Process Sub-process
Project Department
functional Structure
Budget Revisions
Issue of RFP
Receiving of Bids
Receiving of Margin
money / bid security
amount
Costing validation
Vendor Assessment /
Evaluation and selection
Bank Guarantees
Insurance
6 Fixed Asset Capitalization & Asset Capitalization
Depreciation Accounting
Defects liability
Feasibility Study
Quality Control
Access Control
Sub-contracting
Risk
Level 1
a. Check if there is a project SOP in place , duly updated in
line with current practices and approved by the Board of
Directors / DOA.
Level 2
Prepare a checklist and ensure compliance to the key provisions of SOP
Ensure that :-
- Person responsible for project procurement activity or directly dealing with vendors are not
involved in accounting / transactions posting in Books or have access to master data
- there is cross functional committee to evaluate bids / select vendor
Check if such revisions have been correctly reflected in the MIS / project monitoring template
- Understand / ask the basis of identifying the vendors being invited for submitting bids and also
for rejecting the ones not shortlisted for bidding
- Check if any standard parameters (such as size of company / number of years into the
market, market reputation , global presence, etc.) were used for shortlisting the parties
identified
Check if RFP included the following parameters at the minimum to facilitate submission of
standard bids by the vendors:
- Project overview
- vendor pre-qualification parameters
- Margin money / bid security money required
- Estimated size of project and value etc
Check if all the bid opening details (e.g. vendor, date of receipt of bid, total quote amount etc),
are captured in the bid opening form and signed off by the bid opening committee
Check if the margin money has been returned post completion of selection process and
acknowledgement of the same has been obtained
Obtain detailed cost sheets / BOQ for shortlisted vendor and check whether all the elements of
cost were accurately considered in the cost :-
- Materials (ensure that material measurement standards have been specified to ascertain the
cost of material, rates for commodity can be checked through market rates)
- Manpower (ensure mandays for each activity and rates are specified)
- Freight cost (ensure no double computation e.g. included in material cost and considered
separately also)
- Taxes (as per applicable rates per law)
- Scrap realization value (deduction basis standard scrap ratio)
Check if the following parameters have been considered in the evaluation process at the
minimum :-
Technical Criteria:-
- Financial Strength (current turnover, assets base etc)
- Relevant previous experience
- previous performance experience with the company (if any)
- restrictions / reservation in the bid submitted
- Reference check results
- Results of visit to vendor facility
Commercial Criteria :
- Bid value
- payment terms including credit period etc.
- penalty terms on SLAs (e.g. accetance of penalty clauses for delay in completion etc)
Check if the following terms (at the minimum) have been included as part of the contract :-
- Payment terms
- SLAs
- Warranty as to quality & Structural Warranty & Asset componenet wise Warantee
• Passing of risks and title in the materials brought to the site
• Responsibility / penalty for late completion
• Mode of payment
• Liability for contractor’s labour (e.g.Pension, Overtime, etc.)
• Applicability of Local Labour Laws
• Mode of settlement of disputes
• Jurisdiction of courts
- Sub-contracting not permitted without pre-approval
• Company’s entitlement to inspect/ audit the contractor’s materials and records
• Periodic or final technical audit by the company
- Retention money
- Performance Bank guarantee
For duplicate vendor codes, check if both the codes have been used and if dual payments and
outstanding are reflecting in the ledger accounts.
For vendors with missing mandatory details, select a sample and review customer addition
forms and selection documents to check for authenticity and existence of such customers.
Select a sample of top 10 vendors and check if the contracts are in force for existing parties If
the work has not been completed.
Select a sample of 10 top contractors including civil contract to check if the following types of
Bank guarantees have been collected:-
- Bank guarantee for Advance payment
- Performance Bank guarantee (post completion of work upto defects liability period)
- Check If such Bank Guarantees have been collected for correct value as per terms of contract
- Ensure that bank guarantees are unconditional and irrevocable
- Ensure bank guarantees are in force if the related work / condition has not completed.
*The following associated costs, which are normally incurred while purchasing any fixed asset,
should be capitalized, along with the cost of asset (i.e. the suppliers invoice price net of all
discounts/ commission):
• All non-refundable duties and taxes such as excise duty, custom duty, sales tax, octroi, (net of
Cenvat / Modvat credit and Sales Tax set off)
• Cost of site preparation
• Freight, loading, unloading and handling costs
• Cost of foundation, installation and commissioning
• Costs of fees and expenses incurred for professional services used such as architects,
engineers, surveyors
• Cost of foreign exchange, forward contract and variation in the foreign exchange rates
relating to borrowings specifically obtained for procuring fixed assets
• All other costs, which are directly attributable to the purchase of fixed assets e.g. In case of
land, if the cost of an advertisement for ensuring clear title, etc.; the same is added to the cost
of land.
• Ensure that interest and other financing costs such as bank charges, stamp duty/paper
charges paid for loan agreements with the financier, documentation charges, commitment
charges etc. Have been capitalized along with the respective fixed asset, if such borrowings
are specifically identifiable with and earmarked for a particular asset or assets and such assets
are qualifying assets in terms of AS-16
• Ensure that expenditure incurred on interest and commitment charges on loans upto the date
of completion and commissioning of the project have been capitalized.
Compare project budget with actual cost on the project for each line item and ascertain
instances of under spend compared to budget.
Discuss and understand reasons for the under spending and check if such costs were not
allocated on the project and charged off as expenses
Select a sample of 25 assets (mix of capitalized and CWIP assets) and perform physical
verification. Ensure the following are checked :-
- Condition of the asset
- matching of asset number / tag
- status of asset (in use / not in use)
- location of the asset
Check how project department and consultant ensure compliances to statutory requirements by
the the company and contractors ?
Check whether records of project completion tests are properly documented ( info such as
Plant, Manufacture reference number, validity of testing equipments, qualification of tester) and
certificates of tests are received by the Company.
Ensure that consultant has certified that all the requiements of the contract has been complied
by contracor and equipments loaned to contractors have been recovered and deposited to the
company .
Check if maintenance work expense (check through expense ledger) post completion of project
during defects libility period whether being recovered from contractor as per terms of contract ?
If contractor is responsible, ensure that the same has been deducted from / factored into the
costing agreed with the contractor.
Check through review of expense ledgers if company has incurred any scrap disposal cost
which should have been debited to the contractor.
Check if approval as per DOA (generally Board of Directors) is available for concept and overall
investment that company intends to make into the project
Review Financial & Technical feasibility study for accuracy, completeness and relevance.
Review Technical Feasibility study for the coverage / consideration on the following elements:-
- Availability of required resources for the project at the location being proposed (e.g.
electricity / water / labour supply , roads / connectivity etc)
- Availability of know-how for the project implementation
- Key challenges in implementation of project
- Expected timelines for the project
- Geo-political scenario
- Project plan overview
Check if a cash / fund flow statement has been prepared for duration of the project to ensure
consistent flow of cash to fund the project .
Check if such cash / fund flow statement is being revised periodically basis actual scenario.
Obtain quality control procedures of the company / as agreed with the contractor(s) and
understand types of quality checks to be performed.
Select sample days , materials and sections and obtain quality check reports and Check
- If such reports are available
- if such reports include specifications as per agreed specifications in the BOQ or quality control
procedures.
- If these have been reviewed and signoff by quality auditor / technical engineer
(Quality control checks on project include brick strength test, structural strength test etc.)
Ascertain if there have been any incidents on the project (through discussions and project
MIS), if so check the reasons and if corrective action was taken against the same.
Check security register to review outward movements of assets / equipments and select
samples to obtain authorizations for the same.
Ensure that company is not incurring any additional cost on account of appointment of sub-
contractor by the contractor (unless specifically agreed and approved as per DOA)
Applicability (Yes/No)
Level 3
If no updated SOP is available, obtain detailed understanding /
walkthrough of the process followed and summarize as part of audit
planning document.
Check if budgets are fed into the financial system and control exists to
prevent expense booking in excess of budget
- seek justification for the same from the process owner and assess
reasonableness
Make cold calls (as imaginary party) and perform web search to verify
existence of the bidders.
Also, pick contracts for related nature of work of different vendors and
ensure that money is not being paid for same service performed by the
different vendors (i.e. there should not be a duplication of service
between 2 contractors)
Check if all the negotiations have been documented and signed off by
the bid evaluation committee and if the selection has been approved as
per the DOA.
Check if the following types of common costs have been identified and
appropriately allocated on the project for capitalization / amortization over
a period:-
- Management time spent on the project
- Corporate overheads
- Pre-operative expenses
Check If there is a process to identify root causes and action plan for
exceeding budget .
Ensure that root causing performed identifies the responsibility for the
variance. If the responsibility lies with the contractor / service provider ,
the variance / excess cost needs to be debited to the contractor.
Ensure that root causing performed identifies the responsibility for the
variance. If the responsibility lies with the contractor / service provider ,
the variance / excess cost needs to be debited to the contractor.
Perform a visit to the project site and perform general inspections and
ascertain deviations .
Level 1
Project / Capex SOP / Startegy
Document
- Organization / Functional
Structure
- Employee Job description
- System access rights matrix
- Budget Revisions
- Project MIS
Vendor Identification Tracker for
sending RFP
RFP Document
Bid opening document
- Bids
- Comparative evaluation
- Negotiation summary
- Vendor Master
- Vendor addition form and
supporting documentation
- Bank Guarantees
- Expense ledger
- Project Budget
- Vendor contract
- Scrap standards
- Scrap sales ledger
- Scrap Vendor ledger
- Scrap register
- Scrap invoices
- Scrap disposal expense ledger
- Scrap disposal approvals
- Project MIS
- PO Dump
- Project Cost centre
- GRN and SRN Dump
- Expense Ledgers
- Project MIS
- Progress bills
- sub-contractor appointment
approvals
Exceptions Noted Cause Working paper
ref
Level 2 Level 3 People/Process/Technology