IMPROVEMENT OF BUBONG MULTI-PURPOSE BUILDING

Barangay Bubong, Kolambugan, Lanao del Norte

BILL OF MATERIALS AND COST ESTIMATES

I. FABRICATION OF DOOR GRILLS

A. Materials;

8 Length 1 1/4'' Ф G.I. Pipe S-40 x 6.00m P 1,275.00 P 10,200.00


16 Length 1'' x1'' 3/16'' Angle Bar x6.00m. P 315.00 P 5,040.00
42 Length 10mm Square Bar 195.00 8,190.00
6 Kls #11 Fujiweld Welding Electrodes 145.00 870.00
6 pcs 4''ф cutting disc 85.00 510.00
2 pcs 4''ф grinding disc 115.00 230.00
3 gal Enamel Paint (Black) 485.00 1,455.00
3 gal Red Lead Primere 465.00 1,395.00
4 lit Paint Thinner 415.00 1,660.00
2 pcs #1'' Paint Brush 65.00 130.00
12 pcs #120cc Sand Paper 36.00 432.00
30,112.00

B. Labor; 35% 10,539.20

C. Hauling of Materials 5% 1,505.60

D. Equipment Rental

10 days Welding Machine P 350.00 P 3,500.00


10 days Electric Baby Grinder P 150.00 P 1,500.00

TOTAL P 47,156.80

C. Unit Cost 50,000.00 Lot


19 Linear Meter

SUMMARY

A. MATERIALS - -- - -- - - - - - - - - - - - - - - - - - - P 30,112.00

B. LAB O R ; 35% 10,539.20

C. HAULING OF MATERIALS 5% 1,505.60

D. EQUIPMENT RENTAL 5,000.00

E. CONTINGENCY 2,843.20

TOTAL ESTIMATED PROJECT COST P 50,000.00