Anda di halaman 1dari 53

Bar and Bench (www.barandbench.

com)

IN THE HIGH COURT OF DELHI AT NEW DELHI

EXTRAORDINARY ORIGINAL WRIT JURISDICTION

WRIT PETITION (C) NO. OF 2018

IN THE MATTER OF:


Social Action For Forest and Environment.
Office: SAFE, T-16, Senior Citizen Housing Complex,
Sector- P3, Greater Noida, U.P.- 201308.

……Petitioner
VERSUS

Union of India
Through Secretary, Govt. of India
Ministry of Environment, Forest & Climate Change
Indira Paryavaran Bhavan, Jora Bagh Road,
New Delhi-110003
……Respondent

WRIT PETITION UNDER ARTICLE 226 OF THE


CONSTITUTION OF INDIA SEEKING ISSUANCE OF AN
APPROPRIATE WRIT IN THE NATURE OF CERTIORARI
QUASHING THE IMPUGNED NOTIFICATIONS DATED
14.11.2018 AND 15.11.2018 ISSUED BY THE
RESPONDENT (MOEF&CC); AND FURTHER SEEKING A
WRIT IN THE NATURE OF MANDAMUS DIRECTING
THE RESPONDENT TO FOLLOW THE LEGAL
FRAMEWORK UNDER THE EIA NOTIFICATION DATED
14.09.2006 IN BOTH LETTER AND SPIRIT.

TO,
THE HON’BLE CHIEF JUSTICE AND
HIS OTHER COMPANION JUSTICES OF THE
HON’BLE HIGH COURT OF DELHI:-

THE HUMBLE PETITION OF


THE PETITIONER ABOVE
NAMED
Bar and Bench (www.barandbench.com)

THE PETITIONER MOST RESPECTFULLY SHEWETH:-

1. The instant Writ Petition is being filed by the

Petitioner under Article 226/ 227 of the Constitution

of India for issuance ofan appropriate writ/ order(s)

in the nature of Certiorari quashing the impugned

Notifications dated 14.11.2018 and

15.11.2018(hereinafter referred to as ‘the Impugned

Notifications’) whereby the Respondents have

substantially amended the EIA Notification dated

14.9.2006 and excluded the necessity of obtaining

Environmental Clearance/ Enviromental Impact

Assessment/ Enviromental Management Plan for

building projects up to 50,000 sq.m. built up area

and 1,50,000 sq m in the case of industrial sheds,

hospitals etc, out of purview regulatory regime of EP

Act 1986, as against the current criteria of 20,000

sq.m. built-up area.

2. That the Impugned Notifications are grosslyillegal

and unsustainble, being in blatant contempt of the

Order dated 1.11.2018 passed by this Hon’ble Court

in W.P. (C) No. 11027/ 2018 wherein this Hon’ble

Court noted the contents of the draft Notification

dated 13.03.2018; recorded the apprehensions of the

Petitioner that the Respondent would overlook all

objections and issue the final notification; and


Bar and Bench (www.barandbench.com)

thereafter by a speaking Order (i.e. 1.11.2018)

granted liberty to the Petitioner to make a detailed

representation within a period of four weeks, and

directed the Respondent to take an informed

decision after considering the said representation.

It is submitted that the Respondent has

contemptuously and in wilful disobediance and

deliberate defiance of the said Order dated

1.11.2018 issued the Impugned Notifications, which

is not only in violation of the principles of natural

justice, but are also issued in an arbitrary and

unreasonable manner without any application of

mind and/or objective analysis regarding the serious

and deleterious ramifications that the Impugned

Notification would have on the environment and

ecology in the entire Country.

3. That the Impugned Notifications are Ultra Virus the

provisions of the Environment (Protection) Act, 1986,

Air Pollution Act, Water Pollution Act, in as much as,

the said Notifications,substantially and directly

dilute and relax the effects of the earlier EIA

notification dated 14.9.2006 whereby now projects

upto 50,000 sq.m. and 1,50,000 sqm in case of

industrial sheds, hospitals etc would not require

prior environmental clearance/ environmental


Bar and Bench (www.barandbench.com)

impact assessment study, which would directly and

adversely impact the environment and ecology of the

entire Country, thus contravening the provisions of

Article 21 and various judgments passed by the

Hon’ble Supreme Court.

4. It is submitted that the Impugned Notifications

issued by the Respondent are an abriged and inferior

version of the earlier Notification dated 9.12.2016

whereby Building and Construction projects upto

1,50,000 sq m were sought to be taken out of the

regulatory regime of EIA Notification dated

14.09.2006 and to be entrusted to non-expert/

technical local bodies. The Notification dated

9.12.2016 was quashed by the Principal Bench of

Hon’ble National Green Tribunal vide its Judgment

dated 08.12.2017 due to the following reasons:

(a) The Notification dated 9.12.2016 considerably

dilutes the entire enviromental assessment

framework under the EIA Notification, 2006

and is against the basic letter and spirit of the

EPA Act, 1986, Regulations thereof and various

judgments passed by Indian Courts.

(b) The dilution to the EIA Notification, 2006

would directly impede the Doctrine of Non-

Regressionwhich is internationally a well


Bar and Bench (www.barandbench.com)

accepted norm and is founded on the idea that

Enviromental laws should not be modified to

the deteriment of the Environment.

(c) The removal of the Enviromental Assessment

process would have a severe impact on

ecologically sensitive and vulnerable areas, and

would contravene the Precautionary Principle

as propounded by the Hon’ble Apex Court,

which is a cornerstone of environmental

jurisprudence in the Country.

(d) The power under Section 3 of the EPA Act are

to be exercised only to take measures to

protect and improve the quality of enviroment,

however such essential features are missing in

the notification issued.

(e) The proposal to exempt Enviromental

Clearance for constructions nad building

projects within built up area to 1,50,000 sq m

is baseless and bereft of any study that

indicated any improvement in enviromental

quality in this regard.

(f) The said Amendment is only a ploy to

circumvent the provisions of enviroment

assessment under the EIA Notification, 2006 in

the name of ‘ease of doing business’ and there


Bar and Bench (www.barandbench.com)

is no mechanism laid down under the

amendment notification for evaluation,

assessment or monitoring of the enviromental

impact of building and construction activity.

(g) The MOEF& CC has failed to produce any

study, literature, evaluation of the reasons for

taking such a retrgrade decision to go back to a

pre-2004 situation wherein the failure of local

bodies was considered to be the primary reason

for bringing building and construction activity

within the EIA framework. In pre-2004 the

position was that the construction sector

projects were only regulted through Bye-laws

and no Envriomental clearance was required.

(h) The very purpose of including construction

projects in the EIA Notification was the failure

of local bodies to ensure compliance with

enviromental norms. It was the case of the

MOEF& CC that local bodies while approving

new construction projects are not adhering to

enviromental norms. Now the MOEF is taking a

step in the backward direction without there

being any change brought about in the

capacity and technical competance of the local


Bar and Bench (www.barandbench.com)

body to assess, evaluate and monitor

enviromental norms or to ensure complaince.

(i) The EIA Notification, 2006 has a

comprehensive process for evaluating the

impact on enviroment, by providing for a

Expert Appriasal Committee at the Centre and

the State Expert Committee at the State Level

which consists of independent experts,

enviromental quality experts and sectoral

experts.

(j) The MOEF& CC has failed to fullfil its statutory

duties by trasnfering its power to local bodies

(Development auhtorities) thereby creating a

situation of conflict of interest as all powers are

vested in a particular authority. The CAG

Report, 2016 discourages sich integration of

enviromental conditions to the sactioning

auhtority under the urban local bodies instead

of independent assessment by enviromental

experts of buidling and construction projects.

The CAG Report, 2016 clearly states that

urban local bodies are not flloiwng

enviromental parametres.

(k) The said notification which excludes the

construction projects of built up area of more


Bar and Bench (www.barandbench.com)

than 20,000 sq m to 50,000 sq m, is contrary

to the recommendations of the Kasturirangan

Committee Constituted by the MOEF&CC on

11.12.2012 to review the provisions of the EIA

Notification. If the MOEF& CC is changing its

stand, it is duty bound to produce a back up

study or research material to prove that local

bodies have concern towards the environment.

5. That the Petitioner is an NGO working and

functioning for the improvement and betterment of

the environment as a whole, and has consistently

and sincerely worked towards strenghing and

protecting envriomental laws in the Country. The

Petitioner is represented through its auhtorized

representative Mr. Vikrant Tongad who is the

founder of the Petitioner NGO.

6. The Respondent, Ministry of Environment, & Forest

& Climate Change (MOEF&CC) is the nodal

ministry/ authority under the administration of the

Central Government that is responsible for the

management, regulations and monitoring of all

matters of Environment and pollution control under

the Union of India through various Acts passed by

the Parliament including the functions of the Central


Bar and Bench (www.barandbench.com)

Government under the Environment Protection Act,

1986.

7. The following Substantial Questions of Law qua the

impugned Notificationsarise for the consideration of

this Hon’ble Court in the instant Writ Petition.

(i) Whether the Respondent can exercise power

under Sec 3(1) of EP Act 1986 read with Rule 5

of EP Rules 1986 to issue any Notification of

non-restrictive and retrograde nature to relax

environmental regulations prescribed in the

EIA Notification dated 14.09.2006?

(ii) Whether Respondent has the power to issue a

Notification under Sec 3(1) of EP Act 1986 read

with Rule 5 of Environment Protection Rules,

thereby substantiallydiluting existing

enviromental norms/ laws without any study,

assessment or literature, bereft of any reason

and further impeding the priciple of non-

regression adopted in environmental matters?

(iii) Whether the Impugned Notifications

contravene the various principles/ Doctrines

recognized by Indian Courts in the field of

enviromental jurisprudence, namely,

Precautionary principle, Polluter Pay,


Bar and Bench (www.barandbench.com)

Intergenerational Equity, Public Trust,

Sustainable Development and the newly

accepted principle of Non-regression?

(iv) Whether the Impugned Notifications are an

abridged version of the earlier Notification

dated 9.12.2016 which was quashed by the

National Green Tribunal vide its Judgment

dated 8.12.2017?

(v) Whether the impugned Notification violates the

Precautionary Principle and the doctrine of

Sustainable Development, in as much as it

completely ignores several aspects of

environmental impacts including those during

construction phase for building and

construction projects of built-up area between

upto 50,000 sq.m. and 1,50,000 sq m in case

of Industrial sheds, hospitals etc, which was

expressely included at item 8(a) to the the

schedule of EIA Notification dated 14.09.2006.

requiring prior Environment Clearance.

(vi) Whether the impugned Notification is in

conflict with Principle 15 and 17 of Rio

Declaration of June 1992 to which Govt. of

India is a party/ signatory.


Bar and Bench (www.barandbench.com)

(vii) Whether the impugned notification is violative

of fundamental right of people for clean and

safe environment which is covered under right

to life under Article 21 of the Constitution of

India and further in contravention of Article 14

being unreasonable and arbitrary?

(viii) Whether the impugned Notifications are legally

sustainable, in as much as, the same have

been issued in gross contempt of the Order

dated 1.11.2018 passed by this Hon’ble Court?

8. It is submitted that for an effective and efficious

adjuication of the legality of the the Impugned

Notifications, it is imperative to place certain relevant

background facts that would show the complete

process and various Orders passed by the Hon’ble

Supreme Court in complaince of which the EIA

Notification, 2006 was issued, that is now sought to

be substantially diluted by the Impugned

Notifications in the context of building and

construction projects. The Petitioner further seeks to

place on record the obtinate and tenacious stand by

the Respondent (MOEF& CC) and their repeated

attempts to dilute the environmental norms by


Bar and Bench (www.barandbench.com)

amending the provisions of the EIA Notification,

2006.

BRIEF FACTS

8.1 After the catastrophe following the Bhopal Gas leak

tragedy in December 1984 and in furtherance of

India’s commitements being a signatory to Rio

Declaration of June, 1992, the Parliament in 1986

enacted a comprehensive legislation for

Enviromental Protection in India, namely the

Environment (Protection) Act, 1986 (hereinafter

referred to as the ‘the EPA Act, 1986’) with the object

and purpose to protect and improve the

Environment/ Ecology in the entire Country. The

EPA Act empowered the Central Government to

regulate all kinds of commercial and non-commercial

activities/ constructions/ and, all forms of Pollution

including soil, Water, Air and Noise pollution that

adversely affectthe Environment.

8.2 The Central Government in exercise of its Powers

under Section 3 of the Environment Protection Act

1986 read with Rule 5 of the Environment Protection

Rules, notified the Environment Impact Assessment

(EIA) Notification dated 27.01.1994,mandating the

requirement of obtaining prior Environmental

Clearance (EC) for select category of highly polluting


Bar and Bench (www.barandbench.com)

industries / activities with the purpose to ensure

sustainable development, minimizing the

environmental impacts of various development

activities such as mining projects, thermal power

plants, hydro-electric projects, etc. as listed in the

schedule of the Notification and thus fulfilling its

obligations under the Rio Declaration.

8.3 That on 07.06.2000, the Govt. of India through the

Ministry of Urban Development (MoUD) issued a

Notification regarding requirement of augmentation

of civic amenities before building sanctions are

issued in certain parts in NCT of Delhi.

84. While considering the large scale unauthorized

constructions in the NCT of Delhi in the face of acute

shortage of sewage treatment amenities in the New

Delhi, the Ld Solicitor General on 4.12.2001

submitted the following before the Hon’ble Supreme

Court in the matter of W.P. (C) No. 725/994 News

Item Hindustan Times A.Q.F.M. Yamuna v. Central

Pollution Control Board:

“that in relation to town planning the provisions of EP

Act would be applicable and whenever any decision is

taken in regard to town planning, environment impact


Bar and Bench (www.barandbench.com)

assessment must first be undertaken, clearance

obtained and then decision taken’.

Further the Hon’ble Supreme Court directed the

Respondent to consider amending the provisions of

the EPA Act so as to require an enviromental impact

assessment for the purposes of town planning.

8.5 The Responedent in compliance of the Order dated

4.12.2001 passed by the Hon’ble Supreme Court in

the above mentioned case, filed an affidavit taking

note of the seriousness of the pollution levels

interalia caused from building and construction

projects such as townships, hotels, hospitals,

industrial estates, offices etc, and the need to bring

them under the pruview of the Enviromental Impact

Assessment Notification, 1994.

A Copy of the Affidavit filed by the Respondent,

MOEF& CC in compliance of Order dated 4.12.2001

passed by the Hon’ble Supreme Court in W.P. (C) No.

725 of 1995 titled ‘News Item Hindustan Times

A.Q.F.M. Yamuna v. Central Pollution Control Board’

is enclosed herein and marked as Annexure 1 [at

pege_______to______].
Bar and Bench (www.barandbench.com)

8.6 That the Respondent, MOEF& CC in furtherance of

the aforesaid Affidavit filed before the Hon’ble

Supreme Court,issued a draft Notification dated

27.10.2003 by observing that the local authorities

have no concern for the environment, and thus

intended to bring construction projects within the

purview of the Enviromental Act, 1986 by mandating

a prior enviromental clearance for certain

commercial and non-commercial projects.

The preamble to the draft of EIA Notification dt. 27-

10-2003 by MOEF is as follows:

“And whereas, such projects have adverse impact on

environment including wetlands, lakes, rivers and

coastal waters posing serious health hazards to the

local population including children. Even for

construction of a house in a Panchayat area, plans

are approved only after the provision of a septic tank.

For an industrial project, an effluent treatment plant is

necessary and for an industrial estate a common

effluent treatment plant is necessary. On the other

hand, local bodies/development authorities in towns

have been approving new construction projects of

various categories and sizes without any concern for

the environment.”

(Emphasis is ours)
Bar and Bench (www.barandbench.com)

8.7 Subsequently, the Respondent in year 2004 issued a

Notification amending the EIA Notification, 1994, by

providing the mandatory requirement of obtaining

prior environment clearance for building

construction projects from Central Government.

8.8 That in September 2006, the prevalent EIA

Notification dated 14.09.2006 was issued by the

Respondent with an endeavour to interalia provide a

substantive legal framework and comprehensive

procedural mechanism for evalution, assessment

and monitoring of the Environmental impact on

builidng and construction activity throughout the

territory of India. The EIA Notification dated

14.09.2006 provided for the constitution of Central

and State level Environmental Impact Assessment

Authorities (SEIAA), manned by professionals, expert

and technical individuals that shall screen, scope

and appriase projects from an enviromental

prospective and further monitor the same from time

to time, in order to achieve the much desired goals of

sustainable development.

For the purposes of the present Petition, it is

necessary to state that the EIA Notification dated

14.09.2006 in the context of Buidling and


Bar and Bench (www.barandbench.com)

Construction Projects, provided for a mandatory and

prior Environment Elearance from the SEIAA for all

building construction projects of built-up area above

20,000 sq.m.

A true copy of the EIA Notification dated 14.09.2006

is enclosed herewith as Annexure - A-2 [page

no.__________to _______].

8.9 That the Respondent consituted a committee under

the Chairmanship of J.M. Mauskar, to examine

certain amendments to the EIA Notification dated

14.09.2006. It is submitted that with respect to the

proposal to ‘increase in threshhold limit from 20,000

sq m to 50,000 sq m and areas development projets

from 50 ha to 100 ha’, the J.M. Mauskar Committee

specially stated ‘Not Recommended. Status quo to be

maintained’based on the following reasoning:

“The limit of 20,000 sq m itself is a fairly large areas

in the Indian conditions and it almost amounts to 200

apartments in a composite apartment building and

the project population would be 1,000… Increasing

the threshold limits for building construction and

township and area developments projets would result

only in chaos as there is no examination of these from

their environmental impacts. In addition it is also to


Bar and Bench (www.barandbench.com)

be noted that even now many projects proponents

whose projects have build up area of more than

20,000 sq m, split their porject into 2 or 3 parts. (For

Eg. A 45,000 sq m project split into three 15,000 sq m

project) to avoid environmental appraisal.”

It is pertinent to submit that the Impugned

Notifications, have diluted the effects of the EIA

Notification dated 14.09.2006 by removing the need to

obtain prior environmental clearance for building and

construction projects upto 50,000 sq m (from 20,000

sq m), and thus made the exact same amendment

which was ‘Not recommended’ by its own Expert

Committee.

A true copy of the O.M. by the MoEF dated

11.11.2009 and Relevant extracts of the J.M.

Mauskar Committee Report are enclosed herewith as

Annexure A-3 (Colly) [page no.__________to _______].

8.10 That the Respondent, MOEF vide OM dated

11.12.2012 consituted a High Powered Committee of

eminent persons headed by Dr. K. Kasturirangan,

then member of Planning Commission in year 2012

to review the provisions of building construction

projects and issuance of mandatory prior

environment clearance. The said Committee which


Bar and Bench (www.barandbench.com)

consisted of members from the Ministry of Urban

Development (MOUD) and the Delhi Development

Authority (DDA) in its Comprehsenive Report dated

March, 2013 did not favour granting of environment

clearance by local bodies to construction projects

and the same was duly accepted by the Central

Govt. The said report rejected the view that

assessment by the Central and State Environment

Impact Assessment authorities and also local

bodies/ muncipal authorities under the Town &

Country Planning Acts resulted in duplication of

environmental clearances and was of the view that

even in the case of Building construction projects

located within area under a Master Plan, the project

require Environment Clearance under EIA

Notification since the Master plan take care of only

land use and no other items. Therefore for projects

falling within the jurisdiction of Master plan areas,

the current environmental regime needs to be

continued.

It is necessary to submit that the committee

identified 14 thrust areas which cannot be

addressed by the local body, and are required to be

focused during environment appraisal before grant

of environment clearance by competent authority


Bar and Bench (www.barandbench.com)

constituted by EIA Notification, 2006 which the

Respondent accepted and consequently issued O.M.

on 10.11.2015. It is further pertinent to mention

that as per the Dr. K. Kasturirangan Committee

Report, the Ministry of Urban Development (MoUD)

was not in agreement with the suggestion that

dispensing with the requirement of Environment

Clearance for big real estate projects under the

umbrella of approved Master Plan for Cities.

A true Copy of the Dr. K. Kasturingan Committee

Report dated March, 2013 is enclosed herewith as

Annexure A-4 [page no.__________to _______].

8.11 The Delhi Development Authority (DDA) functioning

under the administrative control of the Ministry of

Urban Development on22.03.2016 published a

Notification amending the Building Bye laws for NCT

of Delhi with the concurrence of Respondent. The

said Bye-laws dispensed with the mandatory

requirment of of procuring prior Environment

Clearance for all building construction projects of

built-up area up to 1,50,000 sq.m. under EIA

notification dated 14.09.2006 and in lieu thereof

prescribed creation of an Environmental Cell within

the local body to monitor compliance of pre

decided/prescribed environmental conditions in


Bar and Bench (www.barandbench.com)

Building Bye laws, and any other conditions that

could be prescribed by said Environmental Cell for

each individual project which could be prescribed in

the Building sanction under Local Laws by the

competent authority.

8.12 The Respondent thereafter published a draft

Notification dated 29.04.2016 similar to the

amendments incorporated in DDA’s Notification

dated 22.03.2016, to make such changes effective all

over the country.

8.13 The Respondent then issued a Notification dated

9.12.2016 whereby the comprehensive mechanism

provided under the EIA Notification dated

14.09.2006 was substantially diluted and relaxed by

virtue of an amendment. The said amendments

interalia dispensed with the mandatory prior

environment clearancerequired for building and

construction projects of built-up area up to 1,50,000

sq.m. as against an area of 20,000 as stipulated

under the original EIA Notification dated

14.09.2006. It is submitted that the 9.12.2016

notification provided for creation of Environmental

cells which processed environemental permissions in

a subjective manner, and further entrusted the task


Bar and Bench (www.barandbench.com)

to local bodies, thus revisiting the legal framework as

prevalent pre-2004.

A true copy of the Notification dated 09.12.2016

issued by MoEF is enclosed herewith as Annexure

A-5[page no.__________to _______].

8.14 Aggreived by the issuance of the Notification dated

9.12.2016and the DDA DDA Bye laws, 2016, various

persons, including the Petitioner, other NGOs, public

spirit persons challenged the same before the

Hon’ble National Green Tribunal (NGT/ Tribunal).

The Tribunal vide its detailed judgment dated

8.12.2017 considered and tested the dilution of

environment laws on the principle of non-regression,

precautionary principle, various judgments passed

by the Hon’ble Supreme Court, background under

which the EIA Notification dated 14.09.2006, lack of

any study/literature or reason etc, and

tehreafterquashed certain portions of the said

Notification dated 9.12.2016 whereby environement

cells were created under the control of local bodies

and were entrusted with the task of processing

permissions in a subjective manner.

A true copy of the judgment dated 08.12.2017

passed by the Hon’ble National Green Tribunal,


Bar and Bench (www.barandbench.com)

Principle Bench, Delhi in O.A. No. 677 of 2016 and

connected matters is enclosed herein as Annexure

A-6 [page no.__________to _______].

8.15 The Respondent being aggrieved by the Judgment

dated 8.12.2017 passed by the Hon’ble NGT, filed

Civil Appeal No. 2522 of 2018 before the Hon’ble

Supreme Court. The Hon’ble Supreme Court vide its

Order dated 23.03.2018 refused to stay the

Judgment dated 8.12.2017 and directed as under:

“It is agreed between the parties that there are

pending applications before the Environmental Cell

which may be forwarded to State Environment impact

Assessment Authority (SEICC) or the Ministry of

Environment, Forest and Climate Change, Indira

Parayavaran Bhawan, New Delhi, as the case may

be”.

A Copy of the Order dated 23.03.2018 passed by the

Hon’ble Supreme Court in Civil Appeal No. 2522 of

2018 is enclosed herein and marked as Annexure 7

[page_______to______].

8.16 In furthance of the Order dated 23.03.2018 passed

by the Hon’ble Supreme Court in Civil Appeal No.

2522 of 2018 , the Respondent issued O.M. dated


Bar and Bench (www.barandbench.com)

3.04.2018 implementing the said Order and stating

that all applications submitted before the

Environmental Cell shall be considered as per the

provisions of the EIA Notification dated 14.09.2006.

A Copy of the OM dated 3.04.2018 issued by the

Respondent is enclosed herein and marked as

Annexure 8 [at page_______to______].

8.17 The Respondent in exercise of its powers under

Section 3(2)(v) of the EPA Act, 1986 and Rule 5 of the

Environmental Protection Rules, on 13.03.2018

issued an together fresh draft Notification dated

13.03.2018, proposing toagain dilute by the

provisions of the EIA Notification, 2006 by excluding

all building construction projects of built-up area up

to 50,000 sq.m. from regulatory regime under the

said EIA Notification of 14.09.2006.

A Copy of the Draft EIA Notification dated

13.03.2018 issued by the Respondent is enclosed

herein and marked as Annexure 9[at

page_______to______].

8.18 The Respondent along with various other NGOs,

public spirit individuals submitted their respective

objections to draft Notification dated 13.03.2018.


Bar and Bench (www.barandbench.com)

8.19 Through an RTI reply, the Respondent had

acknowledged receipt of 1196 objections to the draft

Notification dated 13.03.2018. The Petitioner

through its wide network with NGOs, environmental

activists throughout the Country who have a

genuine, honestly and bonafide concern and love for

the Environment came to gain knowledge that more

than 2000 objections were filed against the draft

Notification dated 13.03.2018. Accordingly, the

Petitioner vide its letter dated 25.07.2018 and

17.08.2018 apprised the Respondent regarding the

incorrect RTI reply whereby 1196 objections were

stated to have been received against the draft

Notiification dated 13.03.2018 whereas in actuality

more than 2000 objections had been submitted and

the Petitioner could provide the reciepts of the said

objections.

A Copy of the letters dated 25.07.2018 and

17.08.2018 sent by the Petitioner to the Respondent

are enclosed herein and marked as Annexure

10(Colly) [at page_______to______].

8.20 That having not received any reply whatsoever from

the Respondent, MOEF& CC, on an apprehension

that the Respondent would overlook the objections

other than the 1196 stated to have been received


Bar and Bench (www.barandbench.com)

and issue the Final Notification, the Petitioner filed

W.P. (C) No. 11027/2018 before this Hon’ble Court.

8.21 This Hon’ble Court vide its Order dated 1.11.2018

duly considered the submissions made by the

Petitioner and the Respondent andgranted liberty to

the Petitioner to make a detailed representation

within a period of four weeks, and directed the

Respondent to consider the same while taking an

informed decision with regard to the draft

Notification.

A Copy of the Order dated 1.11.2018 passed by this

Hon’ble Court in W.P. (C) No. 11027 of 2018 in the

matter titled ‘Social Action for Forest& Environment v.

Union of India’ is enclosed herein and marked as

Annexure 11 [at page_______to______].

8.22 The Respondent, out of abundant caution,vide its

letter dated 2.11.2018 sent a copy of the aforesaid

Order dated 1.11.2018 passed by this Hon’ble Court

to the Respondent, MOEF&CC, which was duly

received by the Respondent on 5.11.2018.

A Copy of the Letter dated 2.11.2018 sent by the

Petitioner to the Respondent, MOEF& CC is enclosed

herein and marked as Annexure 12 [at

page_______to______].
Bar and Bench (www.barandbench.com)

8.23 That in complete dissonance of the Order dated

1.11.2018 passed by this Hon’ble Court, the

Respondent in a contemptuous, arbitrary and

unreasonable manner issued the Impugned

Notifications dated 14.11.2018 and 15.11.2018

whereby building and Construction projects upto

50,000 sq m and industrial sheds, hospital upto

1,50,000 sq m would not require an assessment,

evaluation and monitoring by the SEIAA, and would

now be dealt by the local bodies including municipal

authorites, panchayats etc.

It is submitted that the Impugned Notifications are a

gross abuse of the process of law being in direct

violation of an order passed by this Hon’ble Court

and against the principles of natural justice.

Furthermore, the Impugned Notification are ultra

virus the provisions of the EPA Act, 1986 and the

EIA Notification, 2006 and substantially and

seriously dilutes the existing environmental norms

applicable to building and construction projects by

re-visiting the pre-2004 situation wherein the

Respondent themselves constituted a Expert

Apprisal and Environmental Impact Asseseement

Authority which included various experts and

professionals, and stipulated a detailed Environment


Bar and Bench (www.barandbench.com)

Impact Assessment, Environmental Management

Plan and post clearance monitoring of such projects

from time to time.

8.24 It is submitted that the Respondent vide the

Impugned Notifications dated 14.11.2018 and

15.11.2018 has wrongly and unlawfully delegated its

powers under the EPA Act to local authorities,

district panchayats in respect of (a) building and

construction projects with build up area of 20,000-

50,000 sq m and (b) for a build up area of 20,000-

1,50,000 sq m in the case of Industrial sheds,

educational institutions, hospitals, hostels to

educational institutions;and further exempted

building and construction projects upto 50,000 sq m

(earlier 20,000 sq m) from requiring mandatory

Environmental clearance from the State

Environmental Impact Assessment Authority (SEIAA)

as per the EIA Notification dated 14.09.2006.

A Copy of the Impugned Notification dated

14.11.2018 issued by the Resondent, MOEF& CC is

enclosed herein and marked as Annexure 13 [at

page_______to______].

A Copy of the Impugned Notification dated

15.11.2018 issued by the Resondent, MOEF& CC is


Bar and Bench (www.barandbench.com)

enclosed herein and marked as Annexure 14 [at

page_______to______].

8.25 It is submitted that the Impugned Notifications dated

14.11.2018 apart from being legally unsustainable,

are in variance with the draft Notification dated

13.03.2018, inas much as, the criteria to delegate

powers to local authroities for a build up area of

20,000-1,50,000 sq m in the case of Industrial

sheds, educational institutions, hospitals, hostels to

educational institutions was never envisaged under

the draft Notification dated 13.03.2018 and is a

completely new dimension introduced by the

Impugned Notifications dated 14.11.2018 and

15.11.2018.

8.26 It is submitted that building and construction

projects are one of the principle contributors to Air

and water pollution. THe Respondent by taking a

retrograde step and diluting enviromental norms for

such building and construction projects would a

fortiori result in serious degradation to the

environment.Copies of the Report and Case Studies

by various credible Authorities indicating the impact

of Building and Construction activities on the

Enviroment and their contribution to Air and Water


Bar and Bench (www.barandbench.com)

Pollution are enclosed herein and marked as

Annexure 15 (Colly) [at pege_______to______].

GROUNDS

The Petitioner seeks relief as prayed for on the following

grounds on the basis of above mentioned facts, amongst

other:

A. Because the Impugned Notifications dated

14.11.2018 and 15.11.2018 suffer from serious

laxities and infirmities being Ultra Virus the

provisions of the Sec. 3(1) of EPA Act 1986 read with

Rule 5 of EP Rules 1986, whereby the said power

can only be exercised to take measures to protect

and improve the quality of enviroment, and not to

relax and dilute environmental regulations

prescribed in the EIA Notification dated 14.09.2006

which would seriously result in degradation of the

enviroment and ecology in the entire country.

B. Because the Impugned Notifications substantially

dilutes and relaxes the legal framework adopted

under the EIA Notification, 2006 with respect to

Building and Construction projects upto 50,000 sq

m and upto 1,50,000 sq m in the case of Industrial

sheds, educational institutions, hospitals, hostels to


Bar and Bench (www.barandbench.com)

educational institutions, by exempting the

requirment of prior environmental clearance and

comprehsive Environmental appraisal from from the

State Level Impact Assessment Authority (SEIAA)

constituted under Clause 3 of the EIA Notification,

2006. Resultantly, such a retrograde step would

have a disasterous and deleterious effect on the

environment and cause irrepariable damage to the

environment in the entire country.

C. Because the Respondent by issuing the Impugned

Notifications has wrongly and unlawfully exercised

power under Section 23 of the EPA Act and

delegated its powers under the EPA Act to local

authorities, district panchayats in respect of (a)

building and construction projects with build up

area of 20,000-50,000 sq m and (b) for a build up

area of 20,000-1,50,000 sq m in the case of

Industrial sheds, educational institutions, hospitals,

hostels to educational institutions; and further

exempts building and construction projects upto

50,000 sq m (earlier 20,000 sq m) from requiring

mandatory Environmental clearance from the State

Environmental Impact Assessment Authority (SEIAA)

and thus dilutingand relaxing the exiting legal

framework as per the EIA Notification dated


Bar and Bench (www.barandbench.com)

14.09.2006, that would a fortiori result in

degradation to the environment.

D. Because the Impugned Notification dated 14.11.2018

whereby the Respondent has delegated its powers to

the local body is in direct convention of the

provisions of the EIA Notification, 2006 which

specifically provide for a Central / State

Environmental Impact Assessment Authority and

lays down a comprehensive legal framework for

scoping, screen, appriasal and post clearance

monitoring of the projects above 20000 sq m. The

Respondent by exercise of power under Section 23

cannot amend the provisions of such legal

framework or override an authority created under

Section 3(3) of the EPA Act.

E. Because the removal of the Enviromental

Assessment process for building and construction

projects upto 50,000 sq m and 1,50,000 sq m in the

case of industrial sheds, hospitals etc would s would

have a severe, deleterious and adverse impact on

ecologically sensitive and vulnerable areas, and

would contravene various principles, namely, the

Precautionary Principle, Polluter Pay,

intergenerational equity and sustainable


Bar and Bench (www.barandbench.com)

development as propounded by the Hon’ble Apex

Court, which is a cornerstone of environmental

jurisprudence in the Country.

F. Because the Respondent has issued in the Impugned

Notifications in an unreasonable and comtempous

manner, in wilful disoberdiance and deliberate

defiance of the Order dated 1.11.2018 passed by this

Hon’ble Court in W.P. (C) No. 11027 of 2018.

G. Because the Respondent has issued in the Impugned

Notifications in violation of the Principles of natural

justice, without considering all the objections (more

than 2000) submitted qua the draft notification

dated 13.03.2018, and in complete dissonance of the

Order dated 1.11.2018 passed by this Hon’ble Court

in W.P. (C) No. 11027 of 2018 whereby the Petitioner

was granted liberty to send a detailed representation

to the draft notification dated 13.03.2018 within a

period of four weeks, and further the Respondent

was directed to consider the same while taking an

informed decision.

It is submitted that before the expiry of the period of

four weeks and before the Petitioner sent its detailed

representation, the Respondent has issued the

Impugned Notifications making further dilutions to


Bar and Bench (www.barandbench.com)

the EIA Notifications, 2006 than what was envisaged

even under the draft Notification dated 13.03.2018.

The Petitioner thus prays that on this ground alone

the present petitioner deserves to be allowed and the

impugned Notifications be quashed being in gross

violations of the principles of natural justice.

H. Because the Impugned Notifications considerably

dilutes the entire enviromental assessment

framework under the EIA Notification, 2006 and is

against the basic letter and spirit of the EPA Act,

1986, Regulations thereof, and further directly

impledes the Doctrine of Non-Regression which is

internationally a well accepted norm and is founded

on the idea that Enviromental laws should not be

modified to the deteriment of the Environment.

I. Because the Impugned Notifications are issued by

the Respondent without conducting any study,

literature, evaluation of the reasons for taking such a

backward and retrograde decision to go back to a

pre-2004 situation wherein the failure of local bodies

was considered to be the primary reason for bringing

building and construction activity within the EIA

framework. It is submitted that the Impugned

Notifications have amended the EIA Notification


Bar and Bench (www.barandbench.com)

dated 2006 which are notified on the directions

passed by the Hon’ble Supreme Court in W.P. (C) No.

725/994 in the matter titled News Item Hindustan

Times A.Q.F.M. Yamuna v. Central Pollution Control

Board.

J. Because the Impugned Notifications has no nexus to

the object that is sought to be achieved i.e.

environmental protections and is only a ploy to

circumvent the provisions of enviroment assessment

under the EIA Notification, 2006 for the benefit of

Builders as there is no mechanism laid down under

the Impugned notification for evaluation, assessment

or monitoring of the enviromental impact of building

and construction activity and only a subjective and

tick mark exercise by local bodies, municipal

authorities, district authorities etc.

K. Because the Respondent has failed to consider that

the very purpose of including construction projects

in the EIA Notification, 2006 was the failure of local

bodies to ensure compliance with enviromental

norms. It was previously the case of the MOEF& CC

itself that local bodies while approving new

construction projects are not adhering to

enviromental norms and thus the vide EIA


Bar and Bench (www.barandbench.com)

Notification, 2006 it constituted the SEICC with an

intention to provide a complete legal framework for

through assessement, evalutation and monitoring of

building and construction projects above 20000 sq

m.

Now the Respondent MOEF is taking a step in the

backward direction bereft of any change brought

about in the capacity and technical competance of

the local body to assess, evaluate and monitor

enviromental norms or to ensure complaince.

L. Because the Respondent has issued the Impugned

Notification in an arbitrary and unreasonable

manner, without application of mind or any objective

study whatseover. Infact the said Impugned

Notifications are directly contrary to the Report of

the J.M. Mauskar Committee constituted by the

Respondent, MOEF which specifically rejected the

very same amendment which is made to the EIA

Notification, 2006 by virtue of the Impugned

Notifications. It is submitted that with respect to the

proposal to ‘increase in threhold limit from 20,000 sq

m to 50,000 sq m and areas development projets from

50 ha to 100 ha’, the J.M. Mauskar Committee


Bar and Bench (www.barandbench.com)

specially stated ‘Not Recommended. Status quo to be

maintained’ and further stated as under:

“The limit of 20,000 sq m itself is a fairly large areas

in the Indian conditions and it almost amounts to 200

apartments in a composite apartment building and the

project population would be 1,000… Increasing the

threshold limits for building construction and

township and area developments projets would result

only in chaos as there is no examination of these from

their environmental impacts. In addition it is also to be

noted that even now many projects proponents whose

projects have build up area of more than 20,000 sq m,

split their porject into 2 or 3 parts. (For Eg. A 45,000

sq m project split into three 15,000 sq m project) to

avoid environmental appraisal.”

M. Because the Respondent has failed to appreciate that

the Impugned Notifications dated 14.11.2018 and

15.11.2018 are also in complete disregard to the

recommendation of the High Power Committee

constituted by the Respondent, MOEF& CC under

the chairmanship of Dr. K. Kasturirangan, then

member of Planning Commission in year 2012 and

other eniment persons to review the provisions of

building construction projects and issuance of


Bar and Bench (www.barandbench.com)

mandatory prior environment clearance. The said

Committee which consisted of members from the

Ministry of Urban Development (MOUD) and the

Delhi Development Authority (DDA) in its

Comprehensive Report dated March, 2013 did not

favour granting of environment clearance by local

bodies to construction projects and the same was

duly accepted by the Central Govt. The said report

rejected the view that assessment by the Central and

State Environment Impact Assessment authorities

and also local bodies/ muncipal authorities under

the Town & Country Planning Acts resulted in

duplication of environmental clearances and was of

the view that even in the case of Building

construction projects located within area under a

Master Plan, the project require Environment

Clearance under EIA Notification since the Master

plan take care of only land use and no other items

and therefore for projects falling within the

jurisdiction of Master plan areas, the current

environmental regime needs to be continued.

N. Because the Respondent, MOEF& CC has failed to

produce the Report of any subsequent Committee or

any other credible scientific study recommeding the

amendments to the EIA Notifications, 2006, made by


Bar and Bench (www.barandbench.com)

virtue of the issuance of the Impugned Notifications

and the same is grossly an unreasonable and

arbitrary exercise of power and thus falls foul of the

test of reasonableness propounded under Article 14

of the Constitution of India.

O. Because exclusion of built up area of 20000 sq m

itself is very huge and includes about 200

apartments. Thus relaxing the norm from 20000 sq

m to 50000 sq m would exclude the jurisdiction of

the SEIAA and exempt the requirement of proper

evaluation, assessment and monitoring of projects of

500 apartments which would obviously have an

adverse and serious impact on the environment in

the entire country.

P. Because the EIA Notification, 2006 has a

comprehensive process for evaluating the impact on

enviroment, by providing for a Expert Appriasal

Committee at the Centre and the State Expert

Committee at the State Level which consists of

independent experts, enviromental quality experts

and sectoral experts prescibed as per Annexure VI of

the EIA Notification, 2006. As per the Impugned

Notifications the same local body which is

responsible for stipulation of the condition would be

responsible for ensuring compliance of the same


Bar and Bench (www.barandbench.com)

which would contravene the principle of nemo judex

in sua causa, which is a principle of natural justice,

meaning that a person cannot be a judge of his own

cause. Also there is no technical expertise or

competance within the local bodies to either evaluate

impact or to ensure complaince of enviromental

conditions. It is trite to mention that the aspect of

monitoring of building projects dealt with in

impugned Notification requiring monitoring and thus

ensuring complaince with the provisions of the EPA

Act and Rules have been completed deleted.

Q. Because the Respondent MOEF& CC has failed to

fullfil its statutory duties by transfering its power to

local bodies (Development authorities) thereby

creating a situation of conflict of interest as all

powers are vested in a particular authority. The

Respondent failed to consider the CAG Report, 2016

which discourages such integration of enviromental

conditions to the sanctioning authority under the

urban local bodies instead of independent

assessment by enviromental experts of building and

construction projects. The CAG Report, 2016 clearly

states that urban local bodies are not following

enviromental parametres.
Bar and Bench (www.barandbench.com)

R. Because the present Notification would a

fortioriresult in a substantial, serious and direct

degradation of the environment which would not

only violate the fundamental rights of citizens under

Article 21 of the Constitution of India but would also

contravene various judgments passed by the Hon’ble

Supreme Court and this Hon’ble Court that have

recommended for more stringent laws protecting the

environment and check the depletion of nature

resources.

S. Because the impugned Notifications issued by the

Respondent are in conflict with Principle 15 and 17

of Rio Declaration of June 1992 to which Govt. of

India is a party/ signatory.The same are extracted

below for the ready reference and perusal of this

Hon’ble Court:

Principle 15:

In order to protect the environment, the precautionary

approach shall be widely applied by States according

to their capabilities. Where there are threats of

serious or irreversible damage, lack of full scientific

certainty shall not be used as a reason for postponing

cost-effective measures to prevent environmental

degradation,
Bar and Bench (www.barandbench.com)

Principle 17

Environmental impact assessment, as a national

instrument, shall be undertaken for proposed

activities that are likely to have a significant adverse

impact on the environment and are subject to a

decision of a competent national authority.

T. Because impugned notifications violates

fundamental right of members of the Petitioner and

the public at large, for clean and safe environment

which is covered under right to life under Art 21 of

the Constitution of India.

U. Because studies show that building and

construction projects are responsible for 40% of the

energy use, 30% of the raw material use, 20% of

water use and 20% of land use. They cause 40% of

carbon emissions, 30% of the solid waste generation

and 20% of water effluents and that the building and

construction sector is a major contributor to the

water pollution (sewage generation), air pollution

(DG sets emissions and construction dust),

challenges on solid waste management (construction

waste and municipal solid waste), flooding due to

rampant building construction projects on city sinks


Bar and Bench (www.barandbench.com)

(marshy lands and wet lands) & reclamation and

choking of city drains.

V. Because the Impugned Notifications are nothing but

an abridged version of the earlier Notification dated

9.12.2016 that was quashed by the Hon’ble Green

Tribunal vide its Judgment dated 8.12.2017. it is

submitted that the Respondent, MOEF has by

issuing the Imougned Notification reiterated the

amendments already quashed by the Hon’ble

Tribunal, without any change of circumstance or

reasonable exercise and objective study.

W. Because the environmental concerns like ground

water depletion, environmental pollution during

construction phase of construction projects, impact

on traffic volume and pattern change due to the

project and impact of change in environmental

conditions and its impact on environmental

assimilative/carrying capacity of NCT of Delhi in line

with notified national standards under EP Rules and

impact on other habitants and surrounding of such

project etc. have been totally ignored in the

Impugned Notifications.

X. Because the Respondent has failed to consider

various studies conducted by itself as well as by


Bar and Bench (www.barandbench.com)

individual experts whereby on a scientific analysis it

has been concluded that building and construction

projects cause more than 50% of air and water

pollution and relaxing the environment norms for

the same would invariably result in environmentally

unsound and unsustainable development of

construction projects which Govt. of India already

had accepted as having serious & potential

environmental impact requiring examination for all

building construction projects of built-up area

between 20,000 sq.m. to 50,000 sq.m.

Y. Because the manner in which the Impugned

Notificationsdiluting the requirment of prior

environmental clearance from the SEIAA has been

repeated issued by the Respondent i.e. despite

similar amendments being quashed by the Hon’ble

NGT and also in direct contravention of Order dated

1.11.2018 passed by this Hon’ble Court, prima facie

shows that the said amendments are made with an

malafide motive and ulterior objective to cater to

builders who are the only possible beneficiaries of

the dilution of the EIA Notification, 2006, at the cost

of the environment.
Bar and Bench (www.barandbench.com)

9. That this Hon’ble Court has the territorial

jurisdiction to entertain the present Petition, since

the Respondent is situated within the jurisdiction of

this Hon’ble Court and further the cause of action

has arisen before this Hon’ble Court. Furthermore,

this Hon’ble Court vide its Order dated 1.11.2018

passed in W.P. (C) No. 11027 of 2018 granted liberty

to the Petitioner to avail such remedies available in

law if aggrieved by the final notification issued in

furtherance of the draft Notification dated

13.03.2018.

10 That the Petitioner has filed the present petition

interalia on the grounds of violation of the principles

of natural justice; lack of jurisidiction of the

Respondent in issuing the Impugned Notification

under Section 3 of the EPA Act and the same being

ultra virus thereof; and further on the basis of an

unreasonable and arbitrary exercise of power by the

Respondent whereby environmental norms have

been diluted and relaxed in a contemptuous and

abstruse manner despite the Order dated 1.11.2018

passed by this Hon’ble Court in W.P. (C) No. 11027

of 2018, the judgment passed by the Hon’ble NGT

dated 8.12.2018, and without any application of

mind, apropos without any supporting


Bar and Bench (www.barandbench.com)

comprehensive study, literate or credible scientific

study/ data whatsoever and lastly, in direct

contravention of its own Hgih Powered Expert

Committees.

11. That the Petitioner herein has not filed any other

Petition before any other Court of law including the

Hon’ble Supreme Court or the National Green

Tribunal seeking the relief as sought before this

Hon’ble Court or any other relief with respect to the

Impugned Notifications dated 14.11.2018 and

15.11.2018.

PRAYER

In view of the facts and circumstances arrayed above, the


the Petitioner most respectfully prays that this Hon’ble
Court may graciously be pleased to pass the following
order(s):

a) Issue an appropriate Writ in the nature of Certiorari


quashing the Impugned Notifications dated
14.11.2018 and 15.11.2018 being violative of Article
14 and 21 of the Constitution of India and further
Ultra Virus the provisions of the EPA Act, 1986 and
the EIA Notification dated 14.09.2006; and

b) Issue an appropriate Writ in the nature of Certiorari


quashing the Impugned Notifications dated
14.11.2018 and 15.11.2018 being violative of the
principle of Non-regression, sustainable development
and precautionary principle;and
Bar and Bench (www.barandbench.com)

c) Issue an appropriate Writ in the nature of


Mandamus directing the Respondent to follow the
principle of Non-regression in both letter and spirit
and not to dilute or relax environmental norms
without any reasonable basis; and

d) Pass such other orders/ directions as deemed fit in


the facts and circumstances of the case.

Filed by
Dated: 20.11.2018
Place: New Delhi

(VANSHDEEP DALMIA & I.K. KAPILA)


Advocates for the Petitioners
206, Jor Bagh, New Delhi-110003
M. No. 9810077085
Enrl No. D/1376/2009
vanshdeepdalmia@gmail.com
Bar and Bench (www.barandbench.com)

IN THE HIGH COURT OF DELHI AT NEW DELHI

EXTRAORDINARY ORIGINAL WRIT JURISDICTION

C.M.A. NO. OF 2018


IN
WRIT PETITION (C) NO. OF 2018

IN THE MATTER OF:-


Social Action for Forest and Environment …..Petitioner

Versus

Union of India through Secretary, Govt. of India


Ministry of Environment, Forest & Climate Change
…..Respondent

APPLICATION FOR STAYUNDER SECTION 151 OF CPC,


1908

To,
THE HON’BLE CHIEF JUSTICE AND HIS OTHER
COMPANION JUSTICES OF THE HON’BLE HIGH COURT
OF DELHI AT NEW DELHI

THE HUMBLE PETITION OF THE PETITIONER ABOVE

NAMED

MOST RESPECTFULLY SHEWETH:-

1. The instant Writ Petition is being filed by the

Petitioner under Article 226/ 227 of the

Constitution of India for issuance of an

appropriate writ/ order(s) in the nature of


Bar and Bench (www.barandbench.com)

Certiorari quashing the impugned Notifications

dated 14.11.2018 and 15.11.2018 (hereinafter

referred to as ‘the Impugned Notifications’)

whereby the Respondents have substantially

amended the EIA Notification dated 14.9.2006

and excluded the necessity of obtaining

Environmental Clearance/ Enviromental Impact

Assessment/ Enviromental Management Plan for

building projects up to 50,000 sq.m. built up

area and 1,50,000 sq m in the case of industrial

sheds, hospitals etc, out of purview regulatory

regime of EP Act 1986, as against the current

criteria of 20,000 sq.m. built-up area.

2. That the Impugned Notifications are grossly

illegal and unsustainble, being in blatant

contempt of the Order dated 1.11.2018 passed

by this Hon’ble Court in W.P. (C) No. 11027/

2018 wherein this Hon’ble Court noted the

contents of the draft Notification dated

13.03.2018; recorded the apprehensions of the

Petitioner that the Respondent would overlook all

objections and issue the final notification; and

thereafter by a speaking Order (i.e. 1.11.2018)


Bar and Bench (www.barandbench.com)

granted liberty to the Petitioner to make a

detailed representation within a period of four

weeks and directed the Respondent to take an

informed decision after considering the said

representation. It is submitted that the

Respondent has contemptuously and in wilful

disobediance and deliberate defiance of the said

Order dated 1.11.2018 issued the Impugned

Notifications, which is not only in violation of the

principles of natural justice, but are also issued

in an arbitrary and unreasonable manner

without any application of mind and/or objective

analysis regarding the serious and deleterious

effects of the said Notifications on the

environment and ecology in the entire Country.

3. That the Impugned Notifications are Ultra Virus

the provisions of the Environment (Protection)

Act, 1986, Air Pollution Act, Water Pollution Act,

in as much as the said notifications,

substantially and directly dilute and relax the

effects of the earlier EIA notification dated

14.9.2006 whereby now projects upto 50,000

sq.m. would not require prior environmental


Bar and Bench (www.barandbench.com)

clearance/ environmental impact assessment

study, which would directly and adversely

impact the environment and ecology of the entire

Country, thus contravening the provisions of

Article 21 and various judgments passed by the

Hon’ble Supreme Court.

4. It is submitted that the Impugned Notifications

issued by the Respondent are an abriged and

inferior version of the earlier Notification dated

9.12.2016 which was quashed by the Hon’ble

NGT vide its Judgment dated 8.12.2017,

whereby Building and Construction projects

upto 1,50,000 sq m were sought to be taken out

of the regulatory regime of EIA Notification dated

14.09.2006.

5. That the Impugned Notification in effect provides

for applications seeking permission for building

and construction project upto 50,000 sq m and

1,50,000 sq m in the case of industrial sheds,

hospitals etc to be processed by local bodies

such as muncipalities, development authorities

and Disctrict Panchayats. It is submitted that

there are more than 5000 local bodies in the


Bar and Bench (www.barandbench.com)

country, that shall receive and process such

applications which would result in degradation

and irrepairable injury to the environment

throught the Country apart from creation of

third party rights if not stayed with immediate

affect.

6. That the present application is being made

bonafide, and in the interest of environment as a

whole.

7. That great prejudice will be caused to the

Petitioner and the people of India, incase the

instant application is not allowed.

PRAYER

In these circumstances it is therefore most

respectfully prayed to this Hon’ble Court that:-

a) Stay the operations of the Impugned Notification


dated 14.11.2018 (SO. 5733 E) and
15.11.2018Restrain the Respondent from
15.11.2018 (SO. 5736 E) during the pendency of
the present proceedings; and

b) Direct the Respondent that all buidling and


construction projects covered under item 8(a)
and (b) of the Schedule to the EIA Notification,
Bar and Bench (www.barandbench.com)

2006 shall be continued to be dealt by the


respective SEIXX/ SEAC in different states as
per the extant provisions contained in the EIA
Notification dted 14.09.2006; and

c) Direct the Respondent to deal with all


applications made in consonane with the
Impugned Notifications and pending before the
local bodies, in the manner prescribed under the
EIA Notification dated 14.09.2018; and \

d) Pass any such order or orders deemed fit in the

interest of justice and fair play.

AND FOR THIS ACT OF KINDNESS, THE PETITIONER


AS IN DUTY BOUND SHALL EVER PRAY.

Filed by
Dated: 20.11.2018
Place: New Delhi

(VANSHDEEP DALMIA & I.K. KAPILA )


Advocates for the Petitioners
206, Jor Bagh, New Delhi-110003
M. No. 9810077085
Enrl No. D/1376/2009
vanshdeepdalmia@gmail.com

Anda mungkin juga menyukai