Anda di halaman 1dari 2

SOUTH DHAHRAN HOME OWNERSHIP PROECT (SDHOP), DISTRICT 1 Rev.

02

AZMEEL INSPECTION & TEST PLAN AZITP No. APPROVED DATE DISCIPLINE:

Concrete Works(Cast-In-Place Portland Cement and Precast Concrete) AZITP-Q-03 CIVIL


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

28-00013
SOUTH DHAHRAN HOME OWNERSHIP PROJECT (SDHOP), DISTRICT 1 AZMEEL CONTRACTING CO.
28-10005

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD
CNTRCTR SDHOP

1.0 DOCUMENT REVIEW

Contractor - "RH" of Documents and "H" for Material


Sampling and Testing during mix design preparation
Raw Materials Sampling, Testing & stage.
1.1
Concrete Mix Design Approval
AZIC-Q-1001 AZIC-Q-1001 RH/H RH/H SDHOP - "RH" of Documents and "H" for Material
Sampling and Testing during mix design preparation
stage.

Sch Q Para Contractor/SDHOP - RH of Documents.


1.2 IFC/Shop Drawings Approval Sch Q Para 3.2
3.2
RH RH Procedure requires approval prior to start of work.

2.0 RECEIVING INSPECTION

Epoxy coated /uncoated Steel


2.1 Reinforcement and Embedded Items AZIC-Q-1002 AZIC-Q-1002 H W Provide Material Test Report for each item.
Receiving Inspection

Handling, Storage & Preservation of Contractor QC - Witness every inspection request.


2.2 Epoxy coated/uncoated Steel AZIC-Q-1003 AZIC-Q-1003 W S SDHOP - Witness first 3 delivery and once every 6
Reinforcement occurrences.

3.0 INSTALLATION

Cast-In-Place Concrete Grade & Site


3.1
Preparation
AZIC-Q-1004 AZIC-Q-1004 W W Provide Survey Report

Cast-In-Place & Precast Concrete


3.2
Formwork Inspection
AZIC-Q-1005 AZIC-Q-1005 W W Provide Survey Report (for cast-in-place concrete)

Epoxy coated/uncoated Reinforcing


3.3 Steel Reinforcement, Embedded Items, AZIC-Q-1006 AZIC-Q-1006 H H
and Form Closure Inspection

Page 1 of 2
SOUTH DHAHRAN HOME OWNERSHIP PROECT (SDHOP), DISTRICT 1 Rev.02

AZMEEL INSPECTION & TEST PLAN AZITP No. APPROVED DATE DISCIPLINE:

Concrete Works(Cast-In-Place Portland Cement and Precast Concrete) AZITP-Q-03 CIVIL


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

28-00013
SOUTH DHAHRAN HOME OWNERSHIP PROJECT (SDHOP), DISTRICT 1 AZMEEL CONTRACTING CO.
28-10005

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD
CNTRCTR SDHOP

Concrete Sampling, Testing & Placement


3.4
Inspection
AZIC-Q-1010 AZIC-Q-1010 W W Provide Concrete Pouring Log per each day of pouring

Contractor QC - Witness every inspection request.


3.5 Concrete Finishing and Curing Inspection AZIC-Q-1007 AZIC-Q-1007 W S SDHOP - Witness first 3 occurences and once every 10
occurrences, thereafter.

Contractor QC - Witness every inspection request.


3.6 Concrete Formwork Stripping Inspection AZIC-Q-1008 AZIC-Q-1008 W S SDHOP - Witness first 3 occurences and once every 10
occurrences, thereafter.

Concrete Compressive Strength Testing


3.7
and Final Acceptance Inspection
AZIC-Q-1009 AZIC-Q-1009 H W Provide applicable test reports

4.0 PRE-COMMISSIONING

4.1 Not applicable

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by SDHOP Site Inspection Personnel. After this period, SDHOP Inspection may adjust the levels of
1 SDHOP participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
4 attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to SDHOP.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection