Anda di halaman 1dari 28

Minggu Periode

1 24 MARET s/d 30 MARET 2016 24-Mar 30-Mar 1


2 31 MARET s/d 6 APRIL 2016 31-Mar 6-Apr 2
3 7 APRIL s/d 13 APRIL 2016 7-Apr 13-Apr 3
4 14 APRIL s/d 20 APRIL 2016 14-Apr 20-Apr 4
5 21 APRIL s/d 27 APRIL 2016 21-Apr 27-Apr 5
6 28 APRIL s/d 4 MEI 2016 28-Apr 4-May 6
7 5 MEI s/d 11 MEI 2016 5-May 11-May 7
8 12 MEI s/d 18 MEI 2016 12-May 18-May 8
9 19 MEI s/d 25 MEI 2016 19-May 25-May 9
10 26 MEI s/d 1 JUNI 2016 26-May 1-Jun 10
11 2 JUNI s/d 8 JUNI 2016 2-Jun 8-Jun 11
12 9 JUNI s/d 15 JUNI 2016 9-Jun 15-Jun 12
13 16 JUNI s/d 22 JUNI 2016 16-Jun 22-Jun 13
14 23 JUNI s/d 29 JUNI 2016 23-Jun 29-Jun 14
15 30 JUNI s/d 6 JULI 2016 30-Jun 6-Jul 15
16 7 JULI s/d 13 JULI 2016 7-Jul 13-Jul 16
17 14 JULI s/d 20 JULI 2016 14-Jul 20-Jul 17
18 21 JULI s/d 21 JULI 2016 21-Jul 27-Jul 18
17.14286
119
PEMERINTAH KABUPATEN SERANG
DINAS PEKERJAAN UMUM
BIDANG BINA MARGA
Jl. Samaun Bakri Telp. (0254) 200363 Serang

LAPORAN MINGGUAN
KEMAJUAN FISIK PEKERJAAN

MINGGU KE : 1 (SATU)
PERIODE : 24 MARET s/d 30 MARET 2016

Paket Pekerjaan : PENINGKATAN JALAN NAMBO - TERAS BENDUNG


Lokasi : KECAMATAN CIRUAS
Program : PEMBANGUNAN JALAN DAN JEMBATAN
Kegiatan : PEMBANGUNAN JALAN
Sumber Dana : DAU - APBD Kabupaten Serang
Nomor Kontrak : 620/14-PK.02/SPK/PPK-BM/DPUK/2016
Tanggal Kontrak : ###
Nilai Kontrak : Rp. 3.136.763.000,00

PENYEDIA JASA :

TAHUN ANGGARAN 2016


PEMERINTAH KABUPATEN SERANG
DINAS PEKERJAAN UMUM
BIDANG BINA MARGA
Jl. Samaun Bakri Telp. (0254) 200363 Serang

LAPORAN MINGGUAN
KEMAJUAN FISIK PEKERJAAN

MINGGU KE : 2 (DUA)
PERIODE : 31 MARET s/d 6 APRIL 2016

Paket Pekerjaan : PENINGKATAN JALAN NAMBO - TERAS BENDUNG


Lokasi : KECAMATAN CIRUAS
Program : PEMBANGUNAN JALAN DAN JEMBATAN
Kegiatan : PEMBANGUNAN JALAN
Sumber Dana : DAU - APBD Kabupaten Serang
Nomor Kontrak : 620/14-PK.02/SPK/PPK-BM/DPUK/2016
Tanggal Kontrak : ###
Nilai Kontrak : Rp. 3.136.763.000,00

PENYEDIA JASA :

TAHUN ANGGARAN 2016


PEMERINTAH KABUPATEN SERANG
DINAS PEKERJAAN UMUM
BIDANG BINA MARGA
Jl. Samaun Bakri Telp. (0254) 200363 Serang

LAPORAN MINGGUAN
KEMAJUAN FISIK PEKERJAAN

MINGGU KE : 3 (TIGA)
PERIODE : 7 APRIL s/d 13 APRIL 2016

Paket Pekerjaan : PENINGKATAN JALAN NAMBO - TERAS BENDUNG


Lokasi : KECAMATAN CIRUAS
Program : PEMBANGUNAN JALAN DAN JEMBATAN
Kegiatan : PEMBANGUNAN JALAN
Sumber Dana : DAU - APBD Kabupaten Serang
Nomor Kontrak : 620/14-PK.02/SPK/PPK-BM/DPUK/2016
Tanggal Kontrak : ###
Nilai Kontrak : Rp. 3.136.763.000,00

PENYEDIA JASA :

TAHUN ANGGARAN 2016


PEMERINTAH KABUPATEN SERANG
DINAS PEKERJAAN UMUM
BIDANG BINA MARGA
Jl. Samaun Bakri Telp. (0254) 200363 Serang

LAPORAN MINGGUAN
KEMAJUAN FISIK PEKERJAAN

MINGGU KE : 4 (EMPAT)
PERIODE : 14 APRIL s/d 20 APRIL 2016

Paket Pekerjaan : PENINGKATAN JALAN NAMBO - TERAS BENDUNG


Lokasi : KECAMATAN CIRUAS
Program : PEMBANGUNAN JALAN DAN JEMBATAN
Kegiatan : PEMBANGUNAN JALAN
Sumber Dana : DAU - APBD Kabupaten Serang
Nomor Kontrak : 620/14-PK.02/SPK/PPK-BM/DPUK/2016
Tanggal Kontrak : ###
Nilai Kontrak : Rp. 3.136.763.000,00

PENYEDIA JASA :

TAHUN ANGGARAN 2016


PEMERINTAH KABUPATEN SERANG
DINAS PEKERJAAN UMUM
BIDANG BINA MARGA
Jl. Samaun Bakri Telp. (0254) 200363 Serang
LAPORAN MINGGUAN
PROGRAM : PEMBANGUNAN JALAN DAN JEMBATAN Laporan Minggu Ini
KEGIATAN : PEMBANGUNAN JALAN Tanggal 24 MARET s/d 30 MARET 2016
PEKERJAAN : PENINGKATAN JALAN NAMBO - TERAS BENDUNG Minggu Ke 1 (SATU)
LOKASI : KECAMATAN CIRUAS Bulan 1 (SATU)
DANA/TAHUN ANGGARAN : DAU - APBD Kabupaten Serang 2016

TENAGA KERJA BAHAN - BAHAN BANGUNAN HASIL KERJA


BANYAKNYA BANYAKNYA VOLUME BOBOT % JUMLAH
S/D MINGGU JENIS S/D MINGGU MACAM S/D MINGGU TARGET BOBOTNYA
KEAHLIAN
MINGGU INI JUMLAH BAHAN SAT. MINGGU INI JUMLAH PEKERJAAN RENCANA SAT. MINGGU INI JUMLAH % S/D
LALU LALU LALU INI
1 PENGAWAS I PEKERJAAN UMUM
2 PELAKSANA 1.2 Mobilisasi 1.00 Ls 0.06 0.06 0.663 0.04
3 MANDOR Pembuatan Papan Nama proyek
4 TUKANG Pengujian Laboratorium
5 PEKERJA Direksikeet
6 OPERATOR Dokumentasi dan Rekaman Proyek
7 SUPIR Pengukuran dan Pematokan
Mobilisasi dan Demobilisasi Alat

1.8.(1) Pemeliharaan & Perlindungan Lalu Lintas 1.00 Ls 0.00 0.00 0.351 0.00

III PEKERJAAN TANAH


3.1.(10) Galian Biasa untuk Oprit 6.00 M3 0.00 0.00 0.011 0.00
ALAT-ALAT 3.1.(10) Galian pada bahu (untuk pelebaran) 380.25 M3 0.00 0.00 0.707 0.00
BANYAKNYA 3.4.6 Pembersihan semak - semak 2,028.00 M2 0.00 0.00 0.167 0.00
S/D MINGGU
JENIS ALAT MINGGU INI JUMLAH IV PELEB. PERKERASAN DAN BAHU JALAN
LALU 4.2.(1) Lapis Pondasi Agregat A 152.10 M3 0.00 0.00 1.215 0.00
4.2.(2a) Lapis Pondasi Agregat B 228.15 M3 0.00 0.00 1.819 0.00
4.2.(2d) Timbunan Bahu jalan (Agregat kelas B) 303.00 M3 0.00 0.00 2.331 0.00
7.1.(4) Beton Oprit (beton Semen K-400) 3.60 M3 0.00 0.00 0.139 0.00
7.1.(11) Acuan Untuk Beton 6.00 M2 0.00 0.00 0.023 0.00

V PERKERASAN BERBUTIR DAN BETON SEMEN


5.1.1 Perbaikan Lapis Pondasi Agregat Kelas A 117.25 M3 0.00 0.00 0.931 0.00
5.1.2 Perbaikan Lapis Pondasi Agregat Kelas B 74.19 M3 0.00 0.00 0.581 0.00
5.3.(3) Lapis Pondasi Bawah Beton Kurus (K-125) 527.28 M3 0.00 0.00 16.892 0.00
5.3.1 Perkerasan Beton Semen (K-400) P=1.014 M 1,014.00 M3 0.00 0.00 46.396 0.00
5.3.(4) Baja Tulangan untuk perkerasan Beton 19,053.06 Kg 0.00 0.00 8.670 0.00
5.3.(5) Acuan untuk Perkerasan Beton 636.79 M2 0.00 0.00 2.483 0.00

VII PEKERJAAN STRUKTUR


Tembok Penahan Tanah :
(P=100 m : T=-0.7 m)
(P=618 m : T=-1 m)
3.1.(10) Galian Tanah Untuk TPT 264.70 M3 0.00 0.00 0.492 0.00
7.9.(1) Pasangan Batu Untuk TPT 634.70 M3 0.00 0.00 15.442 0.00
7.9.(2) Plesteran Untuk TPT 308.40 M2 0.00 0.00 0.521 0.00
3.2.4 Timbunan Kembali Untuk TPT 175.50 M3 0.00 0.00 0.166 0.00

JUMLAH 100.00 0.04

Serang, 31 Maret 2016


Mengetahui : Menyetujui : Disetujui : Pelaksana
Pejabat Pelaksana Teknis Kegiatan Pelaksana Teknis KONSULTAN PENGAWAS PT. DUA PUTRI MANDIRI
Bid. Bina Marga DPU Kab. Serang Bid. Bina Marga DPU Kab. Serang CV. JAYA WAHANA RAYA

H. M. RONNY N, ST, MM KANAFIYAH, ST ADI AMIRULLOH, ST AGUS DWI PUTRA, ST


NIP. 19751005 200312 1 007 NIP. 19770906 200801 1 003 SUPERVISION ENGINEER PROJECT MANAGER
PEMERINTAH KABUPATEN SERANG
DINAS PEKERJAAN UMUM
BIDANG BINA MARGA
Jl. Samaun Bakri Telp. (0254) 200363 Serang
LAPORAN MINGGUAN
PROGRAM : PEMBANGUNAN JALAN DAN JEMBATAN Laporan Minggu Ini
KEGIATAN : PEMBANGUNAN JALAN Tanggal 31 MARET s/d 6 APRIL 2016
PEKERJAAN : PENINGKATAN JALAN NAMBO - TERAS BENDUNG Minggu Ke 2 (DUA)
LOKASI : KECAMATAN CIRUAS Bulan 1 (SATU)
DANA/TAHUN ANGGARAN : DAU - APBD Kabupaten Serang 2016

TENAGA KERJA BAHAN - BAHAN BANGUNAN HASIL KERJA


BANYAKNYA BANYAKNYA VOLUME BOBOT % JUMLAH
S/D MINGGU JENIS S/D MINGGU MACAM S/D MINGGU TARGET BOBOTNYA
KEAHLIAN
MINGGU INI JUMLAH BAHAN SAT. MINGGU INI JUMLAH PEKERJAAN RENCANA SAT. MINGGU INI JUMLAH % S/D
LALU LALU LALU INI
1 PENGAWAS 1 1 1 Bambu Patok ls 1 1 I PEKERJAAN UMUM
2 PELAKSANA 3 3 1.2 Mobilisasi 1.00 Ls 0.06 0.06 0.12 0.663 0.08
3 MANDOR Pembuatan Papan Nama proyek
4 TUKANG Pengujian Laboratorium
5 PEKERJA 4 4 Direksikeet
6 OPERATOR Dokumentasi dan Rekaman Proyek
7 SUPIR Pengukuran dan Pematokan
Mobilisasi dan Demobilisasi Alat

1.8.(1) Pemeliharaan & Perlindungan Lalu Lintas 1.00 Ls 0.00 0.00 0.00 0.351 0.00

III PEKERJAAN TANAH


3.1.(10) Galian Biasa untuk Oprit 6.00 M3 0.00 0.00 0.00 0.011 0.00
ALAT-ALAT 3.1.(10) Galian pada bahu (untuk pelebaran) 380.25 M3 0.00 0.00 0.00 0.707 0.00
BANYAKNYA 3.4.6 Pembersihan semak - semak 2028.00 M2 0.00 0.00 0.00 0.167 0.00
S/D MINGGU
JENIS ALAT MINGGU INI JUMLAH IV PELEB. PERKERASAN DAN BAHU JALAN
LALU 4.2.(1) Lapis Pondasi Agregat A 152.10 M3 0.00 0.00 0.00 1.215 0.00
1 Palu 1 1 4.2.(2a) Lapis Pondasi Agregat B 228.15 M3 0.00 0.00 0.00 1.819 0.00
2 Meteran 1 1 4.2.(2d) Timbunan Bahu jalan (Agregat kelas B) 304.20 M3 0.00 0.00 0.00 2.341 0.00
7.1.(4) Beton Oprit (beton Semen K-400) 3.00 M3 0.00 0.00 0.00 0.116 0.00
7.1.(11) Acuan Untuk Beton 4.40 M2 0.00 0.00 0.00 0.017 0.00

V PERKERASAN BERBUTIR DAN BETON SEMEN


5.1.1 Perbaikan Lapis Pondasi Agregat Kelas A 110.93 M3 0.00 0.00 0.00 0.880 0.00
5.1.2 Perbaikan Lapis Pondasi Agregat Kelas B 72.91 M3 0.00 0.00 0.00 0.571 0.00
5.3.(3) Lapis Pondasi Bawah Beton Kurus (K-125) 527.28 M3 0.00 0.00 0.00 16.892 0.00
5.3.1 Perkerasan Beton Semen (K-400) P=1.014 M 1014.00 M3 0.00 0.00 0.00 46.396 0.00
5.3.(4) Baja Tulangan untuk perkerasan Beton 19053.06 Kg 0.00 0.00 0.00 8.670 0.00
5.3.(5) Acuan untuk Perkerasan Beton 608.40 M2 0.00 0.00 0.00 2.372 0.00

VII PEKERJAAN STRUKTUR


Tembok Penahan Tanah :
(P=100 m : T=-0.7 m)
(P=618 m : T=-1 m)
3.1.(10) Galian Tanah Untuk TPT 268.20 M3 0.00 0.00 0.00 0.499 0.00
7.9.(1) Pasangan Batu Untuk TPT 639.60 M3 0.00 0.00 0.00 15.562 0.00
7.9.(2) Plesteran Untuk TPT 349.00 M2 0.00 0.00 0.00 0.589 0.00
3.2.4 Timbunan Kembali Untuk TPT 172.00 M3 0.00 0.00 0.00 0.162 0.00

JUMLAH 100.00 0.080

Serang, 7 April 2016


Mengetahui : Menyetujui : Disetujui : Pelaksana
Pejabat Pelaksana Teknis Kegiatan Pelaksana Teknis KONSULTAN PENGAWAS PT. DUA PUTRI MANDIRI
Bid. Bina Marga DPU Kab. Serang Bid. Bina Marga DPU Kab. Serang CV. JAYA WAHANA RAYA

H. M. RONNY N, ST, MM KANAFIYAH, ST ADI AMIRULLOH, ST AGUS DWI PUTRA, ST


NIP. 19751005 200312 1 007 NIP. 19770906 200801 1 003 SUPERVISION ENGINEER PROJECT MANAGER
PEMERINTAH KABUPATEN SERANG
DINAS PEKERJAAN UMUM
BIDANG BINA MARGA
Jl. Samaun Bakri Telp. (0254) 200363 Serang
LAPORAN MINGGUAN
PROGRAM : PEMBANGUNAN JALAN DAN JEMBATAN Laporan Minggu Ini
KEGIATAN : PEMBANGUNAN JALAN Tanggal 7 APRIL s/d 13 APRIL 2016
PEKERJAAN : PENINGKATAN JALAN NAMBO - TERAS BENDUNG Minggu Ke 3 (TIGA)
LOKASI : KECAMATAN CIRUAS Bulan 1 (SATU)
DANA/TAHUN ANGGARAN : DAU - APBD Kabupaten Serang 2016

TENAGA KERJA BAHAN - BAHAN BANGUNAN HASIL KERJA


BANYAKNYA BANYAKNYA VOLUME BOBOT % JUMLAH
S/D MINGGU JENIS S/D MINGGU MACAM S/D MINGGU TARGET BOBOTNYA
KEAHLIAN
MINGGU INI JUMLAH BAHAN SAT. MINGGU INI JUMLAH PEKERJAAN RENCANA SAT. MINGGU INI JUMLAH % S/D
LALU LALU LALU INI
1 PENGAWAS 1 1 1 Bambu Patok ls 1 1 I PEKERJAAN UMUM
2 PELAKSANA 3 3 6 1.2 Mobilisasi 1.00 Ls 0.12 0.06 0.18 0.663 0.12
3 MANDOR Pembuatan Papan Nama proyek
4 TUKANG Pengujian Laboratorium
5 PEKERJA 4 2 6 Direksikeet
6 OPERATOR Dokumentasi dan Rekaman Proyek
7 SUPIR Pengukuran dan Pematokan
Mobilisasi dan Demobilisasi Alat

1.8.(1) Pemeliharaan & Perlindungan Lalu Lintas 1.00 Ls 0.00 0.00 0.00 0.351 0.00

III PEKERJAAN TANAH


3.1.(10) Galian Biasa untuk Oprit 6.00 M3 0.00 0.00 0.00 0.011 0.00
3.1.(10) Galian pada bahu (untuk pelebaran) 380.25 M3 0.00 0.00 0.00 0.707 0.00
ALAT-ALAT 3.4.6 Pembersihan semak - semak 2028.00 M2 0.00 0.00 0.00 0.167 0.00
BANYAKNYA
S/D MINGGU IV PELEB. PERKERASAN DAN BAHU JALAN
JENIS ALAT MINGGU INI JUMLAH 4.2.(1) Lapis Pondasi Agregat A 152.10 M3 0.00 0.00 0.00 1.215 0.00
LALU 4.2.(2a) Lapis Pondasi Agregat B 228.15 M3 0.00 0.00 0.00 1.819 0.00
1 Palu 1 1 4.2.(2d) Timbunan Bahu jalan (Agregat kelas B) 304.20 M3 0.00 0.00 0.00 2.341 0.00
2 Meteran 1 1 7.1.(4) Beton Oprit (beton Semen K-400) 3.00 M3 0.00 0.00 0.00 0.116 0.00
7.1.(11) Acuan Untuk Beton 4.40 M2 0.00 0.00 0.00 0.017 0.00

V PERKERASAN BERBUTIR DAN BETON SEMEN


5.1.1 Perbaikan Lapis Pondasi Agregat Kelas A 110.93 M3 0.00 0.00 0.00 0.880 0.00
5.1.2 Perbaikan Lapis Pondasi Agregat Kelas B 72.91 M3 0.00 0.00 0.00 0.571 0.00
5.3.(3) Lapis Pondasi Bawah Beton Kurus (K-125) 527.28 M3 0.00 0.00 0.00 16.892 0.00
5.3.1 Perkerasan Beton Semen (K-400) P=1.014 M 1014.00 M3 0.00 0.00 0.00 46.396 0.00
5.3.(4) Baja Tulangan untuk perkerasan Beton 19053.06 Kg 0.00 0.00 0.00 8.670 0.00
5.3.(5) Acuan untuk Perkerasan Beton 608.40 M2 0.00 0.00 0.00 2.372 0.00

VII PEKERJAAN STRUKTUR


Tembok Penahan Tanah :
(P=100 m : T=-0.7 m)
(P=618 m : T=-1 m)
3.1.(10) Galian Tanah Untuk TPT 268.20 M3 0.00 0.00 0.00 0.499 0.00
7.9.(1) Pasangan Batu Untuk TPT 639.60 M3 0.00 0.00 0.00 15.562 0.00
7.9.(2) Plesteran Untuk TPT 349.00 M2 0.00 0.00 0.00 0.589 0.00
3.2.4 Timbunan Kembali Untuk TPT 172.00 M3 0.00 0.00 0.00 0.162 0.00

JUMLAH 100.00 0.119

Serang, 14 April 2016


Mengetahui : Menyetujui : Disetujui : Pelaksana
Pejabat Pelaksana Teknis Kegiatan Pelaksana Teknis KONSULTAN PENGAWAS PT. DUA PUTRI MANDIRI
Bid. Bina Marga DPU Kab. Serang Bid. Bina Marga DPU Kab. Serang CV. JAYA WAHANA RAYA

H. M. RONNY N, ST, MM KANAFIYAH, ST ADI AMIRULLOH, ST AGUS DWI PUTRA, ST


NIP. 19751005 200312 1 007 NIP. 19770906 200801 1 003 SUPERVISION ENGINEER PROJECT MANAGER
PEMERINTAH KABUPATEN SERANG
DINAS PEKERJAAN UMUM
BIDANG BINA MARGA
Jl. Samaun Bakri Telp. (0254) 200363 Serang
LAPORAN MINGGUAN
PROGRAM : PEMBANGUNAN JALAN DAN JEMBATAN Laporan Minggu Ini
KEGIATAN : PEMBANGUNAN JALAN Tanggal 14 APRIL s/d 20 APRIL 2016
PEKERJAAN : PENINGKATAN JALAN NAMBO - TERAS BENDUNG Minggu Ke 4 (EMPAT)
LOKASI : KECAMATAN CIRUAS Bulan 1 (SATU)
DANA/TAHUN ANGGARAN : DAU - APBD Kabupaten Serang 2016

TENAGA KERJA BAHAN - BAHAN BANGUNAN HASIL KERJA


BANYAKNYA BANYAKNYA VOLUME BOBOT % JUMLAH
S/D MINGGU JENIS S/D MINGGU MACAM S/D MINGGU TARGET BOBOTNYA
KEAHLIAN
MINGGU INI JUMLAH BAHAN SAT. MINGGU INI JUMLAH PEKERJAAN RENCANA SAT. MINGGU INI JUMLAH % S/D
LALU LALU LALU INI
1 PENGAWAS 1 4 5 1 Bambu Patok ls 1 1 I PEKERJAAN UMUM
2 PELAKSANA 6 15 21 2 Kaso Btng 6 6 1.2 Mobilisasi 1.00 Ls 0.18 0.12 0.30 0.663 0.20
3 MANDOR 3 Paku Kg 2 2 Pembuatan Papan Nama proyek
4 TUKANG 2 2 Pengujian Laboratorium
5 PEKERJA 6 2 8 Direksikeet
6 OPERATOR 4 4 Dokumentasi dan Rekaman Proyek
7 SUPIR 2 2 Pengukuran dan Pematokan
8 PEMBANTU OPERATOR 2 2 Mobilisasi dan Demobilisasi Alat

1.8.(1) Pemeliharaan & Perlindungan Lalu Lintas 1.00 Ls 0.00 0.08 0.08 0.351 0.03

III PEKERJAAN TANAH


3.1.(10) Galian Biasa untuk Oprit 6.00 M3 0.00 0.00 0.00 0.011 0.00
3.1.(10) Galian pada bahu (untuk pelebaran) 380.25 M3 0.00 0.00 0.00 0.707 0.00
ALAT-ALAT 3.4.6 Pembersihan semak - semak 2028.00 M2 0.00 676.00 676.00 0.167 0.06
BANYAKNYA
S/D MINGGU IV PELEB. PERKERASAN DAN BAHU JALAN
JENIS ALAT MINGGU INI JUMLAH 4.2.(1) Lapis Pondasi Agregat A 152.10 M3 0.00 0.00 0.00 1.215 0.00
LALU 4.2.(2a) Lapis Pondasi Agregat B 228.15 M3 0.00 0.00 0.00 1.819 0.00
1 Palu 1 1 2 4.2.(2d) Timbunan Bahu jalan (Agregat kelas B) 304.20 M3 0.00 0.00 0.00 2.341 0.00
2 Meteran 1 1 7.1.(4) Beton Oprit (beton Semen K-400) 3.00 M3 0.00 0.00 0.00 0.116 0.00
3 Excavator 4 4 7.1.(11) Acuan Untuk Beton 4.40 M2 0.00 0.00 0.00 0.017 0.00
4 Gergaji 1 1
5 Dump Truck 2 2 V PERKERASAN BERBUTIR DAN BETON SEMEN
5.1.1 Perbaikan Lapis Pondasi Agregat Kelas A 110.93 M3 0.00 0.00 0.00 0.880 0.00
5.1.2 Perbaikan Lapis Pondasi Agregat Kelas B 72.91 M3 0.00 0.00 0.00 0.571 0.00
5.3.(3) Lapis Pondasi Bawah Beton Kurus (K-125) 527.28 M3 0.00 0.00 0.00 16.892 0.00
5.3.1 Perkerasan Beton Semen (K-400) P=1.014 M 1014.00 M3 0.00 0.00 0.00 46.396 0.00
5.3.(4) Baja Tulangan untuk perkerasan Beton 19053.06 Kg 0.00 0.00 0.00 8.670 0.00
5.3.(5) Acuan untuk Perkerasan Beton 608.40 M2 0.00 0.00 0.00 2.372 0.00

VII PEKERJAAN STRUKTUR


Tembok Penahan Tanah :
(P=100 m : T=-0.7 m)
(P=618 m : T=-1 m)
3.1.(10) Galian Tanah Untuk TPT 268.20 M3 0.00 0.00 0.00 0.499 0.00
7.9.(1) Pasangan Batu Untuk TPT 639.60 M3 0.00 0.00 0.00 15.562 0.00
7.9.(2) Plesteran Untuk TPT 349.00 M2 0.00 0.00 0.00 0.589 0.00
3.2.4 Timbunan Kembali Untuk TPT 172.00 M3 0.00 0.00 0.00 0.162 0.00

JUMLAH % 100.00 0.283

Serang, 21 April 2016


Mengetahui : Menyetujui : Disetujui : Pelaksana
Pejabat Pelaksana Teknis Kegiatan Pelaksana Teknis KONSULTAN PENGAWAS PT. DUA PUTRI MANDIRI
Bid. Bina Marga DPU Kab. Serang Bid. Bina Marga DPU Kab. Serang CV. JAYA WAHANA RAYA

H. M. RONNY N, ST, MM KANAFIYAH, ST ADI AMIRULLOH, ST AGUS DWI PUTRA, ST


NIP. 19751005 200312 1 007 NIP. 19770906 200801 1 003 SUPERVISION ENGINEER PROJECT MANAGER
PEMERINTAH KABUPATEN SERANG
DINAS PEKERJAAN UMUM
BIDANG BINA MARGA
Jl. Samaun Bakri Telp. (0254) 200363 Serang

LAPORAN BULANAN
KEMAJUAN FISIK PEKERJAAN

BULAN KE : 1 (SATU)
PERIODE : 24 MARET S/D 20 APRIL 2016

Paket Pekerjaan : PENINGKATAN JALAN NAMBO - TERAS BENDUNG


Lokasi : KECAMATAN CIRUAS
Program : PEMBANGUNAN JALAN DAN JEMBATAN
Kegiatan : PEMBANGUNAN JALAN
Sumber Dana : DAU - APBD Kabupaten Serang
Nomor Kontrak : 620/14-PK.02/SPK/PPK-BM/DPUK/2016
Tanggal Kontrak : ###
Nilai Kontrak : Rp. 3.136.763.000,00

PENYEDIA JASA :

TAHUN ANGGARAN 2016


LAPORAN BULANAN KEMAJUAN FISIK PEKERJAAN

BULAN KE : 1 (SATU)
PERIODE : 24 MARET S/D 20 APRIL 2016
PEKERJAAN : PENINGKATAN JALAN NAMBO - TERAS BENDUNG
LOKASI : KECAMATAN CIRUAS

PROGRAM : PEMBANGUNAN JALAN DAN JEMBATAN NO. KONTRAK : 620/14-PK.02/SPK/PPK-BM/DPUK/2016


KEGIATAN : PEMBANGUNAN JALAN TGL. KONTRAK : ###
NILAI KONTRAK : Rp. 3.136.763.000,00

KONTRAK AWAL MC 0 PROGRES PELAKSANAAN


BOBOT
NO URAIAN PEKERJAAN SAT KUANTITAS HARGA SATUAN KUANTITAS HARGA SATUAN % S/D BULAN LALU BULAN INI S/D BULAN INI SISA S/D BULAN INI
AWAL (Rp.) MC 0 MC. 0 (Rp.) JUMLAH HARGA
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I PEKERJAAN UMUM
1.2 Mobilisasi Ls 1.00 18,900,000.00 1.00 18,900,000.00 18,900,000.00 0.66 0.30 0.20 0.30 0.20 0.70 0.46
Pembuatan Papan Nama proyek
Pengujian Laboratorium
Direksikeet
Dokumentasi dan Rekaman Proyek
Pengukuran dan Pematokan
Mobilisasi dan Demobilisasi Alat

1.8.(1) Pemeliharaan & Perlindungan Lalu Lintas Ls 1.00 10,000,000.00 1.00 10,000,000.00 10,000,000.00 0.35 0.08 0.03 0.08 0.03 0.92 0.32

III PEKERJAAN TANAH


3.1.(10) Galian Biasa untuk Oprit M3 6.00 53,006.25 6.00 53,006.25 318,037.50 0.01 0.00 0.00 0.00 0.00 6.00 0.01
3.1.(10) Galian pada bahu (untuk pelebaran) M3 380.25 53,006.25 380.25 53,006.25 20,155,626.56 0.71 0.00 0.00 0.00 0.00 380.25 0.71
3.4.6 Pembersihan semak - semak M2 2,028.00 2,347.81 2028.00 2,347.81 4,761,358.68 0.17 676.00 0.06 676.00 0.06 1352.00 0.11

IV PELEB. PERKERASAN DAN BAHU JALAN


4.2.(1) Lapis Pondasi Agregat A M3 152.10 227,876.00 152.10 227,876.00 34,659,939.60 1.22 0.00 0.00 0.00 0.00 152.10 1.22
4.2.(2a) Lapis Pondasi Agregat B M3 228.15 227,414.00 228.15 227,414.00 51,884,504.10 1.82 0.00 0.00 0.00 0.00 228.15 1.82
4.2.(2d) Timbunan Bahu jalan (Agregat kelas B) M3 303.00 219,417.00 304.20 219,417.00 66,746,651.40 2.34 0.00 0.00 0.00 0.00 304.20 2.34
7.1.(4) Beton Oprit (beton Semen K-400) M3 3.60 1,099,574.30 3.00 1,099,574.30 3,298,722.90 0.12 0.00 0.00 0.00 0.00 3.00 0.12
7.1.(11) Acuan Untuk Beton M2 6.00 111,168.75 4.40 111,168.75 489,142.50 0.02 0.00 0.00 0.00 0.00 4.40 0.02

V PERKERASAN BERBUTIR DAN BETON SEMEN


5.1.1 Perbaikan Lapis Pondasi Agregat Kelas A M3 117.25 226,315.65 110.93 226,315.65 25,105,195.05 0.88 0.00 0.00 0.00 0.00 110.93 0.88
5.1.2 Perbaikan Lapis Pondasi Agregat Kelas B M3 74.19 223,235.65 72.91 223,235.65 16,276,390.29 0.57 0.00 0.00 0.00 0.00 72.91 0.57
5.3.(3) Lapis Pondasi Bawah Beton Kurus (K-125) M3 527.28 913,554.95 527.28 913,554.95 481,699,254.04 16.89 0.00 0.00 0.00 0.00 527.28 16.89
5.3.1 Perkerasan Beton Semen (K-400) P=1.014 M M3 1,014.00 1,304,753.18 1014.00 1,304,753.18 1,323,019,724.52 46.40 0.00 0.00 0.00 0.00 1014.00 46.40
5.3.(4) Baja Tulangan untuk perkerasan Beton Kg 19,053.06 12,976.56 19053.06 12,976.56 247,243,176.27 8.67 0.00 0.00 0.00 0.00 19053.06 8.67
5.3.(5) Acuan untuk Perkerasan Beton M2 636.79 111,168.75 608.40 111,168.75 67,635,067.50 2.37 0.00 0.00 0.00 0.00 608.40 2.37

VII PEKERJAAN STRUKTUR


Tembok Penahan Tanah :
(P=100 m : T=-0.7 m)
(P=618 m : T=-1 m)
3.1.(10) Galian Tanah Untuk TPT M3 264.70 53,006.25 268.20 53,006.25 14,216,276.25 0.50 0.00 0.00 0.00 0.00 268.20 0.50
7.9.(1) Pasangan Batu Untuk TPT M3 634.70 693,802.24 639.60 693,802.24 443,755,912.70 15.56 0.00 0.00 0.00 0.00 639.60 15.56
7.9.(2) Plesteran Untuk TPT M2 308.40 48,159.65 349.00 48,159.65 16,807,717.85 0.59 0.00 0.00 0.00 0.00 349.00 0.59
3.2.4 Timbunan Kembali Untuk TPT M3 175.50 26,921.68 172.00 26,921.68 4,630,528.96 0.16 0.00 0.00 0.00 0.00 172.00 0.16

JUMLAH 2,851,603,226.68 100.00 0.00 0.28 0.28 99.72

Serang, 21 April 2016


Mengetahui : Menyetujui : Disetujui : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan Pelaksana Teknis KONSULTAN PENGAWAS Kontraktor Pelaksana
Bid. Bina Marga DPU Kab. Serang Bid. Bina Marga DPU Kab. Serang CV. JAYA WAHANA RAYA PT. DUA PUTRI MANDIRI

H. M. RONNY N, ST, MM KANAFIYAH, ST ADI AMIRULLOH, ST AGUS DWI PUTRA, ST


NIP. 19751005 200312 1 007 NIP. 19770906 200801 1 003 SUPERVISION ENGINEER PROJECT MANAGER
GRAFIK TENAGA KERJA
CV. JAYA WAHANA RAYA
PEMBANGUNAN JALAN DAN JEMBATAN
PEKERJAAN :

PENINGKATAN JALAN NAMBO - TERAS BENDUNG


Minggu Ke : 1 (SATU)
LOKASI : KECAMATAN CIRUAS Bulan : 1 (SATU)
TAHUN : 2016 PERIODE TANGGAL : 24 MARET s/d 30 MARET 2016

TANGGAL
TENAGA
KERJA
KET.
MARET APRIL
24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

105
100
95
90
85
80
75
70
65
60
55
50
45
40
35
30
25
20
15
10
5
0
Jml. Orang 0 0 0 0 0 0 0

Serang, 31 Maret 2016


Dibuat Oleh,
Disetujui : KONTRAKTOR PELAKSANA
KONSULTAN PENGAWAS PT. DUA PUTRI MANDIRI
CV. JAYA WAHANA RAYA

ADI AMIRULLOH, ST AGUS DWI PUTRA, ST


SUPERVISION ENGINEER PROJECT MANAGER
GRAFIK TENAGA KERJA
CV. JAYA WAHANA RAYA PEMBANGUNAN JALAN DAN JEMBATAN
PEKERJAAN :

PENINGKATAN JALAN NAMBO - TERAS BENDUNG


Minggu Ke : 2 (DUA)
LOKASI : KECAMATAN CIRUAS Bulan : 1 (SATU)
TAHUN : 2016 PERIODE TANGGAL : 31 MARET s/d 6 APRIL 2016

TANGGAL
TENAGA
KERJA
KET.
MARET APRIL
24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

105
100
95
90
85
80
75
70
65
60
55
50
45
40
35
30
25
20
15
10
5
0
Jml. Orang 8 0 0 0 0 0 0

Serang, 7 April 2016


Dibuat Oleh,
Disetujui : KONTRAKTOR PELAKSANA
KONSULTAN PENGAWAS PT. DUA PUTRI MANDIRI
CV. JAYA WAHANA RAYA

ADI AMIRULLOH, ST AGUS DWI PUTRA, ST


SUPERVISION ENGINEER PROJECT MANAGER
GRAFIK TENAGA KERJA
CV. JAYA WAHANA RAYA PEMBANGUNAN JALAN DAN JEMBATAN
PEKERJAAN :

PENINGKATAN JALAN NAMBO - TERAS BENDUNG


Minggu Ke : 3 (TIGA)
LOKASI : KECAMATAN CIRUAS Bulan : 1 (SATU)
TAHUN : 2016 PERIODE TANGGAL : 7 APRIL s/d 13 APRIL 2016

TANGGAL
TENAGA
KERJA
KET.
MARET APRIL
24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

105
100
95
90
85
80
75
70
65
60
55
50
45
40
35
30
25
20
15
10
5
0
Jml. Orang 0 0 0 0 0 0 5

Serang, 14 April 2016


Dibuat Oleh,
Disetujui : KONTRAKTOR PELAKSANA
KONSULTAN PENGAWAS PT. DUA PUTRI MANDIRI
CV. JAYA WAHANA RAYA

ADI AMIRULLOH, ST AGUS DWI PUTRA, ST


SUPERVISION ENGINEER PROJECT MANAGER
GRAFIK TENAGA KERJA
CV. JAYA WAHANA RAYA
PEMBANGUNAN JALAN DAN JEMBATAN
PEKERJAAN :

PENINGKATAN JALAN NAMBO - TERAS BENDUNG


Minggu Ke : 4 (EMPAT)
LOKASI : KECAMATAN CIRUAS Bulan : 1 (SATU)
TAHUN : 2015 PERIODE TANGGAL : 14 APRIL s/d 20 APRIL 2016

TANGGAL
TENAGA
KERJA
KET.
MARET APRIL
24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

105
100
95
90
85
80
75
70
65
60
55
50
45
40
35
30
25
20
15
10
5
0
Jml. Orang 5 0 0 6 8 6 6

Serang, 21 April 2016


Dibuat Oleh,
Disetujui : KONTRAKTOR PELAKSANA
KONSULTAN PENGAWAS PT. DUA PUTRI MANDIRI
CV. JAYA WAHANA RAYA

ADI AMIRULLOH, ST AGUS DWI PUTRA, ST


SUPERVISION ENGINEER PROJECT MANAGER
Paket Pekerjaan : PENINGKATAN JALAN NAMBO - TERAS BENDUNG
Lokasi : KECAMATAN CIRUAS
Program : PEMBANGUNAN JALAN DAN JEMBATAN
JADWAL PELAKSANAAN
Kegiatan : PEMBANGUNAN JALAN

BULAN KE I BULAN KE II BULAN KE III BULAN KE IV BULAN KE V


NO JENIS PEKERJAAN SAT KUANT. BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 KET
24 Mar - 30 Mar 31 Mar - 6 Apr 7 Apr - 13 Apr 14 Apr - 20 Apr 21 Apr - 27 Apr 28 Apr - 4 Mei 5 Mei - 11 Mei 12 Mei - 18 Mei 19 Mei - 25 Mei 26 Mei - 1 Jun 2 Jun - 8 Jun 9 Jun - 15 Jun 16 Jun - 22 Jun 23 Jun - 29 Jun 30 Jun - 6 Jul 7 Jul - 13 Jul 14 Jul - 20 Jul 21-Jul

I PEKERJAAN UMUM
1.2 Mobilisasi Ls 1.00 0.663 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041
Pembuatan Papan Nama proyek
Pengujian Laboratorium
Direksikeet
Dokumentasi dan Rekaman Proyek
Pengukuran dan Pematokan
Mobilisasi dan Demobilisasi Alat
1.8.(1) Pemeliharaan & Perlindungan Lalu Lintas Ls 1.00 0.351 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022

III PEKERJAAN TANAH


3.1.(10) Galian Biasa untuk Oprit M3 6.00 0.011 0.006 0.006
3.1.(10)
3.4.6
Galian pada bahu (untuk pelebaran)
Pembersihan semak - semak
M3
M2
380.25
2,028.00
0.707
0.167
0.236
0.056
0.236
0.056
0.236
0.056 L
IV PELEB. PERKERASAN DAN BAHU JALAN
I
4.2.(1) Lapis Pondasi Agregat A M3 152.10 1.215 0.405 0.405 0.405 B
4.2.(2a)
4.2.(2d)
Lapis Pondasi Agregat B
Timbunan Bahu jalan (Agregat kelas B)
M3
M3
228.15
303.00
1.819
2.341
0.606 0.606 0.606
1.170 1.170
U
7.1.(4) Beton Oprit (beton Semen K-400) M3 3.60 0.116 0.058 0.058 R
7.1.(11) Acuan Untuk Beton M2 6.00 0.017 0.009 0.009

V
5.1.1
PERKERASAN BERBUTIR DAN BETON SEMEN
Perbaikan Lapis Pondasi Agregat Kelas A M3 117.25 0.880 0.293 0.293 0.293
I
5.1.2 Perbaikan Lapis Pondasi Agregat Kelas B M3 74.19 0.571 0.190 0.190 0.190 D
5.3.(3)
5.3.1
Lapis Pondasi Bawah Beton Kurus (K-125)
Perkerasan Beton Semen (K-400) P=1.014 M
M3
M3
527.28
1,014.00
16.892
46.396
2.413
6.628
2.413
6.628
2.413
6.628
2.413
6.628
2.413
6.628
2.413
6.628
2.413
6.628
U
5.3.(4) Baja Tulangan untuk perkerasan Beton Kg 19,053.06 8.670 1.084 1.084 1.084 1.084 1.084 1.084 1.084 1.084 L
5.3.(5) Acuan untuk Perkerasan Beton M2 636.79 2.372 0.339 0.339 0.339 0.339 0.339 0.339 0.339

VII PEKERJAAN STRUKTUR


Tembok Penahan Tanah :
F
(P=100 m : T=-0.7 m) I
(P=618 m : T=-1 m)
3.1.(10) Galian Tanah Untuk TPT M3 264.70 0.499 0.166 0.166 0.166
T
7.9.(1) Pasangan Batu Untuk TPT M3 634.70 15.562 3.890 3.890 3.890 3.890 R
7.9.(2) Plesteran Untuk TPT
3.2.4 Timbunan Kembali Untuk TPT
M2
M3
308.40
175.50
0.589
0.162
0.196 0.196 0.196
0.081 0.081 I
JUMLAH 100.000
BOBOT RENCANA 0.063 0.355 0.355 1.366 1.075 1.559 1.631 1.631 10.527 10.599 10.693 14.584 14.780 14.686 14.782 1.315 - -
BOBOT RENCANA KOMULATIF 0.063 0.418 0.773 2.139 3.214 4.773 6.403 8.034 18.561 29.160 39.854 54.437 69.217 83.903 98.685 100.000 100.000 100.000
BOBOT REALISASI 0.040
BOBOT REALISASI KOMULATIF 0.040
DEVIASI -0.024

Serang, 31 Maret 2016


Pejabat Pelaksana Teknis Kegiatan Pelaksana Teknis Konsultan Pegawas Penyedia Jasa Konstruksi
BIDANG BINA MARGA DPU KAB. SERANG BIDANG BINA MARGA DPU KAB. SERANG CV. JAYA WAHANA RAYA PT. DUA PUTRI MANDIRI
H. M. RONNY N, ST, MM KANAFIYAH, ST ADI AMIRULLOH, ST AGUS DWI PUTRA, ST
NIP. 19751005 200312 1 007 NIP. 19770906 200801 1 003 SUPERVISION ENGINEER PROJECT MANAGER
Paket Pekerjaan : PENINGKATAN JALAN NAMBO - TERAS BENDUNG
Lokasi : KECAMATAN CIRUAS
Program : PEMBANGUNAN JALAN DAN JEMBATAN
JADWAL PELAKSANAAN
Kegiatan : PEMBANGUNAN JALAN

BULAN KE I BULAN KE II BULAN KE III BULAN KE IV BULAN KE V


NO JENIS PEKERJAAN SAT KUANT. BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 KET
24 Mar - 30 Mar 31 Mar - 6 Apr 7 Apr - 13 Apr 14 Apr - 20 Apr 21 Apr - 27 Apr 28 Apr - 4 Mei 5 Mei - 11 Mei 12 Mei - 18 Mei 19 Mei - 25 Mei 26 Mei - 1 Jun 2 Jun - 8 Jun 9 Jun - 15 Jun 16 Jun - 22 Jun 23 Jun - 29 Jun 30 Jun - 6 Jul 7 Jul - 13 Jul 14 Jul - 20 Jul 21-Jul

I PEKERJAAN UMUM
1.2 Mobilisasi Ls 1.00 0.663 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041
Pembuatan Papan Nama proyek
Pengujian Laboratorium
Direksikeet
Dokumentasi dan Rekaman Proyek
Pengukuran dan Pematokan
Mobilisasi dan Demobilisasi Alat
1.8.(1) Pemeliharaan & Perlindungan Lalu Lintas Ls 1.00 0.351 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022

III PEKERJAAN TANAH


3.1.(10) Galian Biasa untuk Oprit M3 6.00 0.011 0.006 0.006
3.1.(10)
3.4.6
Galian pada bahu (untuk pelebaran)
Pembersihan semak - semak
M3
M2
380.25
2,028.00
0.707
0.167
0.236
0.056
0.236
0.056
0.236
0.056 L
IV PELEB. PERKERASAN DAN BAHU JALAN
I
4.2.(1) Lapis Pondasi Agregat A M3 152.10 1.215 0.405 0.405 0.405 B
4.2.(2a)
4.2.(2d)
Lapis Pondasi Agregat B
Timbunan Bahu jalan (Agregat kelas B)
M3
M3
228.15
304.20
1.819
2.341
0.606 0.606 0.606
1.170 1.170
U
7.1.(4) Beton Oprit (beton Semen K-400) M3 3.00 0.116 0.058 0.058 R
7.1.(11) Acuan Untuk Beton M2 4.40 0.017 0.009 0.009

V
5.1.1
PERKERASAN BERBUTIR DAN BETON SEMEN
Perbaikan Lapis Pondasi Agregat Kelas A M3 110.93 0.880 0.293 0.293 0.293
I
5.1.2 Perbaikan Lapis Pondasi Agregat Kelas B M3 72.91 0.571 0.190 0.190 0.190 D
5.3.(3)
5.3.1
Lapis Pondasi Bawah Beton Kurus (K-125)
Perkerasan Beton Semen (K-400) P=1.014 M
M3
M3
527.28
1,014.00
16.892
46.396
2.413
6.628
2.413
6.628
2.413
6.628
2.413
6.628
2.413
6.628
2.413
6.628
2.413
6.628
U
5.3.(4) Baja Tulangan untuk perkerasan Beton Kg 19,053.06 8.670 1.084 1.084 1.084 1.084 1.084 1.084 1.084 1.084 L
5.3.(5) Acuan untuk Perkerasan Beton M2 608.40 2.372 0.339 0.339 0.339 0.339 0.339 0.339 0.339

VII PEKERJAAN STRUKTUR


Tembok Penahan Tanah :
F
(P=100 m : T=-0.7 m) I
(P=618 m : T=-1 m)
3.1.(10) Galian Tanah Untuk TPT M3 268.20 0.499 0.166 0.166 0.166
T
7.9.(1) Pasangan Batu Untuk TPT M3 639.60 15.562 3.890 3.890 3.890 3.890 R
7.9.(2) Plesteran Untuk TPT
3.2.4 Timbunan Kembali Untuk TPT
M2
M3
349.00
172.00
0.589
0.162
0.196 0.196 0.196
0.081 0.081 I
JUMLAH 100.000
BOBOT RENCANA 0.063 0.355 0.355 1.366 1.075 1.559 1.631 1.631 10.527 10.599 10.693 14.584 14.780 14.686 14.782 1.315 - -
BOBOT RENCANA KOMULATIF 0.063 0.418 0.773 2.139 3.214 4.773 6.403 8.034 18.561 29.160 39.854 54.437 69.217 83.903 98.685 100.000 100.000 100.000
BOBOT REALISASI 0.040 0.040
BOBOT REALISASI KOMULATIF 0.040 0.080
DEVIASI -0.024 -0.338

Serang, 7 April 2016


Pejabat Pelaksana Teknis Kegiatan Pelaksana Teknis Konsultan Pegawas Penyedia Jasa Konstruksi
BIDANG BINA MARGA DPU KAB. SERANG BIDANG BINA MARGA DPU KAB. SERANG CV. JAYA WAHANA RAYA PT. DUA PUTRI MANDIRI
H. M. RONNY N, ST, MM KANAFIYAH, ST ADI AMIRULLOH, ST AGUS DWI PUTRA, ST
NIP. 19751005 200312 1 007 NIP. 19770906 200801 1 003 SUPERVISION ENGINEER PROJECT MANAGER
Paket Pekerjaan : PENINGKATAN JALAN NAMBO - TERAS BENDUNG
Lokasi : KECAMATAN CIRUAS
Program : PEMBANGUNAN JALAN DAN JEMBATAN
JADWAL PELAKSANAAN
Kegiatan : PEMBANGUNAN JALAN

BULAN KE I BULAN KE II BULAN KE III BULAN KE IV BULAN KE V


NO JENIS PEKERJAAN SAT KUANT. BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 KET
24 Mar - 30 Mar 31 Mar - 6 Apr 7 Apr - 13 Apr 14 Apr - 20 Apr 21 Apr - 27 Apr 28 Apr - 4 Mei 5 Mei - 11 Mei 12 Mei - 18 Mei 19 Mei - 25 Mei 26 Mei - 1 Jun 2 Jun - 8 Jun 9 Jun - 15 Jun 16 Jun - 22 Jun 23 Jun - 29 Jun 30 Jun - 6 Jul 7 Jul - 13 Jul 14 Jul - 20 Jul 21-Jul

I PEKERJAAN UMUM
1.2 Mobilisasi Ls 1.00 0.663 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041
Pembuatan Papan Nama proyek
Pengujian Laboratorium
Direksikeet
Dokumentasi dan Rekaman Proyek
Pengukuran dan Pematokan
Mobilisasi dan Demobilisasi Alat
1.8.(1) Pemeliharaan & Perlindungan Lalu Lintas Ls 1.00 0.351 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022

III PEKERJAAN TANAH


3.1.(10) Galian Biasa untuk Oprit M3 6.00 0.011 0.006 0.006
3.1.(10)
3.4.6
Galian pada bahu (untuk pelebaran)
Pembersihan semak - semak
M3
M2
380.25
2,028.00
0.707
0.167
0.236
0.056
0.236
0.056
0.236
0.056 L
IV PELEB. PERKERASAN DAN BAHU JALAN
I
4.2.(1) Lapis Pondasi Agregat A M3 152.10 1.215 0.405 0.405 0.405 B
4.2.(2a)
4.2.(2d)
Lapis Pondasi Agregat B
Timbunan Bahu jalan (Agregat kelas B)
M3
M3
228.15
304.20
1.819
2.341
0.606 0.606 0.606
1.170 1.170
U
7.1.(4) Beton Oprit (beton Semen K-400) M3 3.00 0.116 0.058 0.058 R
7.1.(11) Acuan Untuk Beton M2 4.40 0.017 0.009 0.009

V
5.1.1
PERKERASAN BERBUTIR DAN BETON SEMEN
Perbaikan Lapis Pondasi Agregat Kelas A M3 110.93 0.880 0.293 0.293 0.293
I
5.1.2 Perbaikan Lapis Pondasi Agregat Kelas B M3 72.91 0.571 0.190 0.190 0.190 D
5.3.(3)
5.3.1
Lapis Pondasi Bawah Beton Kurus (K-125)
Perkerasan Beton Semen (K-400) P=1.014 M
M3
M3
527.28
1,014.00
16.892
46.396
2.413
6.628
2.413
6.628
2.413
6.628
2.413
6.628
2.413
6.628
2.413
6.628
2.413
6.628
U
5.3.(4) Baja Tulangan untuk perkerasan Beton Kg 19,053.06 8.670 1.084 1.084 1.084 1.084 1.084 1.084 1.084 1.084 L
5.3.(5) Acuan untuk Perkerasan Beton M2 608.40 2.372 0.339 0.339 0.339 0.339 0.339 0.339 0.339

VII PEKERJAAN STRUKTUR


Tembok Penahan Tanah :
F
(P=100 m : T=-0.7 m) I
(P=618 m : T=-1 m)
3.1.(10) Galian Tanah Untuk TPT M3 268.20 0.499 0.166 0.166 0.166
T
7.9.(1) Pasangan Batu Untuk TPT M3 639.60 15.562 3.890 3.890 3.890 3.890 R
7.9.(2) Plesteran Untuk TPT
3.2.4 Timbunan Kembali Untuk TPT
M2
M3
349.00
172.00
0.589
0.162
0.196 0.196 0.196
0.081 0.081 I
JUMLAH 100.000
BOBOT RENCANA 0.063 0.355 0.355 1.366 1.075 1.559 1.631 1.631 10.527 10.599 10.693 14.584 14.780 14.686 14.782 1.315 - -
BOBOT RENCANA KOMULATIF 0.063 0.418 0.773 2.139 3.214 4.773 6.403 8.034 18.561 29.160 39.854 54.437 69.217 83.903 98.685 100.000 100.000 100.000
BOBOT REALISASI 0.040 0.040 0.040
BOBOT REALISASI KOMULATIF 0.040 0.080 0.119
DEVIASI -0.024 -0.338 -0.653

Serang, 14 April 2016


Pejabat Pelaksana Teknis Kegiatan Pelaksana Teknis Konsultan Pegawas Penyedia Jasa Konstruksi
BIDANG BINA MARGA DPU KAB. SERANG BIDANG BINA MARGA DPU KAB. SERANG CV. JAYA WAHANA RAYA PT. DUA PUTRI MANDIRI
H. M. RONNY N, ST, MM KANAFIYAH, ST ADI AMIRULLOH, ST AGUS DWI PUTRA, ST
NIP. 19751005 200312 1 007 NIP. 19770906 200801 1 003 SUPERVISION ENGINEER PROJECT MANAGER
Paket Pekerjaan : PENINGKATAN JALAN NAMBO - TERAS BENDUNG
Lokasi : KECAMATAN CIRUAS
Program : PEMBANGUNAN JALAN DAN JEMBATAN
JADWAL PELAKSANAAN
Kegiatan : PEMBANGUNAN JALAN

BULAN KE I BULAN KE II BULAN KE III BULAN KE IV BULAN KE V


NO JENIS PEKERJAAN SAT KUANT. BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 KET
24 Mar - 30 Mar 31 Mar - 6 Apr 7 Apr - 13 Apr 14 Apr - 20 Apr 21 Apr - 27 Apr 28 Apr - 4 Mei 5 Mei - 11 Mei 12 Mei - 18 Mei 19 Mei - 25 Mei 26 Mei - 1 Jun 2 Jun - 8 Jun 9 Jun - 15 Jun 16 Jun - 22 Jun 23 Jun - 29 Jun 30 Jun - 6 Jul 7 Jul - 13 Jul 14 Jul - 20 Jul 21-Jul

I PEKERJAAN UMUM
1.2 Mobilisasi Ls 1.00 0.663 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041
Pembuatan Papan Nama proyek
Pengujian Laboratorium
Direksikeet
Dokumentasi dan Rekaman Proyek
Pengukuran dan Pematokan
Mobilisasi dan Demobilisasi Alat
1.8.(1) Pemeliharaan & Perlindungan Lalu Lintas Ls 1.00 0.351 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022

III PEKERJAAN TANAH


3.1.(10) Galian Biasa untuk Oprit M3 6.00 0.011 0.006 0.006
3.1.(10)
3.4.6
Galian pada bahu (untuk pelebaran)
Pembersihan semak - semak
M3
M2
380.25
2,028.00
0.707
0.167
0.236
0.056
0.236
0.056
0.236
0.056 L
IV PELEB. PERKERASAN DAN BAHU JALAN
I
4.2.(1) Lapis Pondasi Agregat A M3 152.10 1.215 0.405 0.405 0.405 B
4.2.(2a)
4.2.(2d)
Lapis Pondasi Agregat B
Timbunan Bahu jalan (Agregat kelas B)
M3
M3
228.15
304.20
1.819
2.341
0.606 0.606 0.606
1.170 1.170
U
7.1.(4) Beton Oprit (beton Semen K-400) M3 3.00 0.116 0.058 0.058 R
7.1.(11) Acuan Untuk Beton M2 4.40 0.017 0.009 0.009

V
5.1.1
PERKERASAN BERBUTIR DAN BETON SEMEN
Perbaikan Lapis Pondasi Agregat Kelas A M3 110.93 0.880 0.293 0.293 0.293
I
5.1.2 Perbaikan Lapis Pondasi Agregat Kelas B M3 72.91 0.571 0.190 0.190 0.190 D
5.3.(3)
5.3.1
Lapis Pondasi Bawah Beton Kurus (K-125)
Perkerasan Beton Semen (K-400) P=1.014 M
M3
M3
527.28
1,014.00
16.892
46.396
2.413
6.628
2.413
6.628
2.413
6.628
2.413
6.628
2.413
6.628
2.413
6.628
2.413
6.628
U
5.3.(4) Baja Tulangan untuk perkerasan Beton Kg 19,053.06 8.670 1.084 1.084 1.084 1.084 1.084 1.084 1.084 1.084 L
5.3.(5) Acuan untuk Perkerasan Beton M2 608.40 2.372 0.339 0.339 0.339 0.339 0.339 0.339 0.339

VII PEKERJAAN STRUKTUR


Tembok Penahan Tanah :
F
(P=100 m : T=-0.7 m) I
(P=618 m : T=-1 m)
3.1.(10) Galian Tanah Untuk TPT M3 268.20 0.499 0.166 0.166 0.166
T
7.9.(1) Pasangan Batu Untuk TPT M3 639.60 15.562 3.890 3.890 3.890 3.890 R
7.9.(2) Plesteran Untuk TPT
3.2.4 Timbunan Kembali Untuk TPT
M2
M3
349.00
172.00
0.589
0.162
0.196 0.196 0.196
0.081 0.081 I
JUMLAH 100.000
BOBOT RENCANA 0.063 0.355 0.355 1.366 1.075 1.559 1.631 1.631 10.527 10.599 10.693 14.584 14.780 14.686 14.782 1.315 - -
BOBOT RENCANA KOMULATIF 0.063 0.418 0.773 2.139 3.214 4.773 6.403 8.034 18.561 29.160 39.854 54.437 69.217 83.903 98.685 100.000 100.000 100.000
BOBOT REALISASI 0.040 0.040 0.040 0.163
BOBOT REALISASI KOMULATIF 0.040 0.080 0.119 0.283
DEVIASI -0.024 -0.338 -0.653 -1.856

Serang, 21 April 2016


Pejabat Pelaksana Teknis Kegiatan Pelaksana Teknis Konsultan Pegawas Penyedia Jasa Konstruksi
BIDANG BINA MARGA DPU KAB. SERANG BIDANG BINA MARGA DPU KAB. SERANG CV. JAYA WAHANA RAYA PT. DUA PUTRI MANDIRI
H. M. RONNY N, ST, MM KANAFIYAH, ST ADI AMIRULLOH, ST AGUS DWI PUTRA, ST
NIP. 19751005 200312 1 007 NIP. 19770906 200801 1 003 SUPERVISION ENGINEER PROJECT MANAGER