TRAINIG REPORT
ON
Guru Hargobind Thermal Power Plant
LehraMohabbat
(Bathinda)
1
PROFILE OF THE PLANT
CONSTRUCTION IN 1992
STARTED
TOTAL UNITS IN 4
THE PLANT
3
CHAPTER-1
BRIEF HISTORY OF PLANT
Ever widening gap between the power demand and its availability in the
state of Punjab was one of the basic reasons for envisaging the thermal plant
at “Lehra Mohabbat” Distt. Bathinda. The other factors favoring the
installation of this thermal were low initial cost and less generation period as
compared to hydroelectric generating stations, its good railway connection
for fast proximity to load center. Guru Gobind Singh thermal plant is
Government undertaking (under P.S.E.B.).
Initially it was going to set up at Bathinda under GNDTP but the air
force personal restricted its set up at Bathinda hence plant site is shifted to
Lehra Mohabbat about 22Km from Bathinda city. Later this plant was
approved as a separate autonomous body its name as Guru Hargobind
Thermal Plant.
The construction of the plant commenced in 1992 and its unit
started working in December 1997. Its second unit commenced in August
1998. The main companies whose technology pawed the way of this plant
are TATA Honeywell & BHEL in turbine and boiler control .The total set up
cost of the plant is 1200 crores and the capacity of the plant is 2 *210+2*250
=920 MW. The over all efficiency of the plant is 95%. The power
availability from the plant now meets 20-25% of the total power requirement
in Punjab. It has gone a long way in ushering prosperity in the state by
emerging a large number of agricultural pumping sets, more industrial
connections, 100% rural electrification, increased employment potential
reliability and improvement in continuity of supply and system and removal
4
of power cuts to a great extent. It has also led fast development of
environment in area around District Bathinda by providing employment to
about 3000 persons. Two new units of 250MW each are started,
1.1 The following considerations have to be examined in detail before
selection of site for a plant: -
A Availability of fuel such as coal.
B Ash disposal facilities.
C Space requirements.
D Nature of land.
E Most important availability of water.
F Availability of labour.
G Transport facilities.
H Public Society problems such as pollution.
I Development of backward area.
5
CHAPTER-2
RAW MATERIAL AND THEIR SOURCES
2.1 INTRODUCTION
6
CHAPTER-3
BASICS OF A THERMAL PLANT
7
which grind the coal into powder. The powder coal is carried from the mill
by steam of air heated air in the air heater driven by primary air fan (PA) to
boiler burners where it is blown into the furnace and burns like a gas a force
draft fan provide addition controllable to the burners to assist combustion.
The product of this combustion is dust and ash. (Ratio of 5to 1) the ash to
the bottom of the boiler and is periodically sluiced to mash setting pits .The
dust carried in the fuel gas to the precipitators where it is extracted by high
voltage electrodes. The dust is then conveyed to settling lagoons or removed
by the road for safe. The fuel gas passes by an induced draft fan (ID) to the
chimney. The heat released by the burning coal is absorbed by long length of
tubing which forms the boiler valves. Inside the tube extremely pure water
that is known boiler feed water is converted by the heat into steam at high
pressure and temperature. The steam is then superheated in further tubes and
passes to the high pressure (H.P) turbine where it is discharged through the
nozzle into the turbine blades. The energy of the steam striking the blades
make the turbine rotates after passing through the high-pressure turbine. The
steam is returned to the boiler for reheating before passing through the
intermediate pressure turbine (IPT) and to the low-pressure turbine (LP).
Coupled to the turbine shaft is rotor of the generator, a large cylindrical
electromagnet, so that when the turbine rotor rotates, other rotor rotates with
it. The generator rotor is enclosed in the stator; which consist of large coils
copper bar in which electricity is produced by the rotation of magnetic field
created by the rotor. The electricity from the stator winding goes to a
transformer; which increase its voltage so that it can be transmitted over the
power lines into grid system. Mean while, the steam that is exhausted its
useful energy in turning the turbine is turned back into water in the
condenser so that it can be Used again in the boiler.
8
The diagram showing this whole process is shown
COAL PLANT
Conveyer belt
BOILER BUNKERS
PULVERISING MILLS
BOILER BURNER
FD Fan
COMBUSTION
Dust
Ash
COAL BURN
Heat released
BOILS WATER WHICH GIVES STEAM
STEAM IS SUPERHEATED
9
EXHAUSTED STEAM CONDENSER USED AGAIN IN
ENERGY BOILER
Steam
TURBINE BLADES WATER IS PUMPED
DEAERATED IN
STEAM IS RETURNED TO
DEAERATOR
BOILER FOR REHEATING
PRESSURE INCREASES
TIRBINE SHAFT IS COMPLED BY BOILER FEED PUMPS
TO ROTOR OF GENERATOR
POWER IS STEPED UP
BY TRANSFORMER STEAM IS HEATED
IN SUPERHEATER
GRID SYSTEMS
HP TURBINE
12
The gland steam cooler is used to condense the steam extracted from turbine
glands and to maintain slight vacuum at the turbine glands to avoid steam
leakage to atmosphere from turbine glands. It is a single pass heat exchanger
with the main condensate entering from one end and leaving from the other
end. Air steam mixture passes over the tubes in zigzag path due to number of
baffles and thus steam is condensed there-by heating the condensate inside
the tubes.
3.3.10 DRAIN COOLER (DRN CLR)
Drain cooler (DRN CLR) is provided to sub cool the drains coming from
Low Pressure (LP) Heater to improve the cycle efficiency by heating up the
condensate flowing through the tube system.
3.3.11 LP HEATERS (LP HTRS)
The LP heaters (LP HTRS) are of the surface cooled type. They are designed
for vertical mounting. These heaters are of tube system withdrawal type;
these are of four-pass design. Condensate flows inside the tubes while steam
flows Outside the tubes. The condensed steam is collected in the bottom of
the shell that is drained out.
3.3.12 H.P. HEATER (HP HTRS)
High Pressure heater is supplied heating steam from extraction 5 taken from
IP casing of turbine. The feed water enters first in this H.P heater and after
getting heated goes to High Pressure (HP) heater 6. The feed water flows
through the tubes from coldest zone to the hot most zones before it leaves
the heater. The steam flows from hot most zones to coldest zone and the
drain normally goes to deaerator.
CHAPTER-4
14
CYCLES INVOLVED IN POWER GENERATION
FURNAC
E 16
FD SCAPH RAH
FAN A&B A&B
A&B
PRIMARY AIR CYCLE
Air I/l
SECONDARY AIR CYCLE
Flue gases travel upward in the furnace and downward through the rear gas
pass to the economizer and air heaters. In the economizer, the some heat of
flue gases is utilized to heat the feed water before it goes to drum. Further in
the air heaters, the residual heat of the flue gases is utilized to pre-heat the
secondary and primary air. From the air heaters, the gases pass through the
electrostatic precipitators (ESP) and induced draft fans to the stack.
Interconnections of the gas ducts at inlet and outlet of electrostatic
precipitators are provided.
RAH ID FAN
FURNACE A&B ESP A, B, C
CHIMNEY
OR
FLUE GAS CYCLE
STACK
4.3 WATER CYCLE
17
The steam after working in three casings of the turbine i.e.
HP, IP & LP casings is condensed in the surface condenser installed just
below the LP exhaust hood. The condensate is collected in the bottom
portion called ho well from where it is pumped into the Deaerator by
condensate extraction pump (CEP) through different heating stages through
which condensate flows and get heated up gradually before finally reaching
the Deaerator. The various heating stages are Gland Steam Cooler, Drain
Cooler, and LP Heater (1, 2, 3) Deaerator. The approximate temperature rise
of condensate after passing through above heating stages is from 40/45 at
hot well to 166oC at the Deaerator (at full load).
The condensate coming from LP heaters passes the tubes of
vent condenser. The steam transfers its heat to condensate flowing within the
tubes and gets condensed. The non-condensable gases along with some
steam go out of the equipment. The drain (condensed steam) is returned to
the deaerating header.
The condensate after leaving the deaerating header enters
the feed storage tank. From feed water tank, the boiler feed pumps takes
suction of feed water thorough booster Pumps and discharge is fed to the
boiler drum after passing through different heating stages viz. HP heaters (5,
6) and feed water regulation station (FW REG STN).
FM DM
M/U
18
COND. CEP GSC DRN
A&B CLR
steam
FW HP BFP DEA
REG STN HTRS 5,6 A, B, C
FURNA
CE
HPT
FURNACE
HP BP
ECON SH
RH
IPT
COND LP BP LPT
CHAPTER-6
SYSTEM DESCRIPTION
22
6.1 INTRODUCTION
G.H.T.P.Thermal Power Plant consists of various systems. These are the
following systems: -
Coal Handling System.
Fuel oil system
Ash handling system.
D.M. Plant.
Emergency Power supply system.
Control & Instrumentation system.
Data Acquisition system.
Power supply distribution system
6.10 SOFTWARE
26
Functionally and physically separate automatic
process controllers, process monitoring and data logging equipment,
connected with each other to share relevant information for optimum plant
control is called DISTRIBUTED CONTROL SYSTEM.
6.11.1 ADVANTAGE AND DISADVANTAGE
27
Reduction in cabling in control room.
Physically and functionally separate modules.
More uniform operations and tighter controls.
Excellent information management.
Better integration of plant controls.
Considerable reduction over maintenance efforts.
Further advancement resulted in release of MAX station in. This now release
of DCS from BHEL contained new Supervisory LOCAL CONTROL
NETWORKK (LCN).
CHAPTER-7
MAX DNA SOFTWARE
28
7.1 Overview of Max station
1. Cable entry: - After when we place all the components of the system
then there must be wiring system to connect the system with each
other and with dcs. After selecting a site of the system, cable entry
must be considered. Standard entry to the cabinet is through the
bottom.
2. Power & Grounding:- Max stations are usually supplied with a
power distribution system which requires independent ac lines
(240V/10A) per line. Workstation be powered from two independent
AC lines that provide filtering & surge suppression protection. If the
extension cords are run near the electrical noise then noise could be
picked up. So all equipment should be connected to the AC safety
ground.
3. Ambient environmental condition:- When we place the system there
should be care about the environmental condition. These conditions
are, the room ventilation source should not be connected directly to
the equipment enclosure.
29
7.2 DIFFERENT PERIPHERAL CONNECTED TO MAX STATION
30
There must be at least 12-inch space be allowed b/w CRT-based
monitors to avoid electromagnetic interference. If the monitors are too
closed to one another, their picture quality may be diminished.
Whereas LCD-based monitors may be positioned closely together as
they don’t generate any electromagnetic interference.
The technology of CRT-based monitors requires that relatively
fast vertical refresh rate may be used to drive them. Slower refresh
rate may cause some users to see flickers. However LCD-based
monitor operate differently so that they do not cause flicker. They may
be run at much slower refresh rate (60Hz). Monitor run at faster rate
above 72Hz it will damage the monitor.
31
Ethernet cabling: - To reduce signal losses the metallic
network connections should be made with category better
unshielded twisted pair electrical cable.
Ethernet switch:-Ethernet switches are used to interconnect all
nodes of the Maxnet network its desired features are:-
Its support remote management to allow user to check and
configure switch setting and to read and reset port statics. The
features can great help each system maintenance procedure and
help diagnose network problem.
Fiber optic converters:- The 100base-tx to 100base-fx
converter and 10base T to 10base FL converter are used to
provide optical links to the Maxnet backbone or to individual.
When selecting a converter, look for MDI switch features to
accommodate any straight through and cross over cabling
requirements. It is also desirable for the converter to have
ability to explicitly configure their operational speed and
duplex setting.
Model PDP distributed processing unit, which runs under the window
ce.net real time multitasking operating system, is a processing engine
of the MAX dna distributed control System. The DPU performs
primary data acquisition, Control and data processing functions.
DPU also known as MAXDPU-4F is a self contained Microprocessor
based which occupies a single slot is remote processing unit cabinet
using an 8-wide MAX-PAC backplane. It is designed to operate with
user-defined combination of MAX DNA model and to communicate
32
with other devices such as PLC and remote terminal unit. DPU scan &
process information that use by another device.
Functions performed by DPU
Comprehensive alarming and calculations.
Logging of sequence of events data at 1ms.
Acquisition of trend information.
Continuous scanning of model IDP.
Execution of predefined algorithms called function blocks.
33
atomic block. DPMS keep track the object size and total
execution time for each time class.
I/O bus interface:- A Motorola 68332, 32 bit I/O processor and
field programmable gate array(FPGA) are used to interface to
both the mode IOP and I/O bus expander module. Maximum
length of model I/O bus is 30ft. The length of the remote I/O link
with fiber optic extenders is up to 2000m.
Memory :- All information regarding the operation of DPU
stored in DPU memory including (tag name, descriptions, tuning
constants, alarms limits etc). In addition, all graphical
configuration data is stored in the DPU.
Sequence of events:- Each DPU includes a built in sequence of
events recorder that can monitor up to 512 discrete inputs. These
inputs are scanned 1000 times a second and state changes are
time stamped with 1ms resolution and stored in DPU’s 1000
event buffer.
7.5 WORKING IN MAX SYSTEM
Working in MAX system will include working
with maxVUE runtime, max storian, Max editor
34
time information in the form of reports and trends usable by
operators and others within the plant
(iii) MAX DPU Tools Max DPU Tools is software utility that allow
you to create a configuration in offline mode. Using Max DPU
tools you can create configuration database file for each DPU and
define function blocks within the configuration representing an
individual DPU’s associated I/O hardware along with the control
35
(a) Updating the configuration Use the MAXDPU Tools to
create a new database .Remember that ,if you are editing an
existing database, It may need to be converted from earlier
versions .Max DPU Tools support mixed versions of the
maxDPU from a single workstation. This allows a site to have
multiple maxDPU versions present in a system. Multiple
versions may exit for several reasons. For instance, new
equipment is added or a complete update to existing equipment
is not desired or must be deferred until a later date.
36
Incremental Download This includes downloading of only a
particular group in to the DPU
37
Process control is automatically transferred from primary DPU to the
secondary DPU when the primary DPU experience a severe diagnostic alarm
of when communication between the primary and secondary DPU is lost.
38
39
INTERCONNECTION OF DPU WITH I/O MODULES
1. Remove the compact flash from the DPU and inset it into a
reader/writer attached to the workstation. Use the Workstation utility
DPU4F setup program to initialize the compact flash. This utility will
configure the IP address, Redundancy, Network Speed and version of
software. Reinstall the compact Flash into the DPU
2. Set the front panel mode switch to B to demand a cold startup
3. Insert the DPU into the chassis slot and secure the DPU using two
thumbscrews
4. Insert the network A cable into the top RJ45 connector and network B
cable into second Rj45 connector
40
5. Wait until the CP LED begins to blink Yellow/Green signifying that
DPU is operational.
6. Return the mode switch to F
7. Use the DPU4F detailed Status Display to verify that the DPU is
operational.
7.5.8 Demanding a blank startup
8. Remove the compact flash from the DPU and inset it into a
reader/writer attached to the workstation. Use the Workstation utility
DPU4F setup program to initialize the compact flash. This utility will
configure the IP address, Redundancy, Network Speed and version of
software. Reinstall the compact Flash into the DPU
9. Set the front panel mode switch to B to demand a cold startup
10.Insert the DPU into the chassis slot and secure the DPU using two
thumbscrews
11.Insert the network A cable into the top RJ45 connector and network B
cable into second Rj45 connector
12.Wait until the CP LED begins to blink Yellow/Green signifying that
DPU is operational.
13.Return the mode switch to F
14.Use the DPU4F detailed Status Display to verify that the DPU is
operational.
41
The DPU front panel contains a hexadecimal rotary switch and push buttons
for reset and Takeover. The mode switch is used to determine the operational
mode of the DPU
Setting Description
A Reserved
B If this mode is set during a reboot of the DPU, the DPU will
clear the configuration database from compact flash and go on
line as in mode ‘F’. Once the mode switch is on line the mode
switch should be moved back to the F position so that an
unexpected restart of the DPU will not erase the new database.
C Network Flash mode where DPU uses a fixed IP and MAC
address. Used when DPU needs to be configured for the first
time .The software can be upgraded on the DPU compact Flash
D Debug mode. This is a factory test mode. The DPU application
will not start automatically.
E Network Flash mode used to upgrade software on the compact
flash.
F Normal operating mode. Will use the database stored in flash if
available.
By clicking this icon will open the tracking point pop up for the point in the
Point select area. The Tracking point pop –up does not automatically close
when you swap to a new display. This allows you to monitor this point while
swapping to the other displays
42
The tag name for the point is shown in the first line of the popup. The
second line shows the value of interest for the point. The third line shows the
value of measure
43
9 BEM: IOP371: Bus Extender module
44
FIELD WIRING FOR COMMON RTD MODULE
2. THERMOCOUPLE:
It is also a temperature detecting equipment which works on the
principle of Thermo electric effect or Seebeck effect. According to this
principle, when two junctions of two metals are kept at different
temperatures some emf will be induced across these junctions. Mostly nickel
chromium metal junction is being used. One junction is called cold junction
and another is called hot junction.
Cold junction is made inside the CJB with the particular equipment and cold
junction temperature will be measured by an RTD and transmitted to DCS.
45
Special Nickel-Chromium cable, called as compensating cable is used to
connect the thermocouple to the CJB. This unit may require 24 V dc supply
or 240V AC in our plant.
3. PT (Pressure Transmitter):
A pressure transmitter is a device which generates 4-20mA output
based on the pressure applied. Input may be 24Vdc or 110Vac or 230Vac.
We are using 24V dc power supply. There are three types of these based on
its electrical connections.
They are:
1. 2-wire
2. 3-wire
3. 4-wire
It works on the basic fact that variable capacitance can be achieved by
changing the distance between the plates of a parallel plate capacitor.
4. Auma Actuators
Calibration of Auma actuators feedback (4-20mA) to DCS using the
provided rheostats for zero adjustment and Max adjustment.
Adjustment of limit switches arrangement.
5 SOV (Solenoid Operated Valve):
These are the types of valves which are operated with help of air. Mainly
3 or4 kg of air is required for the proper operation of the valve.
46
Operation of valve (manual also), path of the pressurized air.
Regulating the air pressure.
Limit switches arrangement adjustment.
The solenoid used in these types of valves mainly uses 110V AC
47