the physical ahead tool is released in order to proceed with the subsequent
interfacing of the BOP with the the PGB. Although 26in section down to 400–600m below the mudline.
verification of CAD drawings had been conducted, this type of The jetting technique was chosen as it will save rig time
test has allowed the identification of physical clashes between compared with a drill-and-cement technique for the conductor
the BOP of each rig and the PGBs. This was easily solved by pipe. The drill-ahead feature will save an additional round trip
minor modifications to the PGB structure. This shows that this of the drilling BHA. Only one re-entry - the 20in casing - is
type of test is a cheap, valuable investment, when compared required with this technique.
with a stack-up on the first well with its potential for millions
of dollars of cost implications.. Casing Design. The casing design below the 20in depends
An example of a deepwater trial were those carried out on upon three design parameters: occurrence of shallow reservoir,
the ROVs to be used on the three drilling units. ROV costs are well path requirements,and well types.
a small fraction of a D&C operation. However ROV reliability
is a critical issue as deepwater operations are highly dependent Shallow reservoirs. In the Girassol area, there are several
on ROV availability. A major emphasis was placed on this shallow reservoir systems of Miocene age, overlying the
issue and involved a full cycle of tests from FAT to deepwater Oligocene system targeted by the development. These
trials, including interfacing of tools with the subsea system Miocene systems are usually hydrocarbon bearing. They are
supplier. The ROV spreads were installed while the rigs were located 600-900m below the mudline and can have significant
in the shipyards and deepwater tests were conducted several vertical thickness and large surface extensions.
weeks before rig delivery in Angola. The same philosophy of Most of the Girassol well paths cut through one or several
deepwater testing ahead of rig arrival in Angola was applied to hydrocarbon bearing reservoirs of Miocene age. Several of the
the BOPs (Ref . 3). Girassol wells will penetrate the Miocene reservoirs of the
Dalia field on the flanks of this field which is adjacent to
Well Design Girassol. These Miocene reservoirs are normally pressured,
but have very low frac pressure. For mud weight, there is a
Conductor Pipe Design. The conductor pipe design is of very narrow margin between pore pressure and frac pressure
particular interest in the Girassol environment : in the Miocene reservoirs. This mud weight margin issue is
more critical for the shallower Miocene systems. This dictates
• It must be able to withstand the high bending loads which the requirement to set an intermediate casing (13-⅜in)
can be generated during rig drift-off; whenever Miocene reservoirs are encountered, before drilling
• Wellhead displacement must be compatible with the rigid the Oligocene pay.
production jumper deformation envelope. The production
jumper is not installed during the initial drilling and Well paths. In the initial field development plan, the
completion phase. However this scenario is relevant for average horizontal departure of wells was low, typically 300m
workovers and or re-drills, when the rig BOP is latched for injectors and 600m for producers. A cost reduction
onto the wellhead, the latter being mechanically linked to a exercise was performed in order to optimize the combined cost
production manifold via the PGB and production jumper; of the subsea network (flowline hardware and installation
• Soil at the mudline consists of normally consolidated costs) and of the development wells.
organic clay of high plasticity with limited shear This exercise led to a reduction in the extent of the subsea
resistance. Soil data for conductor and anchor design network, which resulted in higher well step-out distances. An
resulted from geotechical surveys involving several extreme example is the last injection well drilled to date,
shallow boreholes (20-25m) and one deep which has a total horizontal displacement of 3,000m.
borehole (103m). The visualization of the Girassol reservoirs has evolved
significantly from the project start. The resolution of seismic
OTC 14168 GIRASSOL: DRILLING AND COMPLETION EXPERIENCE GAINED THROUGH FIRST 12 WELLS 5

images has been greatly enhanced by the acquisition of a 3D open hole completions. It was concluded that screen-only
high resolution seismic. For example, four separate units have were not suitable for the finer sands, but had to be dedicated to
been identified within the B3 complex. The spatial a limited range of facies. Wire wrapped screens were selected
arrangement of these units is such that they are partially due to their ‘self cleaning’ ability when compared to premium
stacked. Placement of high angle or horizontal wells is screens, and slot sizes were optimized from testing with
constrained by the spatial arrangement of these units or by the representative samples of the finer allowable facies.
overall shape of the meandering channels. Consequently, there Completion of horizontal or high angle wells with wire
are severe constraints on the well path within the reservoir wrapped screens is not possible in all sequences, but must be
section with little flexibility to modify trajectory heading. As a dedicated to suitable facies. Well planning requires close
result, 3-D well paths were frequently required to meet the cooperation between the geoscientists/geologists, the drilling
target definition objectives. and the completion/sand control engineers. Whenever fine
Overall, well trajectories are significantly more complex facies are encountered in a high angle well, they are not
than initially anticipated with 3-D well paths being quite completed, but left behind pipe and external casing packers.
frequent and a tendency to increase step-out distances. Such Horizontal drains are typically 500-1,000m long and are
wells involve complex directional work, which results in a completed with 6-⅝in screens in order to limit friction
reduction of the possibility of eliminating the 13-⅜in from the pressures in the screen base pipe, thus allowing to get flow
casing architecture. contribution from the far end of the drain. A 9-½in open hole
Of the 15 first wells drilled, the intermediate casing has (10-¾in production casing) was preferred for this size of
been eliminated in only two low-angle well injectors. In those screen in order to increase annulus clearance and to facilitate
cases, a 20in by 13-⅜in casing has been set below the installation in the 3-D well paths.
36in conductor.
A 9-⅝in cased hole gravel-packed completion is
Well types. The production casing size is dictated by preferred where:
productivity or injectivity requirements as described in the • Finer facies are the main target;
completion design section. For the majority of the wells • Laminated sands with low net to gross are expected; and
(horizontal oil producers, gas injectors, water injectors • Expected reservoir mobility is within the technical limit
equipped with downhole gauges), there is a requirement to run of frac pack technology.
a full string of 10-¾in casing. For other wells, such as
conventional oil producers or water injectors without gauges, a Injectors. Water injectors are completed with 5-½in wire
tapered 10-¾in by 9-⅝in is installed with a 10-¾in length of wrapped screens in 8-½in open hole. Gas injectors have
100-500m according to downhole safety valve requirement horizontal drains and are completed with 6-⅝in screens in a
and placement. 9-½in open hole.
For the wells where a full 10-¾in string is required, there
is an issue related to hydraulic limitations during the casing Upper completion design (Fig. 4)
running and cementing operations. The narrow hydraulic
margin is not compatible with the tight annulus clearance Tubing Hanger. The 5in by 2in tubing hanger has two
between the 10-¾in casing and a 12-¼ in open hole size, electric and four hydraulic penetrations. These penetrations
especially for the wells which have the longer departures. For were specified to meet downhole function requirements
the wells to be cased with 10-¾in casing, the 12-¼in hole is as described below, but also to allow installation of
enlarged to 13-½-14in in order to reduce surge effects while intelligent completions.
running casing and friction losses while cementing. Various
techniques have been experienced to open the 12-¼in hole and Safety Valves. The requirement for safety valves in a
are discussed in the operation section. deepwater environment was reviewed and debated longly
within the project group. It was finally decided to install
Lower Completion Design TRSCSSV in all producers and gas injectors.
The lower completion refers to the sand control equipment In oil producers, the 5-½in TRSCSSV are set at 500m
installed across the reservoir. Sand control is a major driver in below the mudline, which corresponds to a geothermal
design of both the sand face and the overall well architecture. temperature of 20°C. This ensures that the valve will remain
outside the hydrate formation domain during a long shutdown.
Oil Producers. Girassol utilizes two different completion The resulting setting depth for the valves is typically 1,800m
techniques for oil producers: open hole with screen-only in below sea level, which requires very specific design features
horizontal wells and gravel-packed completions in low for the valve.
angle wells. Water injectors are completed in the oil pool and have the
Grain sizes vary very widely along the 12 facies types potential to flow naturally. Such wells have no surface
identified in the Girassol Oligocene reservoirs: from very fine controlled safety devices but are equipped with non return
(less than 80 microns) to very coarse (centimetric). Extensive mechanical valves which are shifted open by injection flow.
lab work and studies were conducted to qualify screens for
6 J. L. DESSUS, J. ABREU OTC 14168

These valves serve the purpose of a safety device, but also reservoir and completion string of producers. There is still a
prevent backflow during injection shutdown, which is possibility for other types of scales and wax deposition. A
detrimental to injection potential. They are set deep in the chemical injection line has been incorporated in the
vicinity of the tubing shoe in order to minimize the completion design to allow pumping of adequate inhibitors,
compressible volume below the valve. In addition, they reduce should it be required at some point in time over the production
hydrate formation risks in the upper section of the tubing by life of a well. Special attention was paid to the design of this
avoiding gas migration during long shutdowns. line to avoid plugging (a 5/8in OD line in Incoloy 825 was
selected) as the latter could become of prime importance for
Tubing Design. The vertical xmas tree has an internal flow assurance.
production bore of 5in which sets limitations for flow control
equipment and intervention tools to be conveyed on wireline Other Completion Features. Some other completion
or coil tubing. Hence, completion items are 5-½in tubing size. features are worth mentioning.
A mixed 7in by 5-½in string is run on most of the wells
(horizontal producers, gas injectors, water injectors) as Separation from lower completion. There is no
outflow studies revealed a significant flow performance mechanical continuity between the lower and the upper
improvement relative to a full 5-½in string. A 10-¾in casing completion. The rationale behind this design is to avoid the
is required for 7in tubing completions surrounded by requirement for spacing out the upper completion which is a
auxiliary lines. time consuming operation in the Girassol deep water
environment. Also, a mechanical continuity could create
Downhole Monitoring. All producers and a limited number additional difficulties in orienting operations of the tubing
of injectors are equipped with downhole pressure and string which are required during tubing hanger installation. In
temperature gauges. Tandem gauges are installed to provide order to facilitate running of wire line tools or coil tubing tools
redundancy. These gauges are multiplexed downhole, so only inside the gravel pack assembly, a scoop head assembly is
one downhole cable is installed. The gauges are integrated into installed above the gravel pack packer.
the subsea control system, via the xmas tree subsea control
module, allowing downhole data at the FPSO. Deployment of a mechanical barrier. An isolation valve
is installed above the gravel pack/sand control completion.
Flow Assurance Issues. These aspects are of the utmost The purpose of this mechanical barrier is twofold:
importance in the deep water environment owing to the • To allow installation of an under-balanced packer fluid;
potential for hydrate formation, wax and scale deposition. The • To focus on tubing hanger installation without having to
low reservoir temperature, coupled with the long network of worry about well control aspects or a welI situation
flow lines laid in 4°C exacerbate this issue. Designing and involving fluid losses. It is worth mentioning here that the
installing a reliable sand control exclusion device is part of the tubing hanger installation is a technically difficult task
flow assurance strategy (refer to lower completion section). involving full-bore tools (18in OD) and a sophisticated
Electro-hydraulic control system. The presence of a tested
Thermal insulation. Gelled oil mixed from low toxicity mechanical barrier allows to focus on the tubing hanger
mineral base oil is used as a packer fluid in production wells. installation without adding the trouble of a potential
This fluid has been selected to reduce thermal losses and unstable wellbore situation.
hence maximize flowing temperature at the wellhead for flow
assurance considerations (prevention of wax deposition in sea The isolation valve is opened remotely by pressure cycles,
lines and risers). Targeted flowing temperature at the wellhead with contingency opening by wireline or coil tubing conveyed
is a minimum of 57.5°C in order to reach the FPSO with at shifting tools.
least 40°C, which is the limit for wax deposition.
Limited wireline operations. The philosophy of the
Gelled oil has a thermal conductivity of 0.13 W/m.°C design is to minimize wire line operations. Girassol
compared to 6.00 W/m.°C for brine. Cross couplings completion equipment allows most completion operations
protectors with centralizing pads are used on these wells to without the requirement to set wire line plugs. A valve ran
minimize contact of the tubing with the production casing below the tubing string packer allows to pressure test the
wall. The gain in temperature created by the thermal insulation tubing assembly, while allowing reverse circulation/tubing fill
depends upon flow rate and BSW mainly. From simulations up, and to set the packer. The valve is eventually locked open
gelled oil allows to increase flowing temperature by 4°C at by pressure cycles.
1000 M3/day and by 7.2°C at 500 M3/day. In a normal configuration, the only wireline operations
consists in setting/retrieving a plug in the production bore of
Scales and wax. The Girassol formation water contains the tubing hanger in order to provide an additional barrier for
high contents of strontium and barium. The injected sea water BOP retrieval. Wireline is used to set non-return valves on
is processed in order to remove sulfates, which mitigates the water injection wells and also has applications in contingency
risk of barium and strontium sulfates deposits in the near scenarios
OTC 14168 GIRASSOL: DRILLING AND COMPLETION EXPERIENCE GAINED THROUGH FIRST 12 WELLS 7

Full bore design. Girassol completions incorporate affected by poor reliability of components in the the BOP
selective nipples with a minimum 4.562in ID. Completions are control system, requiring four roundtrips of the lower marine
not really of a monobore type as the majority of the wells have riser package. This was addressed by a quality plan and by a
a mixed tubing string 7in by 5-½in”. Some of the wells also thorough preventative maintenance plan developed by the rig
have a 6-⅝in open hole sand control completion across the contractor. BOP audits by a specialized third party have been
reservoir (horizontal oil producers and gas injectors), while regularly scheduled by TotalFinaElf. In addition, improved rig
other have a 5-½in sand control interface (gravel packed contractor performance has resulted in NPT being reduced to
producers and water injectors). below 2% on a monthly basis (Ref . 3).
This full bore design will provide some flexibility for Difficulties were encountered initially in setting the metal-
reservoir management by enabling shut-off of lower zones (by to-metal seal assemblies around the 13-⅜in and 10-¾in casing
setting plugs) and isolation of upper zones in a limited number hangers. The wellheads supplied for Girassol have been used
of well configurations (installation of straddles in cased in Angola by TotalFinaElf for exploration wells since May
hole completions). 1999, or more than one year before development drilling
began. The philosophy was to gain experience with this
Operations in Angola equipment before starting development wells.
Installation of the seal assembly in one trip has not been
The two drillships have been operating in Angola since mid successfull in the first wells. The seal assembly was usually
2000. One of the units has been dedicated to Girassol pulled with the running tool and it was observed that both of
development since that time. The second vessel began with them were usually packed with formation cuttings. Two
exploration work and has been assigned to Girassol additional runs - including one for cleaning - were required for
development since beginning of 2001. installation of this piece of equipment.
At the time this paper is written, 12 wells have been drilled This issue has had a high priority - from both the
and completed. operator and the subsea supplier – as rig time required for two
trips at 1,400m is significant. In two instances, a week of rig
Well durations. A significant reduction in well durations was time was required to solve a problem when a component of the
achieved during the drilling of the the first wells (Fig. 5). seal assembly was lost in hole.
Some caution must be exercised, though when looking at the Several modifications to the equipment have been
evolution of well durations. Wells are not directly comparable implemented. The first step consisted in increasing flowby
due to variations in types (low angle to horizontals producers, areas around the casing hangers and in the running tool. Hole
injectors), and in the scope of each well. With only three cleaning procedures and cementing procedures were also
exploration wells drilled before the development, a strong modified to eliminate as much as possible potential for
emphasis was placed on data acquisition during the first two plugging the equipment. Flowby areas were increased twice
development wells. This involved significant rig time for and resulted in a reduced service pressure of the wellhead
drilling pilot holes, coring the entire interval and acquiring a equipment (to 10,000psi instead of 15,000psi), which is not an
full suite of logs. On the first well there was also a deepwater issue at Girassol. Modifications to the seal assembly were
trial of the tubing hanger and associated landing string (Ref 2). also conducted. However, the increase in flowby areas did not
significantly modify the success ratio of seal assemblies
However, an improvement in performance has contributed to installation in a single trip. Despite all the modifications
the reduction in drilling time achieved over the first wells. conducted on flowby areas, the overall success ratio of single
The main elements, which have contributed to performance trip installations remained low: 50% over 22 seal assembly
improvement, are: installations.
• A large reduction in NPT (Fig. 6) The running tool was evntually modified to incorporate a
• An improved learning curve thanks to the knowledge washing facility. Once a cement job is completed, the tool is
acquired over the wells and to the continuous moved into the washing position to jet drilling fluid in the seal
development and fine tuning of specific procedures; assembly area. The tool is then moved to the seal assembly
• Utilization of recent technology; setting position. The addition of this washing feature has
• An improvement in overall rig performance; allowed a dramatic improvement, increasing to an 87%
• Simplification of procedures; and success rate in single trip installations since it was introduced
• Reduction in data acquisition. during the last 15 installations.

While it is not possible to list in detail all the technical Development of specific procedures. Installation of
issues, we provide here below some relevant examples or conductor pipe by jetting is a good example of the
highlights of this process : development of a specific procedure and tooling. As
mentioned earlier, there are tight tolerances for wellhead
Non Productive Time: NPT reduction was achieved by position, ie, X-Y coordinates, elevation, inclination and
focusing efforts on major events. The first well was heavily heading. The conductor pipe supports the PGB which has to
be oriented in a predefined heading.
8 J. L. DESSUS, J. ABREU OTC 14168

A removable ROV docking platform is deployed together a function of depth was developed. Although pulling the
with the PGB. The ROV is equipped with an instrumentation conductor is no longer required for heading control, it is
package (positioning beacon, gyro, altimeter, depthmeter and necessary to achieve the specified conductor penetration. The
roll/pitch sensors) which allows to compute in realtime the number and amplitude of cycles has now have also been
four parameters. specified and limited.
An array of frames covering the entire field has been Overall, besides one early problem on the third well,
installed on the seabed in order to provide common reference conductor installation by jetting has been very successful and
points for all subsea positioning. The absolute coordinates of has achieved the accurate positioning within the tight
these frames were recorded during array installation and are tolerance band.
known very accurately. Each contractor deploys its own
beacons in frames located near to the targeted working area. Utilization of recent technology. The 12-¼in sections are
For wellhead positioning, a long baseline method is utilised, ie enlarged to 13-½-14in for some specific type of wells as
wellhead position is available in realtime by measuring the described in the casing design section.
distances between the ROV sensor and four frames of the Various techniques have been tried to achieve hole
array. When spudding the well, adjusting the conductor shoe opening while drilling and save a dedicated trip with a hole
coordinates to meet the required position accuracy takes less opener which has a time impact of two or three days rig time.
than one hour. The challenge is that those sections are directionaly drilled and
Three wells were drilled before the array was available. that some of the wells have 3-D well paths with combined
For these wells, a calibration of the four beacons dropped on build and turn.
the seabed was required in order to obtain the required Bi-center bits ran in combination with conventional
accuracy of their absolute coordinates. This calibration steerable assemblies have demonstrated limitations in the dog
process takes typically 36 hours. Although there is some rig leg severity which could be achieved in our particular
time involved to install four beacons in frames with the rig’s environment (1.3°/10m). The preferred technique is to use a
ROV, the array system allows a savings of a minimum of 24 rotary steerable drilling assembly with a PDC reamer. The
hours per well, compared with the dropped beacon solution. PDC reamer is usually placed behind the Logging While
On the first conductor installations, during the jetting Drilling tools to acquire geological information in 12-¼in and
process, the ROV was docked periodically on the PGB to not compromise tools response. This simultaneous drilling and
verify heading. It was observed that the conductor heading hole opening technique also makes it possible to drill float
was moving away from target during jetting. Corrections of equipment (the PDC reamer being activated once in the open
heading had to be conducted at various steps, by rotating the hole) and provides superior hole cleaning capability thanks to
drillpipe from surface. These corrections were difficult to the continuous rotation of drillpipe.
achieve. The conductor had to be pulled to break the skin When directional requirements are moderate, we have had
friction between soil and pipe and allow rotation. The rotation also successful applications of a PDC near-bit reamer placed
process was difficult to initiate and control within the required below a conventional steerable BHA.
10° azimuth band. Pulling and rotating the pipe was also
detrimental to the objective of the jetting operation, which is Improvement in rig performances. Rig tripping performance
to build up high skin friction, in order to establish the has rapidly increased from 400m/hour to 800m/hour or more
foundation for the well. (Ref. 3). Although there was a lot of focus placed on the
On the third well, as the result of these corrections, the commissioning and acceptance of pipe handling equipment, a
conductor sank below the minimum wellhead elevation on the period of two months was required to reach competitive
two jetting attempts and had to be retrieved. On this particular performances.
well, the conductor was finally installed using a drill-and- One element of this improvement is the familiarization of
cement technique. About 10 days of rig time were lost during the rig floor crews with the sophisticated controls and
conductor installation on this well. technology. These crews have had extensive training sessions
In order to provide heading control for the conductor on a simulator. However it took some weeks before they could
pipe, it was attempted to keep the ROV docked on the feel comfortable with the real working environment.
platform and to use the thrusters of the vehicle to Another component of the improvement was the
counterbalance rotation effects induced during jetting. This adjustments required to fine tune the software or various
process has been very successful. The 100hp ROV vehicle, mechanical and hydraulic settings. Finally, the reliability of
working in auto heading mode, was able to keep the entire components and more particularly sensors was greatly
conductor and PGB assembly in the desired azimuth. Since improved.
this methodology has been used we have been able to achieve BOP tripping performance has been excellent from the
the required heading within 1° of angle and we have not had to beginning (Ref. 3) owing to the riser connector design.
re-orient the conductor with drill pipes. Specific functions or features are available from the
Guidelines for jetting have also been developed in order to sophisticated controls (for instance, auto rate of penetration)
assist offshore staff in conducting this delicate operation. An and have a direct impact on the quality and efficiency of
envelope providing minimum and maximum applied weight as operations. Crews are learning how to use the possibilities
OTC 14168 GIRASSOL: DRILLING AND COMPLETION EXPERIENCE GAINED THROUGH FIRST 12 WELLS 9

offered by the controls and it is likely that we have not yet perod of time through the permanent well completion system.
explored all the functionalities of the system. Well productivity is now also available from the two months
of production history which is available at the time the paper
Simplification of procedures. Some specific practises have is written.
been challenged in order to cut rig time. For instance, the The reservoir section of the horizontal producers is drilled
requirement to conduct formation integrity tests at the with oil-based mud. Screens are run in the drilling fluid with
beginning of each section was challenged as the data acquired blank pipe and external casing packers deployed to isolate
on the first 10 wells are very consistent and provide a good shaly sections. Stringent mud control and conditioning
match with a theoretical model. Another example is the procedures have been developed in order to make sure that the
suppression of the wiper trip which was conducted at the end mud and mudcake would flow back easily through the screens
of the 26in section. and not induce any plugging or formation impairment.
Corporate technical rules are also challenged. An example Productivity indexes are in the 300-500m3/d/bar range for
of this is the requirement to pressure test BOPs at every casing horizontal wells (Fig. 7 ). These wells have a high potential
point, given that the sections are fairly short and usually and are limited to a production of 35,000b/d for reservoir
limited in time to less than a week. management purposes and/or for erosion considerations. They
have allowed the field production rate to rise very quickly,
Data acquisition. There has been a rapid evolution towards although the number of wells available at first oil was limited
Formation Evaluation While Drilling (FEWD). On the first to seven. Production logging tools have been run on coil
wells, a full suite of electric logs involving three to four runs tubing in three horizontal wells and have demonstrated a
on cable was acquired. Quality of FEWD information proved contribution of all intervals with smooth profiles. This
good enough to reduce significantly the requirement for experience confirms that this type of completion is well suited
conventional logs. There is now usually no more than one run to the massive and clean sands of the Girassol turbiditic
of electric logs on cable (or drillpipe for horizontal wells) in environment.
order to complement the information which cannot be The first development well was completed with a frac pack
acquired through FEWD, ie vertical seismic profile, reservoir stacked above an open hole gravel pack (OHGP). Significant
pressure information and nuclear magnetic resonance. problems were encountered during the OHGP leading to very
As production start-up occurred recently, there is now a high downtime (25 days) and eventually to a poor quality job
requirement for more frequent pressure information in order to with partial coverage of the open hole by gravel. Although this
derive dynamic reservoir information, i.e reservoir depletion well has a high skin factor, its productivity index is around
due to communication between wells. 150m3/d/b which means that its potential is in excess of
Some FEWD tools modifications, such as the neutron 4,500m3/d/b (28,000b/d). Extensive work has been conducted
density, were required due to the specific 9-½in hole size. over the past months to correct the problems encountered
FEWD procedures have been fine-tuned which has allowed during the OHGP, including work on water-based fluid
for a reduction almost to zero of the amount of reaming time inhibition and mobilization of special equipment, such as
required for data acquisition. screens with shunt tubes. To date, no additional OHGP has
been attempted.
Design changes. Sand control design has evolved drastically Two other wells have been completed, each with two cased
since the initial plans. Completion of producers was initially hole frac packs. These jobs have been pumped in very high
based on gravel pack solutions with a combination of open mobility zones (one well has a mobility of 100,000md.ft/cp,
hole techniques (OHGP) and cased hole techniques. This while the other well has a mobility of 200,000md.ft/cp). This
design has evolved towards a significant proportion of high mobility domain is generally considered to be beyond the
horizontal wells completed with wire wrapped screens. A step technical limit of frac pack application. Excellent results were
by step approach was developed to validate the concept. This obtained on these two wells with very low skins (between 0
evolution created some procurement issues as delivery of and 2). These wells have allowed to extend the limit of frac
equipment in a remote area is quite a long process. pack application further in the high mobility domain and
There is a tendency to drill more complex wells than are considered as a breakthrough in the technology of frac
initially anticipated with longer departures or 3-D well paths. pack stimulation.
These design changes are inherent in the ‘fast track’ approach
and to the limited number of exploration wells which were Completions. There has been no significant problem or major
available. They require a high reactivity. design flaw related to completion equipment. The testing cycle
approach has helped in preventing a ‘train wreck’ involving
Well Productivity. Two different types of completion have weeks of downtime.
been used in the producers drilled to date. Five horizontal The NPT for completions has been somewhat below
wells were completed with screen-only completions and three industry benchmarks for subsea completions in shallower
other wells with gravel-packed completions. water depths (30%). NPT during tubing hanger installation has
In general, well productivity has been high. Production averaged 24% over the first 12 wells, accounting for down
wells have been cleaned up and tested to the rig for a short time from all sources, ie the downhole completion equipment
10 J. L. DESSUS, J. ABREU OTC 14168

(located below the tubing hanger) and the equipment provided Human Resources
by the subsea supplier. About half of this downtime has been The integrated project approach has achieved good
attributed to subsea equipment. In xmas tree mode, NPT has management of the many interfaces. One highlight has been
averaged 22% from all sources with one-third attributed to the secondment of five personnel from the WELL team to the
subsea equipment (Ref. 2). SPS team (Ref. 2) to work alongside the other SPS team
One particular piece of equipment has caused recurrent members. The integration has assisted discussions on
problems which have not been solved to date. The isolation installation issues (rig NPT) together with capital (equipment
valve, used as a temporary barrier when running the upper supply) issues. This approach has provided practical
completion, is opened remotely by application of pressure operational input to equipment design, enabled offshore
cycles. This process is conducted once the xmas tree has been subsea supervisors to gain intimate knowledge of equipment
installed. The isolation valve has failed to open remotely in and developed offshore team spirit ahead of arrival in Angola.
four installations out of 12 wells. Contingency tools run either The same philosophy was adopted for rig commissioning
on wireline or coil tubing have enabled the valve to open in all and acceptance. Drilling supervisors were mobilised six
cases with the exception of one well. This particular well will months ahead of rig delivery.
require a re-entry to mill out the ball on coil tubing. Continuity of personnel from the project phase to the
execution phase has been of great value. The D&C team
Completion highlights. Complex clean-up and well testing moved to Luanda and was integrated with the existing drilling
operations have been conducted through the permanent organisation within the subsidiary. This has enabled all of
completion and subsea xmas tree. Flowing hydrocarbons to a them to benefit from the experience gained over the four-year
dynamically positioned drillship through a well intervention exploration campaign on Bloc 17 which ended in early 2001.
package and workover riser is a hazardous operation requiring Drilling resources have been stretched as a result of the
very throrough preparation. Following a risk assessment, it challenges from the ‘fast track’ approach. All the preparation
was concluded that concentric operations would not be work - conceptual design, engineering, contract set-up,
allowed on the first well while hydrocarbons were flowing. procurement of equipment, rig commissioning, establisment of
Conducting concentric operations (with wireline or coil procedures, et al – was crammed into a limited period.
tubing) from a new drillship, with new people and a prototype Drilling and completion resources had to be sufficient to
subsea intevention package was deemed too risky. Production address all the engineering issues and pay attention to detail.
logging operations were banned from the first well, although The design changes inherent in the ‘fast track’ approach
there was a strong requirement from the reservoir engineers. required a high reactivity. It was also essential to implement
The subsea intervention package and the electro-hydraulic the lessons learnt from the first wells in order to climb quickly
workover controls have demonstrated high reliability from the up the learning curve.
first well which has built up the required confidence for more
sophisticated well work. Specific contingency procedures and CONCLUSIONS
training courses for rig crews have been developed for these
testing operations and concentric work. The challenges confronted by the drilling and completion
Production logging tools have been run on coil tubing at team have been met :
several instances with the well flowing hydrocarbons to the
testing spread installed on the rig. In a few wells, several coil - Twelve wells were delivered at first oil. These high
tubing and/or wireline runs have also been required to open potential wells have allowed production to reach a high
the isolation valve which had failed to open remotely by rate quickly;
application of pressure cycles. Contingency runs with - Technical difficulties were encountered on the first wells.
wire line or coil tubing have been more frequent than However well construction performance improved very
initially envisaged. quickly and reached a satisfactory level within a
Downhole pressure data from permanent gauges is few months;
available to the rig while the intervention package is - Installation of subsea completions has been executed with
connected to the xmas tree. This capability allows great NPT below industry benchmarks;
flexibility to conduct clean-up operations. The drawdown - The two new drillships were delivered six months late
applied on the formation can be monitored and adjusted which is is not a bad performance by industry standards,
accurately in order to avoid abrupt surges which could be given the ambitious construction shedule. The drillships
detrimental to the sand control equipment or well quickly reached a competent level of performance and
performance. This feature has allowed to operate with steps of remarkably low NPT;
no more than two bars drawdown, while ramping up the oil - Screen-only completions in the Girassol turbiditic
rate. Pressure build-up has been recorded concurrently with environment have proven to be technically viable
other handling or tree preservation operations to minimize allowing high well productivity. Successfull frac pack
online rig time. applications have extended the technical limit of this
technology further in the high reservoir mobility domain.
OTC 14168 GIRASSOL: DRILLING AND COMPLETION EXPERIENCE GAINED THROUGH FIRST 12 WELLS 11

The main critical elements which have influenced these References :


achievements are:
- An integrated project approach with good management of Ref. 1 : OTC paper N° 14167 Well Interference Test On
interfaces. Secondment of personnel to the SPS team was Girassol by Philippe Retail, Larry Thane, Emmanuel
of great value; Liberelle, TOTALFINAELF Angola
- Recognition of risks and management decision processes
to allocate sufficient resources; Ref. 2 : OTC paper N° 14207 Girassol subsea completion
- A thorough testing philosophy involving qualification, experience by Larry Thane, Jean Lassus-Dessus, Dominique
integration and stack-up testing. This area is a key Delaporte, TOTALFINAELF Angola
learning. Do not use your first well as an integration test
or stack up test ! Ref. 3 : OTC paper N° 14213 Girassol : Operation of 2 new
- Consider trade-offs between design complexity and rig built drill ships in the Girassol field by Thomas Duhen PRIDE
NPT risk exposure. Adding extra jewelry can be scary in FORAMER, Régis Studer and Claude Richard
a US$20mn well; TOTALFINAELF Angola
- Continuity of personnel from project phase to execution;
- Sufficient resources to allow attention to detail Figures

With only one-third of the wells completed at the time the Fig 1 : Girassol location map
paper is written, we still have numerous challenges ahead:
- Improve safety and environmental performance. Safety Fig 2 : Girassol reservoirs cross section
performance has had a high focus from both the operator
and the rig contractor on the two newbuild units. Fig 3 : Subsea Production System with stand alone PGB and
However, safety performance has been below rigid jumper design
TotalFinaElf objectives in terms of frequency (Ref. 3).
Lost time incidents have been at a low level of severity Fig 4 : Horizontal well completion
(30 days maximum).
- Safety performance improvement is a high priority Fig 5 : Actual Well durations
objective with a target of 2.5 Lost Time Accidents per
million of worked hours; Fig 6 : NPT evolution
- Drill and complete more complex wells involving long
step out and a few ‘intelligent’ completions; Fig 7 : Productivity indexes
- Continue to learn and to improve performance.
- Replace some staff who have been assigned to the project
for more than four years, without affecting performance. List of abbreviations :

ACKNOWLEDGEMENT BHA: Bottom Hole Assembly


BOP : Blow Out Preventer
The Girassol project is a development operated by CAD : Computer Assisted Drawing
TotalFinaElf E&P Angola under a production sharing FPSO : Floating Production Storage and Offloading unit
agreement awarded by Sonangol to a contractor group NPT : Non productive Time
including TotalFinaElf, ExxonMobil, BP, Statoil and Norsk OHGP : Open Hole Gravel Pack
Hydro. TotalFinaElf would like to thank Sonangol and all of PGB: Production Guide Base
its partners for their support in the preparation of this paper ROV : Remote Operated Vehicle
and their permission to publish. SPS : Subsea Production System
UFL : Umbilical and Flowlines
TRSCSSV: Tubing Retrievable Surface Controlled
Subsurface Safety Valve
12 J. L. DESSUS, J. ABREU OTC 14168

85
BLOCK 3

100
200

100

50
AFRICA

LUANDA

ANGOLA

BLOCK 16
BLOCK 17

BLOCK 4
200

320 300
350
10

450
00

500
95
0 85 80 70 550
90 75
10

0 0 0 0 600
11

0 650
11

50
00
50

ROS 1
18

12
12

00
16
18 0
50

50
00
17
0

13
00

15

00
50
17

14 0
13
15

14
16
50

00
50

GIR 2A
00

5
50

GIR 2B
19
00

19
GIR 1
50
DALGIR
1 1 DAL 2

20
00 BLOCK 5 25 Km

Fig 1 : Girassol Location Map

Sheet S6 B3 Complex
B2 Complex
LPC

Seq.3 up Seq.4
Seq.2 3 low
S6 B2 Up
Seq.1 C
B2 Low
A B
B1 Up
S3 B1 Low S2

S3 Complex B1 Complex S2 Complex

Fig 2 : Girassol reservoirs cross section


OTC 14168 GIRASSOL: DRILLING AND COMPLETION EXPERIENCE GAINED THROUGH FIRST 12 WELLS 13

Fig 3 : Subsea Production system with stand alone


PGB and rigid jumper design

GIRASSOL DEVELOPMENT W ELLS - ACTUAL DURATIONS

160

140

PRODUCERS
120
INJECTORS

100
DAYS

80

60

40

20

0
GIR101 GIR102 GIR103 GIR104 GIR105 GIR106 GIR107 GIR108 GIR109 GIR110 GIR111 GIR112

Fig 5 : Actual well durations


14 J. L. DESSUS, J. ABREU OTC 14168

Fig 4: Horizontal Well Completion

Xmas Tree 5'' x 2'' N P T T ota l( hour s)


N P T T o ta l
N P T T ota l%
14 00 40%
34%
12 00 35%
29%
26% 30%
10 00 24%
25%
80 0 20%

H ou r s
20%
36" conductor 23% 19%
60 0
15% 15%
TRSCSSV, 500m 40 0 10%
10% 13%
below seabed 12%
20 0 5% 5%
20'' casing
0 0%

101

102

103

104

107

105

106

108

109

110

111

112
G IR -

G IR -

G IR -

G IR -

G IR -

G IR -

G IR -

G IR -

G IR -

G IR -

G IR -

G IR -
13 3/8" casing

Fig 6 :Evolution of Non Productive Time

P,T gauges

Injection sub

WELL PERFORMANCE (M3/d/bar)

500

450

400
Gas Injector
350

300 OHGP + Frac pack

Isolation valve 250


Screen only Completions
200

150
10''3/4 casing Water Injectors
100
Frac packs
50

6 5/8'' screens
0
w/ blanks & ECPs GIR 101 Gir 105 Gir 106 GIR 102 GIR 107 Gir 108 Gir 109 GIR 103 GIR 104 Gir 110

9"1/2 open hole Fig 7 : Productivity Indexes (M3/d/bar)

Anda mungkin juga menyukai