Anda di halaman 1dari 5

Risk of Cable Overheating And Premature Ageing due

to Load Control Measures


David Clements Dr Pierluigi Mancarella
School of Electrical and Electronic Engineering School of Electrical and Electronic Engineering
University of Manchester University of Manchester
Manchester, UK Manchester, UK
david.clements@postgrad.manchester.ac.uk

Cyclic ratings are dependent on the load curve present on an


underground cable. If the load curve changes the cable rating
must be adjusted or the operator risks overheating and
damaging the cable. Many have suggested using demand
response or energy storage to allow networks to remain within
ratings during contingencies. Unfortunately the resulting load
profiles could cause the real circuit ratings to be lower than
expected. This paper will show that without updating ratings to
allow for manipulated load curves network operators risk
overheating and damaging cables if demand response is used on
a network. However, a case study shows that the demand
response required to cause overheating incidents is very
significant and may not occur in reality.

I. INTRODUCTION
Cyclic ratings for underground cables are widely used by Figure 1. Example of Load Growth after Manipulation by Energy Storage/
Demand Side Response
distribution network operators(DNOs) in the UK. Cyclic
ratings allow more current to pass through a cable than the What is often missed, is that when the load passing
continuous rating by taking advantage of the thermal inertia of through a cable is manipulated the cables cyclic rating should
a cable. The cyclic rating ensures that the cable never reaches fall to match the new profile. Failure to do so may result in
its maximum allowable temperature despite current exceeding cables overheating and suffering premature aging requiring
the cables continuous rating for short times. However, for replacement earlier in their life, at considerable cost.
cyclic ratings to be correct load must follow the load cycle Alternatively running studies on DSR using continuous ratings
used in the cable rating calculation. If the load curve changes will under-estimate how much capacity a network had prior to
due to demand response or energy storage, the cyclic rating the application of demand side response. Correcting the cyclic
must be recalculated. Peak load remaining under the ratings will reduce the effectiveness of energy storage and
previously calculated cyclic rating does not guarantee the demand response, unlocking less capacity than previously
cable will not age prematurely due to overheating. This believed.
premature aging could lead to high impact events such as
occurred in Auckland in 1998[1], as cables will be damaged Several authors have considered the interaction between
while other parallel cables are unavailable . real time ratings for overhead lines and demand response [5]–
[7]. This work does not cover the risk of cyclic ratings no
The use of load control measures such as storage and longer being valid as overhead lines do not have the same
demand side response (DSR) has been much studied by thermal inertia as underground cables. The current rating of an
academics[2], [3] and trialed by industry[4] . The application overhead line is predominately based on prevailing conditions
of these studies can lead to a load profile such as that shown in [8] not historic currents passed through the cable. For this
Figure 1. reason manipulating the load on overhead lines as described in
[5]–[7] does not pose a risk to overhead lines.
Some papers and industrial trials have studied the effect of
dynamically calculating underground cable ratings or

This work was funded by EA Technology and the EPSRC under a iCase
conversion, grant number xxxxx
temperatures[9]–[11]. These studies have focused on how Faults occur randomly at times generated using a
much capacity can be unlocked by knowing soil conditions exponential distribution. Once a fault occurs its repair time is
and being able to predict customer behaviour in advance. They subject to a normal distribution. If a line is overloaded
do not examine what would happen if loads were manipulated following reconfiguration energy storage is used to inject
without considering the effect on cyclic rating factors. enough power to reduce current to the circuit rating. Critically,
load is constrained down to the cables cyclic rather than
This paper will show the frequency of cables overheating continuous rating. The continuous rating can be sustained
due to not correcting cyclic ratings factors on cables used in indefinitely, while the cyclic rating which is widely used can
N-1 arrangements. Appropriate cyclic ratings will be only be sustained for short periods of time, relying on times of
calculated for the cable without the intervention of load lower load to cool the cable.
control measures. Energy storage will then be used to control
load during contingencies, potentially leading to cables B. Energy Storage Utilisation
overheating. This paper will demonstrate the importance of Energy storage is used to manage perceived overloads
acknowledging the effect of changing cyclic ratings when (current in a cable exceeding the cyclic rating) by injecting
loads are manipulated by either demand response or energy current to reduce current in overloaded cables. In practical
storage. situations use of energy storage would likely be limited to
The paper is structured as follows. A methodology is only reducing power to the circuit rating (likely originally
described in section II for estimating how frequently cables calculated as a cyclic rating) and no more so as to maintain
might overheat if demand response is applied to a charge in the battery should repairs take longer than expected.
demonstration system. Section III describes a case study the As energy storage is only utilized during contingency
results of which are presented in section IV. Section V situations this simulation assumes that the storage is only
summarises the outcomes of this research and makes recharged once the contingency has finished to minimize
concluding remarks discussing the practical implications for strain on the network. This may serve to under-estimate the
demand side response users. effects demonstrated here.
II. METHODOLOGY C. Cable Temperature
A. Methodology While cables are typically operated to keep current within
a rating, the real constraint on the amount of current cables
The methodology is a sequential Monte Carlo simulation can carry is the temperature they reach. Cable thermal
with a time-step of half an hour. In order for the cables to dynamics is a complicated field in itself discussed well in [14].
reach equilibrium temperature prior to logging data the model This paper will focus on the application of cable ratings rather
was run for half a year (8760 time steps) before collecting data than their calculation. For this reason the CRATER software
on failures and circuit overloads. Load flows are carried out package [13] is used to calculate the temperature of the cables
using OpenDSS [12] and cable ratings/temperatures are during each half-hour of the simulated year.
calculated by EA Technology’s CRATER software [13]. A
flow chart describing the overall flow of the model is shown Critically the temperature information generated by
in Figure 2. CRATER is not passed to any other part of the model and not
used for assessing the amount of energy that should be
injected into the system to maintain cable temperatures at an
acceptable level.
D. Load Model
Load follows the model expressed algebraically in (1).
∗ 48 ∗ /336 (1)

Where is the Load in MW in period P, is the


maximum demand from the load. is the proportion of
maximum load drawn by a load at a given half hour. is
the proportion total energy demand drawn by loads in a given
week. The constants 48 and 336 are used as they are the
number of half hours in a day and week respectively.
III. CASE STUDY
The case study covers a relatively simple pair of 11kV
feeders constructed from single core 300mm² cables adhering
to BS 6622:1999[15] arranged in trefoil. Each feeder had eight
substations drawing equal load at equal distances distributed
along each feeder. The two feeders were connected at the end
via a normally open point only used to restore supply after a
Figure 2. Flow Chart
fault. This configuration is shown in Figure 3. The simplicity
of this arrangement was primarily to ensure clarity in the supply to all customers. However, an arbitrarily large energy
results that are communicated by this work. storage device was placed at the normally open point to supply
extra energy to whichever feeder was overloaded as a result of
The simulation was carried out using iterations of one restoration activities. This storage was arbitrarily large to
year. However, as the starting cable temperatures are based on demonstrate the consequences of manipulating load profiles
previous loads that have passed though the cable before each without considering the effect on cable ratings. Practical
simulated year. For this reason, before the simulated year in installations would have different characteristics and have
each iteration a initialisation period of 6 months was different impacts on network reliability.
simulated. No results were collected in this time but the cables
were allowed to heat so they started each simulated year at the Two different average repair times were used, 12 and 24
correct temperature. One thousand iterations were executed hours to demonstrate the effect repair times have on the
for each scenario considered in the case study. chance of overheating. Repair times were normally
distributed with a standard deviation of half of the mean (6 or
12 hours respectively). The simulation was stopped when
1000 faults and corresponding reconfiguration had been
simulated.
IV. RESULTS

Table 1 shows the impact of different loading and repair


speed scenarios on the chance of the first leg of the feeder
(from the source substation to the first load point). Throughout
the simulation only the first leg of each feeder ever
overloaded.
Higher loadings and longer repair times are associated
with a higher chance of energy storage causing a cable to
overheat. The conductor of the cable described should never
exceed 90°C. However, in all cases studied this occurs, with
higher base loadings and longer repairs associated with more
frequent, longer lasting and higher temperature events.
The repair time significantly affecting the chance of the
cable overheating may appear counter-intuitive. However, it is
important to understand the repair time effects the chance of
overheating in two ways. Firstly, and perhaps obviously the
longer the repair the more likely peak load is to occur during
Figure 3. Network Diagram the repair. Secondly, it is important to remember that prior to a
fault occurring the cable will be relatively cool, even at 75%
A half hourly load curve was derived from the CLNR loaded the I²R losses will only be 56% of their maximum.
project dataset of residential customers[16]. This data was Therefore pre fault the cables temperature will only be raised
used to create a half hourly representation of load. to approximately 56% of its maximum allowable temperature.
Cables have significant thermal inertia, even if considerably
Two loading scenarios were considered, where each cable overloaded post-fault it takes time for the cable to reach its
was either initially 75% loaded or 65% loaded pre-fault based maximum temperature. If a fault is allowed to persist for
on the cables cyclic rating. This would normally be longer the cable will have longer to reach an unacceptable
unacceptable as post fault it would not be possible to restore

TABLE I. EFFECT OF LOAD MANIPULATION ON RESULTING CABLE TEMPERATURES.

Pre Fault Original Pre Fault Maximum Average Line Probability of Average Average Chance of Cable
Peak Circuit Cyclic Loading as Load Repair Time Fault Resulting Duration of Temperature Temperature
Loading (A) Rating (A) Percentage of Reduction (hours) in Over Over Increase above Exceeding
Original from Storage Temperature Temperature Design Design
Rating (A) Event (%) Event (Hours) Temperature Temperature by
(°C) 5 °C (%)
333 444 75% 226 24 32.1 4.17 2.52 4.6
333 444 75% 226 12 13.8 2.19 1.48 0.5
289 444 65% 137 24 12.0 1.92 1.21 0
289 444 65% 137 12 1.60 1.36 1.18 0
temperature. alongside the relatively small increase in cable temperatures
The effect of higher loadings causing more overheating is suggest that the risk of this occurring is minimal.
unsurprising. Higher loadings mean that more energy is
delivered by the energy storage during contingencies. But also B. Adjusted Ratings
that cable load is maintained at peak for much longer than Given the worst overload a circuit is likely to experience post
would otherwise be the case. Furthermore the cable will be fault is predicable it is possible to adjust ratings to
warmer prior to the fault occurring reducing the beneficial incorporate the flattening of peak load due to load control.
effect of the cable being cool pre-fault. The cable could be operated with this restriction indefinitely
It should be acknowledged that the while the temperatures assuming sufficient load could continue to be constrained.
achieved by cables are higher than normally permitted they do Using Crater adjusted ratings were calculated using an load
not appear excessive. The proportion of a cables life it would curve adjusted by constraining load at a nominal value. This
spend overheated due to these effects is small. The effect of was an iterative process. A new constraining limit was tested,
over temperature events on cables is poorly understood. the load profile calculated and entered into crater to calculate
However, despite the lack of understanding it is entirely the resulting cable temperature. This process gave the values
possible that the over temperature events might be considered in Table III.
tolerable. Even if this is the case, it should be acknowledged
that this is a risk network operators are taking rather than TABLE III. ADJUSTED CYCLIC RATINGS INCLUDING LOAD
assuming that cables are not damaged by changing load cycles CURTAILMENT
using energy storage or demand side response. Worst Pre Fault Original Adjusted Continuous
A. Application of Annual Load Curve Case % Peak Cyclic cyclic Rating
Circuit Circuit Rating rating
The results presented in Table I assume that other than Overload Loading
variation through the day load is constantly at its maximum. After (A)
This is unrealistic, due to reduced heating and lighting Fault
demand in particular load is lower in the UK during the 50% 333 444 397 386
30% 289 444 408 386
summer months. The average energy consumed by a UK
10% 244 444 424 386
domestic customer in each week of the year was calculated
from the CLNR dataset [16]. This was applied to the load as a
This results in the load curves shown in Figure 3.
scaling factor in each week giving the results in Table II. It
should be noted that the figures for average duration and
temperature of events are based on the number of temperature
excursions that occurred. In the case where the circuit was
loaded to 65% pre fault with twelve hour repair times such
over temperature occurrences were very rare and the duration
and average temperature are for this reason likely anomalous.

These results show that the chance an overheat actually


occurring is far lower once the annual variation in load is
accounted for. In order for a fault to cause a cable to overheat
it must happen during the winter when load is sufficiently
high, persist through the peak load, and be on a part of a
feeder where load is sufficiently unevenly distributed to
require use of energy storage to support the network. This
further reduction in the probability of an overheat occurring, Figure 4. Constrained Load Curves

TABLE II. EFFECT OF LOAD MANIPULATION ON RESULTING CABLE TEMPERATURES FOLLOWING THE APPLICATION OF ANNUAL LOAD CURVE.

Pre Fault Original Pre Fault Maximum Average Line Probability of Average Average Chance of Cable
Peak Circuit Cyclic Loading as Load Repair Time Fault Resulting Duration of Temperature Temperature
Loading (A) Rating (A) Percentage of Reduction (hours) in Over Over Increase above Exceeding
Original from Storage Temperature Temperature Design Design
Rating (A) Event (%) Event (Hours) Temperature Temperature by
(°C) 5 °C (%)
333 444 75% 226 24 12.36 2.86 1.85 0.0
333 444 75% 226 12 2.79 1.86 1.44 0
289 444 65% 137 24 2.95 1.6 1.15 0
289 444 65% 137 12 0.43 2.36 1.53 0
VI. REFERENCES
The longer cables operate at the adjusted cyclic rating, the
closer that rating will be to the cables continuous rating. [1] B. Leyland, “Auckland central business district supply failure: the
These reductions in rating may appear significant given the ministerial inquiry,” Power Eng. J., vol. 12, no. 6, pp. 269–273,
rarity of overloads in Table 1. However, it should be 1998.
[2] S. Tindemans, P. Djapic, and G. Strbac, “Comparison of
remembered that the ratings in Table III do not account for approaches for quantifying demand side response capacity credit
the fact the cable will be cool pre-fault and it will be possible for the use in distribution network planning,” IET Int. Conf. Resil.
to exceed these ratings for a short time as the cable heats[17]. Transm. Distrib. Networks 2015, p. 7 (6 .)-7 (6 .), 2015.
[3] Y. Zhou, P. Mancarella, and J. Mutale, “A Framework for Capacity
V. CONCLUSIONS Credit Assessment of Electrical Energy Storage and Demand
Cyclic ratings depend on the shape of the load experienced Response,” IET Gener. Transm. Distrib., vol. 10, pp. 1–17, 2016.
[4] UK Power Networks, “Industrial and Commercial Demand
by the asset being rated. If this shape changes due to load Response for outage management and as an alternative to network
control measures such as demand side response or energy reinforcement,” 2014.
storage, ratings must be recalculated. However, in N-1 [5] K. Kopsidas, A. Kapetanaki, V. Levi, and J. Milanovic, “Optimal
arrangements this paper has shown that aggressive amounts of Demand Response Scheduling with Real Time Thermal Ratings of
demand side response and long repair times are required to Overhead Lines for Improved Network Reliability,” IEEE Trans.
Smart Grid, pp. 1–1, 2016.
cause cables to overheat. Nonetheless, this paper highlights [6] D. M. Greenwood, N. S. Wade, P. C. Taylor, S. Member, P.
the need to remember the assumptions underlying how Papadopoulos, and N. Heyward, “A Probabalistic Method
underground cables have been rated as loads are adjusted to Combining Electrical Energy Storage and Real-Time Thermal
maximise network utility. Failure to do so could lead to Ratings to Defer Network Reinforcement,” vol. 8, no. 1, pp. 374–
premature aging of network assets. Or in a worst case scenario 384, 2017.
high impact events such as the Auckland blackout of 1998[1], [7] D. M. Greenwood, N. S. Wade, P. C. Taylor, S. Member, P.
Papadopoulos, and N. Heyward, “Storage and Real-Time Thermal
as one outage leads to other cables overheating and failing. Ratings to Defer Network Reinforcement,” vol. 8, no. 1, pp. 374–
384, 2017.
As with all cable rating calculations it is important to
[8] Western Power Distribution, “Project FALCON: Dynamic Asset
acknowledge that while calculations can give us precise values Rating Overhead Lines,” 2015.
for anticipated cable temperatures, precision is no guarantee of [9] M. Z. Degefa, M. Koivisto, R. J. Millar, and M. Lehtonen,
accuracy. In many practical cable installations on distribution “Dynamic Thermal State Forecasting of Distribution Network
networks there are a great number of unknowns. There may be Components For enhanced active distribution network capacity,”
crossings with other electrical cables, heating pipes, local 13th Int. Conf. Probabilistic Methods Appl. to Power Syst.
(PMAPS 2014), 2014.
conditions which affect soil thermal conductivity. Many [10] R. Huang, J. A. Pilgrim, and P. L. Lewin, “Dynamic Cable Ratings
cables may already be running hotter than simple calculations for Smarter Grids,” in 4th IEEE PES Innovate Smart Grid
might suggest. Even adding a comparatively small extra Technologies Europe, 2013.
amount to cable temperatures could have significant [11] Western Power Distribution, “Project FALCON: Dynamic Asset
consequences. If aggressive demand response was utilised it Rating Cables,” 2015.
[12] R. C. Dugan and T. E. McDermott, “An open source platform for
may be wise to extract samples from the first circuits it was collaborating on smart grid research,” IEEE Power Energy Soc.
used on to check for insulation degradation. Gen. Meet., no. Ivvc, pp. 1–7, 2011.
[13] G. L. E. Poidevin and T. Dutton, “Modern Approaches to Cable
The risk of overheating cables could be mitigated by the Ratings in the UK,” in 19th International Conference on Electricity
use of adjusted cable ratings alongside load reduction efforts. Distribution, 2007, no. 355, pp. 21–24.
Cable rating packages could be used to calculate an [14] R. J. Millar and M. Lehtonen, “A Robust Framework for Cable
appropriate derating factor for the cable when demand Rating and Temperature Monitoring,” IEEE Trans. Power Deliv.,
response or storage is used. Alternatively once load reduction vol. 21, no. 1, pp. 313–321, 2006.
[15] British Standards Institute, “BS 7870-4.10:2011.” 2011.
(by storage or demand response) is necessary, load might be [16] Northern Power Grid, “Basic profiling of domestic smart meter
curtailed to the continuous rating. This conservative customers.” Northern Power Grid, 2015.
assumption might result in too much load being curtailed or [17] D. Clements, P. Mancarella, and R. Ash, “Use of Time-Limited
more energy storage being installed than might otherwise be Ratings in Distribution System to Improve Asset Utilization,” in
necessary, but would allow for the deployment of load control Cired Workshop 2016, 2016.
techniques without risking premature aging and failure of
existing network components.

Anda mungkin juga menyukai