17 Sand for morter do 5 149.67 35.00 184.67 45.71 230.38 River Mahanadi
21 Bitumen (Bulk) 60/70 (VG-30) MT 615 4481.37 Nil 4481.37 38267.40 Haldia
21 Bitumen (Bulk) 30/40 (VG-30) MT 615 4481.37 Nil 4481.37 39671.60 Vizag
Certified that, the lead and the average lead provided in this Lead Statement are minimum and correct to the best of my knowledge.
Sl. Material Description Unit Distance Cost of Royalty Total Basic Cost Name of
No in Km carriage source
1 2 3 4 5 6 7 8 9
From plant
1 26.5mm HGCB Metal Cum 5 149.67 130.00 279.67 764.76 914.43 site
2 25mm HGCB Metal Cum 5 149.67 130.00 279.67 789.52 939.19 -do-
3 22.4mm HGCB Metal Cum 5 149.67 130.00 279.67 812.38 962.05 -do-
4 20mm HGCB Metal Cum 5 149.67 130.00 279.67 1076.19 1225.86 -do-
5 13.2mm CB Chips Cum 5 149.67 130.00 279.67 1090.48 1240.15 -do-
6 12mm CB Chips Cum 5 149.67 130.00 279.67 1095.24 1244.91 -do-
7 11.2mm CB Chips Cum 5 149.67 130.00 279.67 1095.24 1244.91 -do-
8 10mm CB Chips Cum 5 149.67 130.00 279.67 1095.24 1244.91 -do-
9 6.7mm CB Chips Cum 5 149.67 130.00 279.67 761.90 911.57 -do-
10 Stone Screening Cum 5 149.67 130.00 279.67 571.43 721.10 -do-
11 4.7mm CB Chips Cum 5 149.67 130.00 279.67 706.67 856.34 -do-
12 Crusher Dust Cum 5 149.67 35.00 184.67 83.81 233.48 -do-
13 Bitumen (Bulk) 60/70 MT 610 4446.42 - 4446.42 38267.40 -do-
13 Bitumen (Bulk) 30/40 MT 610 4446.42 - 4446.42 39671.60 -do-
The Lead from plant to middle portion of proposed stretch = 5 Km
A. Labour
Mate Each 0.01 244.30 2.44
Mazdoor Each 0.25 224.30 56.08
58.52
B. Machinaries
Tractor with ripper attachment @ 60cum/hrs Hour 0.08 200.87 16.07
Front end loader 1cum bucket capacity Hour 0.20 452.17 90.43
Tipper 5.5cum capacity 4 Trip/hrs Hour 0.23 506.09 116.40
222.90
C. Over head Charges 7.5% on a+b 21.11
D. Contractor Profit 7.5% 21.11
Total cost for 100sqm=a+b+c+d 323.64
Add for Cess 1% 3.24
326.87
Cost for 1sqm=(a+b+c)/100 3.27 /Sqm
2 Tack coat
Providing and applying tack coat with bitumen 60/70 grade
using emulsion pressure distributor @ 0.20kg per sqm on
prepared bituminous surface/ @ of 0.30kg per sqm on
granular surface cleaned with mechanical broom.As per
clause 503 of MORTH specificatin for road and bridge work
(4th Revision)
Unit = sqm
Taking out put = 3500sqm
Unit=Sqm
Taking output=3500sqm
A/R 2006/P-168/Item No.44
a) Labour
Mate Each 0.08 244.30 19.54
Mazdoor Each 2.00 224.30 448.60
468.14
b) Mechinaries
Mechanical broom @ 1250sqm/hrs Hour 2.80 200.00 560.00
Air compressor 250cfm Hour 2.80 179.13 501.56
Bitumen pressure distributor @1750sqm/hrs Hour 2.00 448.70 897.40
1958.96
c) Materials
Bitumen RS setting grade @ 0.20 kg/ sqm MT 0.70 31482.40 22037.68
d) Over head Charges 10% on (a+b+c) 1834.86
E. Contractor Profit 7.5% 1834.86
f) Lead & Royalty
Bitumen emulsion (RS) @ 0.2 kg/ sqm MT 0.70 4481.37 3136.96
Total cost for 3500sqm=a+b+c+d+e+f 31271.47
Add for Cess 1% 312.71
31584.18
Rate persqm=(a+b+c+d+e)/3500 9.02 /Sqm
3 Bituminous Macadam
Sl Name of the item Unit Quantity Rate Amount
No
Providing and laying bituminous macadam with 100-120
TPH hot mix plant producing and average output of
75 tonnes per hour using crushed aggregates of specified
grading premixed with bituminous binder, transported to
site etc. complete as per MoRT&H specification clause 504
Data book page-125
Unit=cum
Takingoutput=205cum(450tones)
a) Labour
Mate Each 0.76 244.30 185.67
Mazdoor working with HMP, Mechanical, broom, paver, roller,
asphalt cutter and assistance for setting out lines, level and
layout of construction.
Each 14.00 224.30 3140.20
Skilled mazdoor for checking line and level Each 5.00 264.30 1321.50
4647.37
b) Machinery
Batch mix HMP 100-120TPH @ 75 Tone/hour actual output Hour 6.00 9710.43 58262.58
Paver finisher with senser control Hour 6.00 1605.22 9631.32
Generator 250KVA Hour 6.00 978.26 5869.56
Front end loader 1cum bucket capacity Hour 6.00 452.17 2713.02
Tonnes
Tipper tonne capacity 450 x 5 2.17 4882.50
km
Add 10 per cent of cost of carriage to cover Cost of loading 488.25
and unloading.
Smooth wheeled roller 8-10 tonnes for initial bread down Hour 6.00x0.65 294.78 1149.64
rolling
Vibratory roller 8 tonnes for Intermediate rolling. Hour 6.00x0.65 864.35 3370.97
Finish rolling with 6-8 tonnes smooth Wheeled tandem roller. Hour 6.00x0.65 641.74 2502.79
88870.62
c) Material
i) Bitumen 60/70 @ 3.3 per cent of mix weight of mix =
2.05x2.2 = 450 tonne Tonne 14.85 38267.40 568270.89
Grading-II
25-10mm 40% (20mm) cum 116.04 1076.19 124881.09
a) Labour
Mate Each 0.76 244.30 185.67
Mazdoor working with HMP, Mechanical, broom, paver, roller,
asphalt cutter and assistance for setting out lines, level and
layout of construction.
Each 14.00 224.30 3140.20
Skilled mazdoor for checking line and level Each 5.00 264.30 1321.50
4461.70
b) Machinery
Batch mix HMP 100-120TPH @ 75 Tone/hour actual output hour 6.00 9710.43 58262.58
Paver finisher with senser control 100 Tph hour 6.00 1605.22 9631.32
Generator 250KVA hour 6.00 978.26 5869.56
Front end loader 1cum bucket capacity hour 6.00 452.17 2713.02
Tonnes
Tipper tonne capacity (450x7) km 450 x 5 2.17 4882.50
A.Labour
Man mulia Each 1.00 224.30 224.30
Woman mulia Each 1.50 224.30 336.45
560.75
B.Machineries
Hire and Running charges of PRR Hour 0.053 339.00 18.06
(2.83 x 8.00)/425
578.81
C.Over Head Charges 7.5% on (a+b+c) 43.41
E. Contractor Profit 7.5% on a+b+c 43.41
665.63
Rate per 1 cum = 452.02 / 2.83cum 235.20
Add cost, lead royalty of moorum Cum 1.28 276.29 353.65
Cost for 1cum =(b+c+d+e) 588.86 /Cum
Add for Cess 1% 5.89
594.74
6
Providing and lalying of hot applied thermoplastic
compound 2.5mm thick per sqm including reflectorising
glass beads @ 250gms/sqm area, thickness of 2.55mm is
execlusive of surface apply glass beads as per IRC-35. The
finished surface to be level,
Unit= Sqm
Taking output 640sqm
A. Labour
Mate Each 0.50 244.30 122.15
Mazdoor Each 2.00 224.30 448.60
570.75
B. Mechinary
Road Marking machine @ 80sqm/hour Hour 8.00 52.17 417.36
Tractor Trally Hour 8.00 200.87 1606.96
2024.32
C. Mateials
Hot applied thermoplastic compound 2000Ltr Ltr 2000.00 130.00 260000.00
Reflecting Glass beads Kg 200.00 50.00 10000.00
270000.00
D. Add 7.5% Over Head Charges 20444.63
E. Contractor Profit 7.5% 20444.63
Total = A+B+C+D 313484.33
Rate per one sqm 489.82 /Sqm
Add for Cess 1% 4.90
494.72 /Sqm
7 Painting 2 coats on new concrete surface (by synthetic
enamel paint)
Unit = Sqm, taking out put = 40 Sqm
i) Material
Paint Ltr 6.000 151.97 911.82
ii) Labour
Mazdoor day 1.000 224.30 224.30
Sl Name of the item Unit Quantity Rate Amount
No
Painter Special day 2.000 283.30 566.60
mate day 0.120 244.30 29.32
1732.04
ii) Over Head Charges 7.5% 129.90
iii) Contractor Profit 7.5% 129.90
1991.84
iv) Cess 1% 19.92
Rate per 40 Sqm 2011.76
Rate per 1 Sqm 50.29 /Sqm
8 Providing and laying 25 mm thick mastic asphalt wearing
course with paving grade bitumen meeting the requirements
given in table 500-29, prepared by using mastic cooker and
laid to required level and slope after cleaning the surface,
including providing antiskid surface with bitumen precoated
fine grained hard stone chipping of 13.2mm nominal size @
0.005cum per 10sqm and at an approximate spacing of 10cm
center to center in both directions, pressed into surface when
the temperature of surfaces is not less than 100 degree
centigrade, protruding 1 mm to 4 mm over mastic surface all
complete as per Clause 515 of MoSRT&H Specifications for
Road &
Bridge works (4th Revision)
Unit = sqm
Taking output = 35.00 sqm (0.87 cum )
assuming a density of
2.3 tonnes/cum.-2 tonnes
a) Labour
Mate Each 0.44 244.30 107.49
Mulia unskilled Each 10.00 224.30 2243.00
Mulia skilled Each 1.00 264.30 264.30
2507.30
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.60 200.00 120.00
Air compressor 250 cfm hour 0.60 179.13 107.48
Mastic cooker 1 tonne capacity hour 6.00 1379.13 8274.78
Bitumen boiler 1500 litres capacity hour 6.00 111.30 667.80
Tractor for towing and positioning of mastic cooker and Tonnes 1.00 200.87 200.87
bitumen boiler km
9370.93
c) Materials
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate (6.3mm to 13.2 mm) = 40 per cent .
Proportion of material required for mastic asphalt with coarse
aggregates (based on mix design done by CRRI for a specific
case)
I) Bitumen 30/40 penetration grade @ MT 0.20 39671.60 8093.01
10.2 per cent by weight of mix. 2 x 10.20/100 = 0.204
ii) Fine aggregate passing 2.36mm and retained on 0.075mm Cum 0.39 83.81 32.69
sieve @ 31.9 per cent by weight of mix = 2 x
31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium content not less than 80 MT 0.360 20000.00 7200.00
per cent by weight @ 17.92 per cent by weight of mix = 2 x
17.92/100 = 0.36
iv) Coarse aggregates 6.3 mm to 13.2 mm @ 40 per cent by Cum 0.550 926.19 509.40
weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456 = 0.55
v) Pre-coated stone chips of 13.2 mm nominal size for skid Cum 0.018 1090.48 19.63
resistance = 35 x 0.005/10 = 0.018
Sl Name of the item Unit Quantity Rate Amount
No
vi) Bitumen for coating of chips @ 2 per cent by weight = Kg 0.500 32.43 16.22
0.018 x 1.456 x 2/100 = 0.0005 MT = 0.5kg
15870.94
d) Overhead charges @ 7.5% on (a+b+c) 2081.19
e. Contractor Profit 7.5% 2081.19
e) Lead and Royalty
I) Bitumen Cum 0.740 4481.37 3316.21
Stone Products Cum 0.568 543.67 308.80
Dust 0.390 448.67 174.98
Lime cum 0.360 184.67 66.48
3866.48
Cost for 10 Cum of granular backfill = a+b+c+d+e+f 35778.02
Add for Cess 1% 357.78
36135.80
Cost for 1cum= (a+b+c+d+e+f )/35 1032.45 /Sqm
9 Bituminous Concrete
Providing and laying bituminous concrete with batch type hot
mix plant using crushed aggregates of specified grading,
premixed with bituminous binder of 60/70 penetration grade
of bitumen, transporting the hot mix to work site,
laying with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment, rolling with smooth
wheelede, vibratory and tandem rollers to
achieve the desired compaction as per Clause 509 of
MoSRT&H Specifications for Road & Bridge works (4th
Revision) Unit=cum
Takingoutput=191cum(450tonnes)
a) Labour
Mate Each 0.76 244.30 185.67
Mazdoor working with HMP, Mechanical, broom, paver, roller,
asphalt cutter and assistance for setting out lines, level and
layout of construction. Each 14.00 224.30 3140.20
Skilled mazdoor for checking line and level Each 5.00 264.30 1321.50
4461.70
b) Machinery
Batch mix HMP 100-120TPH @ 75 Tone/hour actual output hour 6.00 9710.43 58262.58
Paver finisher with senser control 100 Tph hour 6.00 1605.22 9631.32
Generator 250KVA hour 6.00 978.26 5869.56
Front end loader 1cum bucket capacity hour 6.00 520.00 3120.00
Tonnes
Tipper tonne capacity (450x7) 450 x 5 2.17 4882.50
km
Add 10 per cent of cost of carriage to cover Cost of loading
and unloading. 488.25
Smooth wheeled roller 8 -10 tonnes for initial bread down Hour 6.00x0.65 294.78 1149.64
rolling
Vibratory roller 8 tonnes for Intermediate rolling. Hour 6.00x0.65 864.35 3370.97
Finish rolling with 6-8 tonnes smooth Wheeled tandem roller. Hour 6.00x0.65 641.74 2502.79
89277.60
c) Materials
Grading-II 13mm (nominal size) Bitumen 40/30 @ 5% of Tonne 22.50 39671.60 892611.00
weight of Mix
Weight of mix= 450tonne
ii) Aggregate
13.2-10mm @ 30 per cent cum 85.50 1092.86 93439.53
10 - 5 mm @ 25 per cent cum 71.25 900.96 64193.04
Sl Name of the item Unit Quantity Rate Amount
No
5mm and below @ 43 per cent cum 122.50 395.24 48416.90
Filler at @2percent of weight of aggregate. cum 5.70 83.81 477.72
1099138.19
d) Overhead charges @ 7.5% on (a+b+c) 89465.81
e. Contractor Profit 7.5% 89465.81
e) Lead and Royalty
i) Bitumen 60/70 @ 5 per cent of weight of mix tonne 22.5 4446.42 100044.45
Weight of mix= 450tonne
ii) Aggregate
25-10 nominal size cum 85.5 543.67 46483.79
10 - 5 mm @ 25 per cent cum 122.5 543.67 66599.58
Filler at @2percent of weight of aggregate. cum 5.7 543.67 3098.92
216226.73
Cost for 195cum= a+b+c+d+e 1588035.85
Add for Cess 1% 15880.36
1603916.21
Cost for 1cum= (a+b+c+d+e+f )/191 8397.47 /Cum
BM for depression filling 110 2.00 2.00 0.05 22.00 Cum 5938.28 130,642.16
6 Providing and laying semi-dense bituminous
concrete with 100-120 TPH batch type HMP
producing and average 75 tone per hour using
crushed aggregate specified grading, premix
bituminous binder @ 4.5 to 5 per cent of mix and
Filler, transporting the hot mix to works site,
laying with a hydrostatic paver finisher with
sensor control to the required grade, level and
alignment, rolling with smooth wheel, vibratory and
tandem rollers to achieve the desire compaction as
per MoRTH specification clause No. 508 data book
page-135.
Total 22,759,374.52
1 2 3
Total `. 22,759,374.52
Add 1% for quality control 1% `. 227,593.75
Add 1% for Contigency 1% `. 227,593.75
Total `. 23,214,562.01
Add 6% for CGST 6% `. 1,392,873.72
Add 6% for SGST 6% `. 1,392,873.72
Total `. 26,000,309.46
Or Say `. #N/A
Sl
No Description Nos Length Width Height Qty Unit Rate Amount
1 2 3 4 5 6 7 8 9 10
From 0/0 to 4/500Km = 5000 Mtr.
1 Scarifying the existing BT surface and stacking them
away from the work site as per specification and
direction of Engineer-in-charge as per Clause
No.501.8.3.2, 501.8.7.2 of spefication of Road &
Bridge Work (4th Revision).
BM for depression filling 200 2.00 2.00 0.05 40.00 Cum 5938.28
Total 18,812,943.42