B.E.(Mechanical Engineering) Semester Seventh (C.B.S.)


Industrial Engineering
P. Pages : 2 KNT/KW/16/7467
Time : Three Hours *0868* Max. Marks : 80
_____________________________________________________________________
Notes : 1. All questions carry marks as indicated.
2. Solve Question 1 OR Questions No. 2.
3. Solve Question 3 OR Questions No. 4.
4. Solve Question 5 OR Questions No. 6.
5. Solve Question 7 OR Questions No. 8.
6. Solve Question 9 OR Questions No. 10.
7. Solve Question 11 OR Questions No. 12.
8. Due credit will be given to neatness and adequate dimensions.
9. Use of design data book is permitted.

om
1. a) Explain the various tools & techniques to improve productivity. 8

e.c
lin
b) What is productivity and what is its relationship with production.

on
6

nu
m
OR
.rt
w
w
2. a) Define method study. What are its objectives? Differentiate between work measurement 8
w

& method study.

b) Define work study. What are the components of work study. 6

3. a) What are allowances in work measurement study? Explain the various types of allowances 7
in work measurement.
om
e.c

b) Define work sampling? Why is work sampling important? 6


lin
on
nu

OR
m
.rt

4. a) What are the principles of motion economy? 7


w
w
w

b) What is ergonomics? What are its objectives? How ergonomics is related to work place 6
design.

5. a) Explain various forecasting Techniques. 7

b) The past data on the load on weaving m/c is shown below. 6


Mon May-14 Jun-14 July-14 Aug-14 Sept-14 Oct-14 Nov-14
Load (HRS) - 585 610 675 750 860 970

i) Compute the load on the weaving m/c. Using 5th moving average for the month of
December-14
ii) Compute a weighted three months moving average for December-14 where weights
are 0.5 for the latest month, 0.3,0.2 for other months respectively.

OR

KNT/KW/16/7467 1 P.T.O

www.rtmnuonline.com
www.rtmnuonline.com

6. a) What is forecasting? How is it different from prediction? What is the need for demand 6
forecasting?

b) Demand for a part is given below: The forecast for April 97 was 100 units. Forecast the 7
demand for July 1997 taking the value of   0.2

7. a) What is maintenance? Explain the various types of maintenance with examples. 7

b) Explain Reliability, Maintainability & Availability in detail giving suitable example. 6

OR

8. a) Explain the various stages of failure analysis. Also explain what is bath tub curve with a 7
neat sketch.

b) Calculate the reliability of following component if all components are parallel & series. 6
R1  0.8, R 2  0.85, R 3  0.65, R 4  0.9, R 5  0.56, R 6  0.72

om
e.c
9. a) What is quality? What do you understand by quality control? What are the various 6

lin
objectives of quality control?

on
nu
m
b) What is process capability? Explain operating characteristic (OC) curve with a neat 7

.rt
sketch. w
w
w

OR

10. a) Control charts of X and R are maintained to control an important dimension of a 7


component. The sub group size is settled as 5. The values of X and R computed for each
subgroup and the values of X and R are computed for each subgroup and the value of
om

X and R after 25 subgroups are found to be 614.8 and 120.0 respectively. Compute
e.c

3 (3 sigma) limits for X chart. Assume R = 2.326 


lin
on

b) What is acceptance sampling? Explain the types of Acceptance sampling in brief. 6


nu
m
.rt

11. a) Explain the following in detail. 6


w

i) Quality Assurance. ii) Quality planning. iii) Quality a Audit.


w
w

b) What is TQM. Explain the principles of TQM. 4

c) Explain the philosophy of six sigma in brief. 4

OR

12. a) Explain various approaches to quality improvement. 5

b) What is vendor quality rating an what basis is a vendor rated. 5

c) Write a short note on ISO 9000. 4

*************