Anda di halaman 1dari 4

Shaft Sinking And Underground Development At T

Kermac Potash Mine

JACK M. SWALES

ermac Potash Co., the newest American entry in


K a rapidly expanding industry, has come on the
scene with notable variations in conventional shaft-
sinking and mining techniques. Located in the famed
potash producing district east of Carlsbad, N. Mex.,
Kermac started up its mine in November, 1965, to
supply ore to the company's 500,000-tpy potash
crystallization refinery. In so doing, the company (1)
drilled the first large diameter mine shaft in the
potash industry and (2) has employed new continu-
ous miners especially adapted for use in thin potash
beds.
REACHING THE ORE ZONE
In its initial mine planning, Kermac, a partnership
owned jointly by Kerr-McGee Corp. and the Na-
tional Farmers Union Development Corp., considered
it imperative that the shafts be sunk and equipped
as soon as possible and that the mine be developed
sufficiently to insure a constant ore feed to the mill
when the unit was placed on stream. After examin-
At Kermac's new ing the alternative sinking techniques available to
potash mine, it, the company decided to accept a proposal by
(I steel liner u:hich
Big Hole Drillers, Inc., to drill the shaft from the
served as both
a structural
surface through various formations of sandstones,
component and a siltstone, shales, anhydrite, limestones, dolomite and
form for placing salts to the potash ore zone.
neat cement Within two months of this decision, preparations
was installed in for drilling were underway. A standard oil field
the first 935 ft
of the shaft, rotary drilling rig modified for large diameter hole
represented here drilling was moved on to the site; a heavy 42-in.-
b y a columnar O.D. drill collar was designed; 2500 ft of 133Js-in.-
section. O.D. drill pipe equipped with special threaded tool
joints were ordered; and all pumps and engines were
assembled.

J. M. SWALES, member of SME, i s Mine Superintendent of


Kermac Potash Co., Hobbs, N. Mex. The author presented this paper
a t the recent SME Fall Meeting in Tampa, Fla.

DECEMBER 1966, MINING ENGINEERING49


the test during the drilling of this particular portion
of the shaft. One of these problems was the vibration
of the drill string which was severe enough to twist
it off just above the drill collar. Subsequently, the
bit dropped to the bottom of the hole and 27 hours
were required to "fish" it out. The vibration problem
was overcome by designing, constructing and instal-
ling a 122-in. stabilizer above the bit so that it (the
stabilizer) would ride against the shaft walls and
dampen vibration. Other problems were caused by
the various formations: the siltstones drilled easily,
but were abrasive and required extra trips for re-
placement of bit cutters; the shales had a tendency
to ball up on the cutting surfaces of the bit; the
anhydrites were tough and caused a continuous
rough rotation and bounce of the bit. Penetration
rates of the 124-in. hole varied from a maximum of
3 ft per hour in the sandstone to a minimum of 6 in.
per hour in the toughest of the anhydrite. Over-all
The 48-in. hole drilled at the Kermuc mine was expanded
tuitlz this 124-in. bit, shown with the rotary table and drill penetration rate averaged 0.94 ft per hour for this
stern to the right. particular phase of drilling.
The next phase of the operation was the lining of
The completed shaft was drilled to a total depth the first 935 f t of shaft. A steel liner was designed to
of 1650 ft with a finished inside diameter of 8% ft. serve as a combination structural component of the
The entire job, from rigging up to tearing down, was shaft and a practical form for placing the neat ce-
accomplished in 173 days, the time broken down as ment. This cement was preferred to concrete because
follows: of the ease with which it could be pumped into place.
The liner was constructed of Y4-in. steel externally
Laying gas lines, levelling location and stiffened with 3 x 3 in, rolled angle irons and fabri-
rigging up 14 days cated in 40-ft sections. The average weight of a sec-
Drilling 48-in. pilot hole 935 ft to salt 33 days tion was 20,000 lb. To facilitate alignment and
Reaming this 48-in. hole to 124 in. diam 70 days welding, a slip joint collar was installed at the top
Installing casing and cementing annulus 12 days of each joint. To prevent contact of the external
Drilling 48-in. hole to shaft bottom 17 days stiffening rings with the wall of the hole and to
Reaming 48-in. hole to 102 in. 23 days provide a carrier for the concreting pipes, six verti-
Tear down 4 days cal runs of perforated 4%-in.-O.D. pipe were welded
Using a fresh water mud gel, the drilling of the symmetrically to the outside of the stiffener rings.
48-in. pilot hole to the top of the salt progressed The sections were then hoisted into the mast, low-
generally as planned. Since it was necessary that ered into the slip joint and welded at the collar by a
this pilot hole be as near vertical as possible, an four-man team using a predetermined welding se-
instrument, specially designed and built by the quence.
Sperry Sun Company, was used to make frequent Following positioning of the liner, the hole was
measurements of deviation during the drilling oper- bailed dry and preparations made to cement the
ations. annulus from the bottom to the surface.
To minimize deviation, the contractor used some-
what lighter than normal bit weights which reduced
penetration rates to some extent. Even under these
conditions, the over-all penetration rate for the 48-
in. hole was 1.87 ft per hour. The total deviation to
the 935-ft depth was 14 in. in a northwesterly di-
rection.
The 48-in. bit was then exchanged for a specially
designed bit to expand the diameter of the hole to
124 in. Again a fresh water mud gel was used to a
depth of 650 ft (the top of the gypsum and anhydrite
section). At this point, the mud was converted to a
brine-water starch mud to prevent dissolution of
the salt section to be drilled below. This conversion
required approximately 590 tons of salt. While the
cost and maintenance of this mud system was one of
the major expense factors in the job, it proved
worthwhile in that there was no extensive deteriora-
tion in the shaft walls.
Because of unexpected difficulties, the experience The Goodman 306 boring machine at the Kermac potash
and engineering ability of the contractor was put to mine accepts 4160 volts c~ndallows for low headroom.

70-MINING ENGINEERING, DECEMBER 1966 SOCIETY OF


A salt saturated cement plug was first placed i n are enclosed in a concrete T-shaped headframe. The
the bottom of the hole and allowed to equalize equipment deck of this headframe has been pres-
around the liner in the annulus. This formed a seal surized to keep out dust; a bridge crane, installed in
to contain the rising cement and prevented the ce- the building and capable of lifting from ground level,
ment from equalizing around and into the inside of was invaluable during the erection of the hoist, and
the liner. After the cement plug set, cementing oper- can be used in the future for change-out of heavy
ations were continuous until completion. A total of pieces of equipment; a two-man electric elevator has
23,554 cu ft of cement slurry was used in this opera- permitted easy access for inspection of the equip-
tion. During the cement placement, the inside of the ment in the headframe. The electrical control equip-
liner was simultaneously filled with mud to offset ment for both hoists is enclosed in a pressurized
the hydrostatic load imposed by the rising cement building immediately adjacent to the hoist house
column. and located so that one man can control both hoists.
Prewarations were made to resume drilling - while
the cement was setting. The 124-in. bit and the 122-
in. stabilizer were easily modified to 102 in. and
101 in. respectively.
In drilling below the casing, it was necessary to
make a decision between two possible methods of
penetrating the carnallite (KC1.MgC1;6H20) de-
posits at approximately 980 ft. The two alternatives
were: (1) to saturate the drilling brine with mag-
nesium at a cost of approximately $250,000; or, ( 2 )
attempt removal of cuttings by air. The contractor
had had past experience with air drilling and this
method was selected and a system designed whereby
air could be blown into the annulus of the hole and
cuttings returned to the surface through the hollow
drill steel. This method proved to be extremely
successful in that hole enlargement was effectively
controlled and penetration rates were accelerated.
The drilled shaft. now known as the "Man and
Materials" shaft, is equipped with a single drum The Man and Material. shaft and hoisthouse at Kemac's new
Nordberg hoist. It is interesting to note that the potash mine.
schedule called for certain work to be done in the
previously sunk production shaft while the Man and
Materials shaft was being drilled. The production MINE PLAN
hoist, already ordered, would not be delivered for At the start of the mine development, it was real-
10 months, and before this the company wanted to ized that an entirely new approach would be re-
erect the permanent headframe, equip the shaft with quired to mine the Kermac potash profitably.
dividers, guides, escapeway, power cables, etc., in- All but two of the seven operating companies in
stall skip loading facilities and develop the shaft the district are mining principally in one ore zone
station. With this work accomplished, Kermac would where the ore varies from 5 to 15 ft in height, is of
then be ready to install the permanent hoist and reasonably good grade and contains not more than
proceed with mine development. The company could 2% clay or insolubles. Kermac is mining in a dif-
have elected to purchase or rent a temporary hoist ferent, higher ore zone, which averages 54 in. in
and the necessary loading facilities, make the neces- height and contains 5 to 7% clay or insolubles. To
sary installations and proceed. It was decided, how- insure maximum extraction with minimum dilution,
ever, to purchase a hoist that would be suitable as the mining department felt that some type of con-
a permanent hoist for the Man and Materials shaft, tinuous mining machine adaptable to a form of long-
locate it in such a position midway between the two wall mining would be most suitable.
shafts so that by overwinding the hoisting rope, it At that time, the only available continuous min-
could be used for all the work in the production ing machines suitable for these mining heights were
shaft and then, by merely underwinding the same ripper-type miners, but, after considerable observa-
rope, use it as a permanent facility in the Man and tion and study, it was decided that the ripper type
Materials shaft. The cost of this permanent installa- machines would not meet Kermac's requirements.
tion was about equal to the investment that would A low headroom boring machine made by the
have been required for the temporary facilities. Goodman Mfg. Co. seemed more suitable and had
The 15-foot-diameter, concrete-lined production proven successful in coal fields, so the company
shaft is equipped with a Koepe-type friction hoist contracted with Goodman for a trial machine
having an 88-in. drum, six 1-in. hoist ropes and built to certain specifications.
three 1%-in. tail, or balance, ropes. It was necessary Because of the higher horsepower required to cut
to use a smaller drum with a greater number of potash and because the proposed system of mining
ropes to permit the hoisting drum to be mounted required the use of long trailing cables, the company
directly over the skip compartments without the use became concerned about the availability of adequate
of rope deflection sheaves. All of the main facilities power at the face. Any excessive voltage drop would
MINING ENGINEERS DECEMBER 1966, MINING ENGINEERING-71
reduce torque output of the machine and could be similar number of headings are driven. This width,
the difference between running or stalling the ma- with a 7-ft-wide pillar, gives an extraction of ap-
chine. The apparent advantages of feeding 4160 v to proximately 80%. To date, subsidence has been
the machine rather than the generally accepted 480 gradual with no major roof problems. Dilution has
v left no choice but to proceed in that direction. A been kept to a minimum and, with controls recently
brief comparison of a 350,000 CM type G cable such initiated, further improvement is anticipated.
as would be used on a 4160-v machine is: weight, In the roof, a thin clay streak separates the ore
7.2 lb per foot for the 480-v machine and 2.2 Ib per bed from a competent 41%-ft-thick salt bed. In nor-
foot for the 4160-v machine. The lighter weight is mal practice, the boring machine cuts to the salt
an advantage when men are pulling cable in entries leaving an excellent firm back. However, if for any
only 54 in. high. The cost for the 480-v cable is reason ore is left in the back, the ore will separate
$7.48 per ft compared to $2.82 per ft for the higher from the clay seam and it becomes necessary to
voltage cable. The voltage drop is 5: for 500 ft of roof-bolt this particular area with 2-ft bolts. At the
480-v cable at 500 KVA, compared with 1.3% for face, the ore is dropped onto the floor by the miner,
2000 ft of the higher voltage cable. picked up by a loading machine and loaded into
The manufacturer incorporated into the machine six-wheel shuttle cars for haulage to the feeder, and
a fail-safe ground-wire monitoring circuit whereby then onto the conveyor.
either an open control wire or ground wire or a Ore from three different directions is conveyed
short circuit between control and ground wire will on 42-in. rope suspended-type conveyors to a central
automatically stop the machine. While it is inevita- surge pocket. All of the belts are interlocked and
ble that trailing cable will be damaged during oper- sequenced to prevent overloading. The ore is then
ation, there has not been a single injury to personnel fed onto a vibrating scalping feeder where the
attributable to the high voltage on the five con- minus 4-in. ore is dropped directly onto a belt con-
tinuous boring machines Kermac now has in use. veyor, the oversized ore is crushed to 4 in. by single
The present mine plan is considered as a modified roll crusher and all material is then conveyed to a
longwall system. Panels 800 to 1000 f t in width by 500-ton underground storage pocket. The bottom
2500 f t in length are driven from a main entry sys- of this pocket is equipped with a vibrating feeder
tem. Initially, a three-entry system is developed to which regulates the feed onto a 36-in. conveyor used
the full length of the panel with the belt conveyor to carry the ore to a 50-ton surge bin located over
installed in the center entry. The conveyor is ad- the skip loading pockets a t the production shaft. Ore
vanced in 160-ft increments or every other break- is hoisted in 12-ton, bottom-dump skips operating
through. on a 91-sec cycle. From the shaft it is conveyed, de-
The rapid advance of these miners while in de- pending on demand, either to the mill or to a 15,000-
velopment (up to 1200 ft of advance per miner per ton raw ore storage building. Both the hoisting and
month), requires careful planning and scheduling conveying systems from the mine face to the sur-
to keep the belt advanced for several machines. face storage building are completely automated and
Upon completion of the development headings, the unattended.
borer is turned at 90" to the entries and starts the The 4160-v power is brought into the mine via the
retreat program. This consists of driving headings production shaft through two 600 MCM cables to
26 f t wide on a double pass to a predetermined the main switch house located near the shaft section.
depth of 300 to 400 ft. Several of these headings are Electrically, the mine is divided into two areas,
driven on the one side and then the machine is north and south, with a separate 600 MCM feeder
moved to the opposite side of the entries where a going to each area. At the intersection of a panel
with the main entry system, a switch house is pro-
A plrzn of the Kermnc potcish mine.
vided. This switch house has a feed-through for
power extension into the main entries and a breaker
for power into the panel. As the panel is developed
2/0 5 KV power cable is extended to feed the con-
tinuous miner control box or ampguard. This amp-
guard also contains a feed-through which permits
feeding a 4160/440 transformer for power into the
shuttle cars, loaders, fans, etc., and a breaker for the
trailing cable to the continuous miner.
The original continuous mining machine has been
in operation for slightly more than a year and has
mined more than 300,000 tons with no major main-
tenance problem. Numerous minor improvements in-
dicated by experience have been incorporated in
the later machines. On several occasions, more than
1000 tons of ore per machine shift have been mined.
Although the mine has been in operation only a
short time, Kermac has been able to meet produc-
tion requirements, and has established that continu-
ous mining is more economical than conventional
methods for its potash orebody. zs

72-MINING ENGINEERING, DECEMBER 1966 SOCIETY OF

Anda mungkin juga menyukai