Anda di halaman 1dari 28

PEMBERSIHAN LAHAN PEMBUATAN BOWPLANK PEMBUATAN BEDENG

Start: 05/04/19 ID: 2 Start: 09/04/19 ID: 3 Start: 10/04/19 ID: 4


Finish: 08/04/19 Dur: 2 days Finish: 09/04/19 Dur: 1 day Finish: 10/04/19 Dur: 1 day
Res: Res: Res:

PEMBUATAN GUDANG
Start: 10/04/19 ID: 5
Finish: 10/04/19 Dur: 1 day
Res:

PEKERJAAN GALIAN TANAH


Start: 18/04/19 ID: 8
Finish: 19/04/19 Dur: 2 days
Res:

Page 1
Page 2
PEMASANGAN AIR DAN LISTRIK
Start: 09/04/19 ID: 6
Finish: 17/04/19 Dur: 7 days
Res:

Page 3
PEKERJAAN URUGAN PASIR BAWAH PONDASI PEKERJAAN ANSTAMPING PEKERJAAN BATU KALI PEKERJAAN URUGAN KEMBALI
Start: 22/04/19 ID: 9 Start: 23/04/19 ID: 10 Start: 24/04/19 ID: 11 Start: 03/05/19 ID: 12
Finish: 22/04/19 Dur: 1 day Finish: 23/04/19 Dur: 1 day Finish: 02/05/19 Dur: 7 days Finish: 03/05/19 Dur: 1 day
Res: Res: Res: Res:

Page 4
Page 5
Page 6
PEKERJAAN PEMBESIAN PEKERJAAN BEKISTING PEKERJAAN PENGECORAN
Start: 06/05/19 ID: 15 Start: 08/05/19 ID: 16 Start: 09/05/19 ID: 17
Finish: 07/05/19 Dur: 2 days Finish: 08/05/19 Dur: 1 day Finish: 10/05/19 Dur: 2 days
Res: Res: Res:

PEKERJAAN PEMBESIAN PEKERJAAN BEKISTING


Start: 08/05/19 ID: 19 Start: 13/05/19 ID: 20
Finish: 09/05/19 Dur: 2 days Finish: 13/05/19 Dur: 1 day
Res: Res:

PEKERJAAN PEMBESIAN
Start: 13/05/19 ID: 23
Finish: 13/05/19 Dur: 1 day
Res:

Page 7
Page 8
Page 9
PEKERJAAN PENGECORAN
Start: 14/05/19 ID: 21
Finish: 16/05/19 Dur: 3 days
Res:

PEKERJAAN BEKISTING PEKERJAAN PENGECORAN PEMASANGAN DINDING BATA MERAH 1:2


Start: 17/05/19 ID: 24 Start: 20/05/19 ID: 25 Start: 23/05/19 ID: 27
Finish: 17/05/19 Dur: 1 day Finish: 22/05/19 Dur: 3 days Finish: 27/05/19 Dur: 3 days
Res: Res: Res:

Page 10
Page 11
Page 12
PEMASANGAN DINDING BATA MERAH 1:5 PEMASANGAN MCB PEMASANGAN KABEL
Start: 28/05/19 ID: 28 Start: 30/05/19 ID: 37 Start: 31/05/19 ID: 38
Finish: 29/05/19 Dur: 2 days Finish: 30/05/19 Dur: 1 day Finish: 31/05/19 Dur: 1 day
Res: Res: Res:

PEMASANGAN PIPA PVC PEMASANGAN SALURAN KRAN AIR


Start: 30/05/19 ID: 50 Start: 31/05/19 ID: 51
Finish: 30/05/19 Dur: 1 day Finish: 31/05/19 Dur: 1 day
Res: Res:

PEMASANGAN PIPA PEKERJAAN SUMUR RESAPAN PEKERJAAN CARPORT


Start: 30/05/19 ID: 53 Start: 31/05/19 ID: 56 Start: 04/06/19 ID: 82
Finish: 30/05/19 Dur: 1 day Finish: 03/06/19 Dur: 2 days Finish: 05/06/19 Dur: 2 days
Res: Res: Res:

PEKERJAAN PLESTERAN 1:4


Start: 03/06/19 ID: 29
Finish: 03/06/19 Dur: 1 day
Res:

Page 13
Page 14
PEKERAAN RANGKA ATAP BAJA RINGAN PEKERJAAN PENUTUP ATAP PEKERJAAN LIST PLANK
Start: 28/05/19 ID: 32 Start: 30/05/19 ID: 33 Start: 03/06/19 ID: 35
Finish: 29/05/19 Dur: 2 days Finish: 30/05/19 Dur: 1 day Finish: 03/06/19 Dur: 1 day
Res: Res: Res:

PEKERJAAN NOK
Start: 31/05/19 ID: 34
Finish: 31/05/19 Dur: 1 day
Res:

Page 15
PEKERJAAN ACIAN 1:3
Start: 04/06/19 ID: 30
Finish: 04/06/19 Dur: 1 day
Res:

Page 16
Page 17
PEMASANGAN RANGKA HOLLOW PLAFOND PEMASANGAN PLAFOND GYPSUM PEMASANGAN LIST PLAFOND PEKERJAAN LANTAI KERJA
Start: 04/06/19 ID: 45 Start: 06/06/19 ID: 46 Start: 07/06/19 ID: 47 Start: 10/06/19 ID: 68
Finish: 05/06/19 Dur: 2 days Finish: 06/06/19 Dur: 1 day Finish: 07/06/19 Dur: 1 day Finish: 10/06/19 Dur: 1 day
Res: Res: Res: Res:

Page 18
Page 19
Page 20
PEKERJAAN URUGAN PASIR BAWAH LANTAI PEMASANGAN LANTAI KERAMIK 30X30
Start: 11/06/19 ID: 69 Start: 12/06/19 ID: 70
Finish: 11/06/19 Dur: 1 day Finish: 12/06/19 Dur: 1 day
Res: Res:

PEMASANGAN CLOSET DUDUK


Start: 12/06/19 ID: 54
Finish: 12/06/19 Dur: 1 day
Res:

PEMASANGAN KERAMIK LANTAI KAMAR MANDI 20X25 PEMASANGAN KERAMIK DINDING KAMAR MANDI
Start: 13/06/19 ID: 71 Start: 14/06/19 ID: 72
Finish: 13/06/19 Dur: 1 day Finish: 14/06/19 Dur: 1 day
Res: Res:

PEMASANGAN KERAMIK DINDING KITCHEN SINK


Start: 14/06/19 ID: 73
Finish: 14/06/19 Dur: 1 day
Res:

Page 21
PEKERJAAN PENGECATAN DINDING PEKERJAAN PENGECATAN PLAFOND PEKERJAAN PENGECAAN LIST PLAFOND PEMASANGAN TITIK LAMPU
Start: 17/06/19 ID: 75 Start: 18/06/19 ID: 76 Start: 19/06/19 ID: 77 Start: 20/06/19 ID: 39
Finish: 17/06/19 Dur: 1 day Finish: 18/06/19 Dur: 1 day Finish: 19/06/19 Dur: 1 day Finish: 20/06/19 Dur: 1 day
Res: Res: Res: Res:

Page 22
PEMASANGAN STOP KONTAK
Start: 20/06/19 ID: 40
Finish: 20/06/19 Dur: 1 day
Res:

PEMASANGAN SAKELAR TUNGGAL


Start: 20/06/19 ID: 41
Finish: 20/06/19 Dur: 1 day
Res:

PEMASANGAN SAKELAR DOUBLE


Start: 20/06/19 ID: 42
Finish: 20/06/19 Dur: 1 day
Res:

PEMASANGAN STOP KONTAK KHUSUS


Start: 20/06/19 ID: 43
Finish: 20/06/19 Dur: 1 day
Res:

PEKERJAAN KUSEN PINTU PEKERJAAN DAUN PINTU


Start: 18/06/19 ID: 59 Start: 19/06/19 ID: 60
Finish: 18/06/19 Dur: 1 day Finish: 19/06/19 Dur: 1 day
Res: Res:

PEKERJAAN KUSEN JENDELA PEKERJAAN DAUN JENDELA


Start: 18/06/19 ID: 62 Start: 19/06/19 ID: 63
Finish: 18/06/19 Dur: 1 day Finish: 19/06/19 Dur: 1 day
Res: Res:

PEKERJAAN BOUVENLIGHT PEKERJAAN PENGECATAN KUSEN


Start: 18/06/19 ID: 65 Start: 20/06/19 ID: 78
Finish: 18/06/19 Dur: 1 day Finish: 20/06/19 Dur: 1 day
Res: Res:

PEKERJAAN JALUSI
Start: 18/06/19 ID: 66
Finish: 18/06/19 Dur: 1 day
Res:

Page 23
Page 24
PEKERJAAN PEMBERSIHAN LAHAN BANGUNAN JADI
Start: 25/06/19 ID: 83
Finish: 26/06/19 Dur: 2 days
Res:

Page 25
PEKERJAAN PENGECATAN PINTU PEKERJAAN PENGECATAN JENDELA
Start: 21/06/19 ID: 79 Start: 24/06/19 ID: 80
Finish: 21/06/19 Dur: 1 day Finish: 24/06/19 Dur: 1 day
Res: Res:

Page 26
Page 27
Critical Milestone Critical Inserted Marked Project Summary

Project: TUBES MK
Noncritical Critical Summary Inserted Critical External Highlighted Critical
Date: Mon 29/04/19
Critical Milestone Summary Critical Marked External Highlighted Noncritical

Page 28