Anda di halaman 1dari 5

PAVIMENTAÇÃO EM BLOQUETE SEXTAVADO DE CONCRETO E DRENAGEM PLUVIAL Área Construída (m²): Área (m²): 2805.00 BDI: 30.

00%
AVENIDA PASTOR BENJAMIN - CONCEIÇÃO DE IPANEMA/MG Leis Sociais: L.S.: 122.82% DATA: Dec-10
CUSTO
CUSTO UNITÁRIO PESO
TOTAL
ITEM DISCRIMINAÇÃO DOS SERVIÇOS UNIDADE QUANT. SINAPI
C/BDI (R$) (R$) (%)
1 SERVIÇOS PRELIMINARES
1.1 AQUISICAO DE PLACA PRONTA E ASSENTAMENTO 2X1,50m MOD. MANUAL CEF (prop. 4:3) M² 3.00 120.00 156.00 468.00 0.15
Total do item 01 468.00 0.15

2 TERRAPLENAGEM
ESCAVAÇÃO, CARGA DE MATERIAL DE 3ª CAT, COM UTILIZAÇÃO DE EQUIPAMENTO DE AR
2.2 COMPRIMIDO - PREÇO SETOP MG COD: TER-ESC-030
M³ 303.38 75.00 97.50 29,579.55 9.38
2.3 TRANSPORTE MATERIAL PARA BOTA FORA DMT 06km M³ 303.38 6.00 7.80 2,366.36 0.75
Total do item 02 31,945.91 10.13
0.00
3 DRENAGEM PROFUNDA 0.00
3.1 ESCAVAÇÃO MECANICA DE VALAS ATÉ 1,50m M³ 474.00 3.70 4.81 2,279.94 0.72
3.2 REATERRO COMPACTADO DE VALAS C/ PLACA VIBRATÓRIA M³ 291.60 5.26 6.84 1,994.54 0.63
3.3 FORNEC/ASSENT DE TUBO DE CONCRETO ARMADO CA1 D=600mm JUNTA ARG. M 350.00 102.00 132.60 46,410.00 14.72
3.4 FORNEC/ASSENT DE TUBO DE CONCRETO SIMPLES C1 D=400mm JUNTA ARG. M 60.00 58.00 75.40 4,524.00 1.44
CAIXA RALO TIPO BOCA DE LOBO 30x90x90cm EM ALV.DE TIJOLO MACIÇO 01 VEZ REVEST.
3.5 ARG. 1:4 CIMENTO:AREIA, SOBRE BASE DE CONCRETO SIMPLES 10Mpa E GRELHA DE UNIDADE 10.00 717.00 9,321.00 2.96
FERRO REMOVÍVEL 135kg, INCL. ESCAVAÇÃO E REATERRO 932.10
3.6 POCO VISITA AG PLUV:CONC ARM 1,10X1,10X1,40M COLETOR D=60CM PAREDES 15cm UNIDADE 6.00 1,270.00 1,651.00 9,906.00 3.14
Total do item 02 74,435.48 23.61
0.00
4 PAVIMENTAÇÃO 0.00
4.1 REGULARIZAÇÃO SIMPLES DE SUB-LEITO ESPESSURA 15cm M² 2,805.00 0.25 0.33 925.65 0.29
4.2 PISO C/BLOCO SEXT CONCR (TIPO BLOKRET) E=8,0 X 30 X 30CM INCL.COLCHÃO 06cm M² 2,505.00 44.50 57.85 144,914.25 45.97
MEIO-FIO DE CONCRETO PRE-MOLDADO 12cm(esp)x30cm(altura), REJUNTADO C/ARG.
4.3 M 750.00 17.00 22.10 16,575.00 5.26
CIMENTO E AREIA 1:3,
4.4 SARJETA DE CONCRETO TRAÇO 1:4:8, PREPARO MECANICO L=40cm E ESP=08cm M 750.00 12.77 16.61 12,457.50 3.95
4.5 CALÇADA EM CONCRETO
PLACA ESMALTADA 1:3:5 - e=07cm
P/ IDENTIFICAÇÃO DE- PREPARO MECANICO,
RUA, DIMENSÕES INCL.AFIXADA
45x25cm REGULARIZAÇÃO
EM TUBO M² 1,125.00 22.20 28.86 32,467.50 10.30
METÁLICO DN=2", hmin do piso=2,00m - CHUMBADA NO PISO (50cm) C/ ARG. 1:4 -
4.6 CIMENTO:AREIA
UNIDADE 4.00 199.00 258.70 1,034.80 0.33
0.00 0.00
Total do item 03 208,374.70 66.10
0.00
TOTAL GERAL (R$) 315,224.09 100.00
Custo unitário (R$/m2 de área construída) 112.38

AUTOR: WILSON PORTES JUNIOR - ENG. CIVIL - CREA/RJ:44.125/D Investimento R$ 315,224.09


Repasse R$ 300,000.00
MCIDADES - CR: 312.952-11/2009
PROGRAMA: Pro Município
AÇÃO: Implantação ou Melhoria de Obras de Infraestrutra Urbana
Prefeitura Municipal
Conceição de Ipanema - MG
Avenida Geraldo de Barros, 192 - Centro - CEP: 36.957.000 — FONE-FAX: (33) 3317- 1180

CNPJ: 18.116.137/0001-71 E-mail: pmconceicao@gmail.com

CRONOGRAMA FÍSICO-FINANCEIRO
GLOBAL

1 - IDENTIFICAÇÃO
PROGRAMA: PRÓ-MUNICÍPIO Endereço/Bairro: Avenida Pastor Benjamin - Sede do municipio
Município/MG: CONCEIÇÃO DE IPANEMA/MG Data da elaboração do orçamento: 14 de fevereiro de 2011

SERVIÇOS A EXECUTAR
ITEM DISCRIMINAÇÃO VALOR DOS PESO MÊS -01 MÊS 02 MÊS 03 MÊS 04 MÊS 05 MÊS 06
DE SERVIÇOS SERVIÇOS % SIMPL.% ACUM. % SIMPL.% ACUM. % SIMPL.% ACUM. % SIMPL.% ACUM. % SIMPL.% ACUM. % SIMPL.% ACUM. %
1 SERVIÇOS PRELIMINARES R$468.00 0.15% 100.00 100.00 100.00 100.00 100.00 100.00 100.00
2 TERRAPLENAGEM R$31,945.91 10.13% 30.00 30.00 30.00 60.00 20.00 80.00 20.00 100.00 100.00 100.00
3 DRENAGEM PROFUNDA R$74,435.48 23.61% 5.00 5.00 10.00 15.00 15.00 30.00 20.00 50.00 30.00 80.00 20.00 100.00
4 PAVIMENTAÇÃO R$208,374.70 66.10% 10.00 10.00 20.00 30.00 20.00 50.00 20.00 70.00 20.00 90.00 10.00 100.00
5 0.00% 0.00 0.00 0.00 0.00 0.00 0.00
6 0.00% 0.00 0.00 0.00 0.00 0.00 0.00
7 0.00% 0.00 0.00 0.00 0.00 0.00 0.00
8 0.00% 0.00 0.00 0.00 0.00 0.00 0.00
9 0.00% 0.00 0.00 0.00 0.00 0.00 0.00
10 0.00% 0.00 0.00 0.00 0.00 0.00 0.00
0.00% 0.00 0.00 0.00 0.00 0.00 0.00
0.00% 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00
0.00

TOTAL EM PERCENTUAL R$315,224.09 100.00% 10.98% 10.98% 18.62% 29.60% 18.79% 48.39% 19.97% 68.36% 20.30% 88.67% 11.33% 100.00%
TOTAL EM REAIS R$315,224.09 34,611.02 58,702.26 59,229.44 62,951.22 64,005.58 35,724.57

CONTRAPARTIDA R$15,224.09 4.83% 1,671.58 4.83% 2,835.09 4.83% 2,860.55 4.83% 3,040.30 4.83% 3,091.22 4.83% 1,725.36 4.83%
REPASSE R$300,000.00 100.00% 32,939.44 95.17% 55,867.17 95.17% 56,368.89 95.17% 59,910.92 95.17% 60,914.36 95.17% 33,999.21 95.17%

Conceição de Ipanema, 14 de fevereiro de 2011


DATA Responsável Técnico - CREA
Wilson Portes Jr.- CREA/RJ: 44.125/D
QUADRO DE COMPOSIÇÃO DO INVESTIMENTO
GLOBAL

1 - IDENTIFICAÇÃO
PROGRAMA: PRÓ-MUNICÍPIO
Município/MG: CONCEIÇÃO DE IPANEMA/MG
Endereço/Bairro: Avenida Pastor Benjamin - Sede do municipio

2 - COMPOSIÇÃO DO INVESTIMENTO

ITEM DISCRIMINAÇÃO DOS SERVIÇOS CONTRAPARTIDA REPASSE (OGU) REGIME FORMA


1 SERVIÇOS PRELIMINARES #NAME? #NAME? EG RF
2 TERRAPLENAGEM #NAME? #NAME? EG RF
3 DRENAGEM PROFUNDA #NAME? #NAME? EG RF
4 PAVIMENTAÇÃO #NAME? #NAME? EG RF
5 R$0.00 R$0.00
6 R$0.00
7 R$0.00 R$0.00
8 R$0.00 R$0.00
9 R$0.00 R$0.00
10 R$0.00 R$0.00
11
12
13
14
15
TOTAL #NAME? #NAME? TOTAL GERAL
PERCENTUAL DE PARTICIPAÇÃO #NAME? #NAME? #NAME?

LOCAL/DATA
Conceição de Ipanema, 14 de fevereiro de 2011 Profissional: Wilson Portes Junior
OBSERVAÇÃO: CREA/RJ: 44.125/D
REGIME DE EXECUÇÃO:
Indicar (AD) para obras por administração direta e (EG) para obras por empreitada global/preço unitário.
FORMA DA CONTRAPARTIDA:
Indicar (OS) para contrapartida em obras/serviços e (RF) para contrapartida em recursos financeiros.
COMPOSIÇÃO DO BDI
1) GARANTIA - ( 0 a 0,42%)

0.42

2) RISCO - ( 0 A 2,05 %)

2.05

3) DESPESAS FINANCEIRAS - ( 0 A 1,20%)

1.20

4) ADMINISTRAÇÃO CENTRAL - (0,11 A 8,03%)

6.42

5) LUCRO - ( 3,83 A 9,96% )

9.96

6) TRIBUTOS ( 6,03 A 9,03%)

Tais itens podem variar:


COFINS – Contribuição para o Financiamento da Seguridade Social: A alíquota depende do enquadramento
fiscal e tributário da empresa.
PIS - Programa de Integração Social: A alíquota depende do enquadramento fiscal e

COFINS= 3.00 PIS= 0.65 ISS= 3.00

BDI= 30.00 0.00


MES 01 MES 02 MES 03 MES 04 MES 05 MES 06
REPASSE CP REPASSE CP REPASSE CP REPASSE CP REPASSE CP REPASSE CP
445.40 22.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9,120.91 462.86 9,120.91 462.86 6,080.61 308.57 6,080.61 308.57 0.00 0.00 0.00 0.00
3,542.03 179.75 7,084.05 359.49 10,626.08 539.24 14,168.11 718.99 21,252.16 1,078.48 14,168.11 718.99

13,108.34 665.21 16,204.97 822.35 16,706.69 847.81 20,248.72 1,027.56 21,252.16 1,078.48 14,168.11 718.99 101,688.98 5,160.41
13,773.55 17,027.32 17,554.50 21,276.28 22,330.64 14,887.10 106,849.39
106,849.39