Anda di halaman 1dari 24

No.

Uraian Volume Satuan Harga Satuan


A PEKERJAAN BONGKARAN
1. Bongkar Dinding Partisi eksisting 64.86 m2 30,000.00
3. Bongkar Pintu Eksisting 1.00 Unit 76,000.00
3. Bongkar Wallpaper 29.25 m2 15,000.00
4. Pembuangan Bongkaran 1.00 Ls 1,200,000.00
SUBTOTAL A
B PEKERJAAN PEMASANGAN
1. Pemasangan Dinding Partisi Gypsum 2 sisi +
Rangka Hollow 4/4 2/2 66.73 m2 245,000.00
2. Pemasangan Wallpaper 162.75 m2 185,000.00
3. Pasang Kusen Allumunium Baru 12.00 m2 245,000.00
4. Pasang Kusen Allumunium Lama 22.95 m2 48,000.00
5. Pasang Kaca Baru 2.25 m2 556,000.00
6. Pasang Kaca Lama 5.89 m2 136,000.00
7. Pasang Kaca Sunglass 17.60 m2 155,000.00
8. Pasang Kusen Kayu Lapis HPL 2.00 Unit 1,200,000.00
9. Pasang Kusen Kayu Lama 1.00 Unit 280,000.00
10. Pasang Kunci 1.00 Unit 228,000.00
11. Pemasangan Pintu baru 2.00 Unit 3,300,000.00
12. Pemasangan Pintu Folding Gate Kayu 6.00 Unit 2,668,000.00
13. Pasang partisi HPL 3.36 m' 566,000.00
14. Plint Atas Bawah 92.00 m' 65,000.00
SUBTOTAL B
D. JUMLAH
E. PPN 10%

F. TOTAL JUMLAH
dibulatkan
Jumlah Harga

1,945,800.00
76,000.00
438,750.00 15000
1,200,000.00
3,660,550.00

16,348,850.00 9.81
30,108,750.00 230000
2,940,000.00
1,101,600.00
1,251,000.00 120000
801,040.00
2,728,000.00
2,400,000.00 800000
280,000.00
228,000.00
6,600,000.00 220 8800
16,008,000.00 40 17600
1,901,760.00
5,980,000.00 50000
88,677,000.00
92,337,550.00
9,233,755.00
101,571,305.00
101,571,300.00
A1 No. Uraian SATUAN KOEFISIEN HARGA
1. 2. 3. 4. 5.
1. Bongkar Dinding Partisi eksisting
A. Tenaga
Pekerja OH 0.2000 90,000.00
Mandor OH 0.0800 115,000.00
Jumlah Harga Tenaga
B. Bahan

Jumlah Harga Bahan


C. Peralatan
Alat bantu Ls 1.0000 2,800.00
Jumlah Harga Peralatan
D. Jumlah (A+B+C)
F. Total Harga Satuan Dibulatkan

A2 No. Uraian SATUAN KOEFISIEN HARGA


1. 2. 3. 4. 5.
1. Bongkar Pintu Eksisting
A. Tenaga
Pekerja OH 0.1000 90,000.00
Tukang OH 0.0800 105,000.00
Kepala Tukang OH 0.0100 100,000.00
Mandor OH 0.0050 115,000.00
Jumlah Harga Tenaga
B. Bahan

Jumlah Harga Bahan


C. Peralatan
Alat bantu Ls 1.0000 57,000.00
Jumlah Harga Peralatan
D. Jumlah (A+B+C)
F. Total Harga Satuan Dibulatkan

A3 No. Uraian SATUAN KOEFISIEN HARGA


1. 2. 3. 4. 5.
1. Bongkaran Wallpaper
A. Tenaga
Pekerja OH 0.1300 90,000.00
Mandor OH 0.0130 115,000.00
Jumlah Harga Tenaga
B. Bahan
Jumlah Harga Bahan
C. Peralatan
Alat bantu Ls 1.0000 1,800.00
Jumlah Harga Peralatan
D. Jumlah (A+B+C)
F. Total Harga Satuan Dibulatkan

B1 No. Uraian SATUAN KOEFISIEN HARGA


1. 2. 3. 4. 5.
1. Pemasangan Dinding Partisi Gypsum 2 sisi + Rangka Hollow 4/4 2/2
A. Tenaga
Pekerja OH 0.1150 90,000.00
Tukang OH 0.2500 105,000.00
Kepala Tukang OH 0.0050 100,000.00
Mandor OH 0.0050 115,000.00
Jumlah Harga Tenaga
B. Bahan
Hollow 4/4 btg 0.4150 145,500.00
Hollow 2/2 btg 0.1500 67,500.00
Gypsum board lbr 0.3640 98,000.00
Paku Gypsum kg 0.1100 30,000.00
Dynabolt bh 4.0000 2,000.00
Cotton plaster bh 0.0720 13,000.00
Compoun zak 0.1250 53,000.00
Jumlah Harga Bahan
C. Peralatan
Alat bantu Ls 1.0000 82,200.00
Jumlah Harga Peralatan
D. Jumlah (A+B+C)
F. Total Harga Satuan Dibulatkan

B2 No. Uraian SATUAN KOEFISIEN HARGA


1. 2. 3. 4. 5.
1. Pemasangan Wallpaper
A. Tenaga
Pekerja OH 0.3500 90,000.00
Tukang OH 0.1750 105,000.00
Kepala Tukang OH 0.0170 100,000.00
Mandor OH 0.0020 115,000.00
Jumlah Harga Tenaga
B. Bahan
Wallpaper m 2.2000 49,400.00
Lem Wallpaper Kg 0.2500 30,000.00
Jumlah Harga Bahan
C. Peralatan
Alat bantu Ls 1.00 17,000.00
Jumlah Harga Peralatan
D. Jumlah (A+B+C)
F. Total Harga Satuan Dibulatkan

B3 No. Uraian SATUAN KOEFISIEN HARGA


1. 2. 3. 4. 5.
1. Pasang Kusen Allumunium Baru
A. Tenaga
Pekerja OH 0.0430 90,000.00
Tukang OH 0.0430 105,000.00
Kepala Tukang OH 0.0043 100,000.00
Mandor OH 0.0021 115,000.00
Jumlah Harga Tenaga
B. Bahan
Profil Allumunium m' 1.1000 110,850.00
Skrup bh 2.0000 283.00
Sealent tube 0.0600 48,000.00

Jumlah Harga Bahan


C. Peralatan
Alat bantu Ls 1.0000 110,500.00
Jumlah Harga Peralatan
D. Jumlah (A+B+C)
F. Total Harga Satuan Dibulatkan

B4 No. Uraian SATUAN KOEFISIEN HARGA


1. 2. 3. 4. 5.
1. Pasang Kusen Allumunium Lama
A. Tenaga
Pekerja OH 0.0430 90,000.00
Tukang OH 0.0430 105,000.00
Kepala Tukang OH 0.0043 100,000.00
Mandor OH 0.0021 115,000.00
Jumlah Harga Tenaga
B. Bahan
Skrup bh 2.0000 16,700.00
Sealent tube 0.0600 48,000.00

Jumlah Harga Bahan


C. Peralatan
Alat bantu Ls 1.00 2,700.00
Jumlah Harga Peralatan
D. Jumlah (A+B+C)
F. Total Harga Satuan Dibulatkan

B5 No. Uraian SATUAN KOEFISIEN HARGA


1. 2. 3. 4. 5.
1. Pasang Kaca Baru
A. Tenaga
Pekerja OH 0.0150 90,000.00
Tukang OH 0.1500 105,000.00
Kepala Tukang OH 0.0150 100,000.00
Mandor OH 0.0008 115,000.00
Jumlah Harga Tenaga
B. Bahan
Kaca Tempered 12mm m2 1.1000 460,000.00
Jumlah Harga Bahan
C. Peralatan
Alat bantu Ls 1.00 31,400.00
Jumlah Harga Peralatan
D. Jumlah (A+B+C)
F. Total Harga Satuan Dibulatkan

B6 No. Uraian SATUAN KOEFISIEN HARGA


1. 2. 3. 4. 5.
1. Pasang Kaca Lama
A. Tenaga
Pekerja OH 0.0150 90,000.00
Tukang OH 0.1500 105,000.00
Kepala Tukang OH 0.1500 100,000.00
Mandor OH 0.0008 115,000.00
Jumlah Harga Tenaga
B. Bahan

Jumlah Harga Bahan


C. Peralatan
Alat bantu Ls 1.00 103,800.00
Jumlah Harga Peralatan
D. Jumlah (A+B+C)
F. Total Harga Satuan Dibulatkan

B7 No. Uraian SATUAN KOEFISIEN HARGA


1. 2. 3. 4. 5.
1. Pasang Kaca Sunglass
A. Tenaga
Pekerja OH 0.0150 90,000.00
Tukang OH 0.1500 105,000.00
Kepala Tukang OH 0.1500 100,000.00
Mandor OH 0.0001 115,000.00
Jumlah Harga Tenaga
B. Bahan
Stiker kaca sunglass m2 1.1000 60,000.00

Jumlah Harga Bahan


C. Peralatan
Alat bantu Ls 1.0000 56,900.00
Jumlah Harga Peralatan
D. Jumlah (A+B+C)
F. Total Harga Satuan Dibulatkan

B8 No. Uraian SATUAN KOEFISIEN HARGA


1. 2. 3. 4. 5.
1. Pasang Kusen Kayu Lapis HPL
A. Tenaga
Pekerja OH 0.6700 90,000.00
Tukang OH 2.0000 105,000.00
Kepala Tukang OH 0.2000 100,000.00
Mandor OH 0.0400 115,000.00
Jumlah Harga Tenaga
B. Bahan
Kusen kayu bh 1.1000 602,000.00
Paku 10cm bh 1.2500 16,700.00
Lem Kayu kg 1.0000 58,000.00
HPL Lbr 0.5000 116,000.00

Jumlah Harga Bahan


C. Peralatan
Alat bantu Ls 1.00 106,000.00
Jumlah Harga Peralatan
D. Jumlah (A+B+C)
F. Total Harga Satuan Dibulatkan

B9 No. Uraian SATUAN KOEFISIEN HARGA


1. 2. 3. 4. 5.
1. Pasang Kusen Kayu Lama
A. Tenaga
Pekerja OH 0.6700 90,000.00
Tukang OH 1.2000 105,000.00
Kepala Tukang OH 0.1000 100,000.00
Mandor OH 0.0400 115,000.00
Jumlah Harga Tenaga
B. Bahan
Paku 10cm kh 1.2500 16,700.00
Lem Kayu kg 1.0000 58,000.00
Jumlah Harga Bahan
C. Peralatan

Jumlah Harga Peralatan


D. Jumlah (A+B+C)
F. Total Harga Satuan Dibulatkan

B10 No. Uraian SATUAN KOEFISIEN HARGA


1. 2. 3. 4. 5.
1. Pasang Kunci
A. Tenaga
Pekerja OH 0.0600 90,000.00
Tukang OH 0.6000 105,000.00
Kepala Tukang OH 0.0600 100,000.00
Mandor OH 0.0300 115,000.00
Jumlah Harga Tenaga
B. Bahan
Kunci tanam bh 1.0000 125,000.00
Jumlah Harga Bahan
C. Peralatan
Alat bantu Ls 1.00 25,000.00
Jumlah Harga Peralatan
D. Jumlah (A+B+C)
F. Total Harga Satuan Dibulatkan

B11 No. Uraian SATUAN KOEFISIEN HARGA


1. 2. 3. 4. 5.
1. Pemasangan Pintu Baru
A. Tenaga
Pekerja OH 1.0000 90,000.00
Tukang OH 3.0000 105,000.00
Kepala Tukang OH 0.3000 100,000.00
Mandor OH 0.0500 115,000.00
Jumlah Harga Tenaga
B. Bahan
Papan kayu kelas I m3 0.0400 3,250,000.00
Lem kayu Kg 0.5000 58,000.00
Paku 3cm kg 0.0300 19,500.00
Plywood tebal 4mm lembar 1.0000 82,000.00
Jumlah Harga Bahan
C. Peralatan

Jumlah Harga Peralatan


D. Jumlah (A+B+C)
F. Total Harga Satuan Dibulatkan

B12 No. Uraian SATUAN KOEFISIEN HARGA


1. 2. 3. 4. 5.
1. Pemasangan Pintu Folding Gate Kayu
A. Tenaga
Pekerja OH 0.8000 90,000.00
Tukang OH 2.4000 105,000.00
Kepala Tukang OH 0.2160 100,000.00
Mandor OH 0.0360 115,000.00
Jumlah Harga Tenaga
B. Bahan
Pintu Lipat Unit 1.0000 1,880,000.00
Paku Kayu 10 cm Kg 0.5000 17,500.00
Jumlah Harga Bahan
C. Peralatan
Alat Bantu Ls 2.00 214,800.00
Jumlah Harga Peralatan
D. Jumlah (A+B+C)
F. Total Harga Satuan Dibulatkan

B13 No. Uraian SATUAN KOEFISIEN HARGA


1. 2. 3. 4. 5.
1. Pasang partisi HPL
A. Tenaga
Pekerja OH 0.8000 90,000.00
Tukang OH 2.5000 105,000.00
Kepala Tukang OH 0.2500 100,000.00
Mandor OH 0.0400 115,000.00
Jumlah Harga Tenaga
B. Bahan
Kayu kamper papan m3 0.0196 2,100,000.00
Paku biasa Kg 0.3000 16,700.00
Lem Kayu Lt 0.8000 20,870.00
Triplek tbl 4 mm Lbr 0.5000 53,850.00
HPL premium Lbr 0.5000 116,000.00
Jumlah Harga Bahan
C. Peralatan
Alat bantu Ls 1.0000 54,200.00
Jumlah Harga Peralatan
D. Jumlah (A+B+C)
F. Total Harga Satuan Dibulatkan

B14 No. Uraian SATUAN KOEFISIEN HARGA


1. 2. 3. 4. 5.
1. Plint Atas Bawah
A. Tenaga
Pekerja OH 0.1200 90,000.00
Tukang OH 0.1200 105,000.00
Kepala Tukang OH 0.0080 100,000.00
Mandor OH 0.0040 115,000.00
Jumlah Harga Tenaga
B. Bahan
Vinyl karet m3 1.7500 20,000.00
Lem vinyl Kg 0.0800 77,000.00
Jumlah Harga Bahan
C. Peralatan

Jumlah Harga Peralatan


D. Jumlah (A+B+C)
F. Total Harga Satuan Dibulatkan
JML HARGA
6.

18,000.00
9,200.00
27,200.00

2,800.00
2,800.00
30,000.00
30,000.00

JML HARGA
6.

9,000.00
8,400.00
1,000.00
575.00
18,975.00

57,000.00
57,000.00
75,975.00
76,000.00

JML HARGA
6.

11,700.00
1,495.00
13,195.00
1,800.00
1,800.00
14,995.00
15,000.00

JML HARGA
6.

10,350.00
26,250.00
500.00
575.00
37,675.00

60,382.50
10,125.00
35,672.00
3,300.00
8,000.00
936.00
6,625.00
125,040.50

82,200.00
82,200.00
244,915.50
245,000.00

JML HARGA
6.

31,500.00
18,375.00
1,700.00
230.00
51,805.00

108,680.00
7,500.00
116,180.00

17,000.00
17,000.00
184,985.00
185,000.00

JML HARGA
6.

3,870.00
4,515.00
430.00
241.50
9,056.50

121,935.00
566.00
2,880.00

125,381.00

110,500.00
110,500.00
244,937.50
245,000.00

JML HARGA
6.

3,870.00
4,515.00
430.00
241.50
9,056.50

33,400.00
2,880.00

36,280.00

2,700.00
2,700.00
48,036.50
48,000.00

JML HARGA
6.

1,350.00
15,750.00
1,500.00
86.25
18,686.25

506,000.00
506,000.00

31,400.00
31,400.00
556,086.25
556,000.00

JML HARGA
6.

1,350.00
15,750.00
15,000.00
86.25
32,186.25

103,800.00
103,800.00
135,986.25
136,000.00

JML HARGA
6.
1,350.00
15,750.00
15,000.00
11.50
32,111.50

66,000.00

66,000.00

56,900.00
56,900.00
155,011.50
155,000.00

JML HARGA
6.

60,300.00
210,000.00
20,000.00
4,600.00
294,900.00

662,200.00
20,875.00
58,000.00
58,000.00

799,075.00

106,000.00
106,000.00
1,199,975.00
1,200,000.00

JML HARGA
6.

60,300.00
126,000.00
10,000.00
4,600.00
200,900.00

20,875.00
58,000.00
78,875.00

279,775.00
280,000.00

JML HARGA
6.

5,400.00
63,000.00
6,000.00
3,450.00
77,850.00

125,000.00
125,000.00

25,000.00
25,000.00
227,850.00
228,000.00

JML HARGA
6.

90,000.00
315,000.00
30,000.00
5,750.00
440,750.00

130,000.00
29,000.00
585.00
82,000.00
241,585.00

682,335.00
3,300,000.00

JML HARGA
6.

72,000.00
252,000.00
21,600.00
4,140.00
349,740.00

1,880,000.00
8,750.00
1,888,750.00

429,600.00
429,600.00
2,668,090.00
2,668,000.00

JML HARGA
6.

72,000.00
262,500.00
25,000.00
4,600.00
364,100.00

41,160.00
5,010.00
16,696.00
26,925.00
58,000.00
147,791.00
54,200.00
54,200.00
566,091.00
566,000.00

JML HARGA
6.

10,800.00
12,600.00
800.00
460.00
24,660.00

35,000.00
6,160.00
41,160.00

65,820.00
65,000.00
DAFTAR HARGA SATUAN UPAH
HARGA UPAH
NO URAIAN SATUAN UPAH UPAH
ORANG/JAM ORANG/HARI

1 Mandor org/Hari/8 jam Rp 14,375.00 Rp 115,000.00


2 Kepala Tukang Batu org/Hari/8 jam Rp 13,125.00 Rp 105,000.00
3 Kepala Tukang Kayu org/Hari/8 jam Rp 13,125.00 Rp 105,000.00
4 KepalaTukang Besi/Alumunium org/Hari/8 jam Rp 13,125.00 Rp 105,000.00
5 Kepala Tukang Cat/Pelitur org/Hari/8 jam Rp 13,125.00 Rp 105,000.00
6 Kepala Tukang Listrik org/Hari/8 jam Rp 13,125.00 Rp 105,000.00
7 Tukang Batu org/Hari/8 jam Rp 12,500.00 Rp 100,000.00
8 Tukang Kayu org/Hari/8 jam Rp 12,500.00 Rp 100,000.00
9 Tukang Besi/Baja org/Hari/8 jam Rp 12,500.00 Rp 100,000.00
10 Tukang Alumunium org/Hari/8 jam Rp 12,500.00 Rp 100,000.00
11 Tukang Cat org/Hari/8 jam Rp 12,500.00 Rp 100,000.00
12 Tukang Listrik org/Hari/8 jam Rp 12,500.00 Rp 100,000.00
13 Tukang Pipa org/Hari/8 jam Rp 12,500.00 Rp 100,000.00
14 Tukang Plitur org/Hari/8 jam Rp 12,500.00 Rp 100,000.00
15 Tukang Taman org/Hari/8 jam Rp 12,500.00 Rp 100,000.00
16 Tukang org/Hari/8 jam Rp 12,500.00 Rp 100,000.00
17 Pembantu Tukang org/Hari/8 jam Rp 11,250.00 Rp 90,000.00
18 Pekerja Biasa org/Hari/8 jam Rp 11,250.00 Rp 90,000.00

DAFTAR HARGA SATUAN BAHAN

Hollow 40 x 40 x 2.00 mm btg 145,500.00 https://dekorrumah.net/harga-besi-h


Hollo2 20 x 20 x 1.70 mm btg 67,500.00 https://dekorrumah.net/harga-besi-h
Gypsum GRC / Versaboard 9.0 mm (1.20x2.40) lbr 98,000.00 http://cekhargabahan.com/harga-gy
Paku Gypsum 1" kg 30,000.00 https://www.bukalapak.com/p/ruma
Dynabolt bh 2,000.00 https://www.tokopedia.com/abs/dyn
Cotton plaster bh 13,000.00 https://www.tokopedia.com/gamajay
Compoun Gypsum Aplus (20kg) zak 53,000.00 https://www.tokopedia.com/cahayab
Wallpaper m 49,400.00 https://www.sejasa.com/blog/daftar
Lem Wallpaper Kg 30,000.00 https://www.tokopedia.com/mansio
Kusen alluminium 4" Superex 110,850.00 http://hargabangunanmurah.com/ha
Sekrup gypsum sunray 8x3 283.00 http://hargaper.com/harga-paku.htm
Harga Kaca Tempered 12mm 460,000.00 https://www.sejasa.com/blog/daftar
HPL ECO Woodgrain ECO P 042 116,000.00 https://bildeco.com/blog/daftar-harg
Balok kayu kelas II 1,750,000.00 http://www.tugumas.com/2016/08/
Paku 10cm 17500 http://hargaper.com/harga-paku.htm
Pintu Lipat kayu Type icyharmonic 1,615,000.00 http://pusatpintulipat.com/pricelist-h
Triplek 4mm 53,850.00 http://hargabangunanmurah.com/ha
Papan Kayu http://www.tugumas.com/2016/08/
Vinyl karet plank "Letto Deco" 20,000.00 https://arnidecor.com/daftar-produk
Lem vinyl Kg 77,000.00 https://www.tokopedia.com/perkaka
Kayu kamper papan 2,100,000.00 http://www.tugumas.com/2016/08/
Kayu papan kelas I
Paku 3cm 19,500.00 http://hargaper.com/harga-paku.htm
Kunci tanam 125,000.00 https://www.bukalapak.com/p/ruma
Stiker kaca sunglass 60,000.00 http://stikerkacamurah.com/
Lem kayu Kg 58000 http://www.lemkayu.net/ini-daftar-h
Kusen kayu 602,000.00 http://www.sari-jati.com/harga-kuse
Plywood tebal 4mm
dekorrumah.net/harga-besi-hollow-per-batang-semua-ukuran.html
dekorrumah.net/harga-besi-hollow-per-batang-semua-ukuran.html
ekhargabahan.com/harga-gypsum-dan-grc-terbaru/
www.bukalapak.com/p/rumah-tangga/perkakas-rumah-tangga/cniext-jual-paku-gypsum-1-inch?from=&product_owner=normal_seller
www.tokopedia.com/abs/dynabolt-10x80
www.tokopedia.com/gamajaya/fiber-tape-kasa-gypsum?gclid=CjwKCAjw85zdBRB6EiwAov3Riliosph-4MMl6l07UO1H7EuZJ-LECpSkIjSBLJjAc
www.tokopedia.com/cahayabarugroup/kompon-gypsumcompound-gypsum-a-plus-20-kg?gclid=CjwKCAjw85zdBRB6EiwAov3Rip458B5nJZx
www.sejasa.com/blog/daftar-harga-wallpaper-dinding-terbaru/
www.tokopedia.com/mansionwallpaper/lem-wallpaper?gclid=CjwKCAjw85zdBRB6EiwAov3RirjSyOwJ2l1JLzv0nUkXyFfWkq526SocnNRg_-Xv
argabangunanmurah.com/harga-kusen-aluminium-pintu-jendela/
argaper.com/harga-paku.html
www.sejasa.com/blog/daftar-harga-kaca-terbaru/
bildeco.com/blog/daftar-harga-hpl-maret-2018/
ww.tugumas.com/2016/08/harga-kayu-kelas-2.html
argaper.com/harga-paku.html
usatpintulipat.com/pricelist-harga-pintu-lipat-daftar-harga-penyekat-ruangan-partisi-peredam-suara/
argabangunanmurah.com/harga-triplek-multiplek/
ww.tugumas.com/2016/08/harga-kayu-kelas-2.html
arnidecor.com/daftar-produk-harga-lantai-vinyl?gclid=CjwKCAjw85zdBRB6EiwAov3RivH5nGQS7bQYAbkIE26IGCoHs-YzktiAIJADm3dv8B_Fp3
www.tokopedia.com/perkakaskucom/crona-lem-carpet-vinyl-1-kg?gclid=CjwKCAjw85zdBRB6EiwAov3RiqkTAxCEcL99ElHXjtr0usnBx4QoZ_4z
ww.tugumas.com/2016/08/harga-kayu-kelas-2.html

argaper.com/harga-paku.html
www.bukalapak.com/p/rumah-tangga/gembok-kunci-pengaman/buppw9-jual-grendel-tanam-slot-pintu-60cm-flushbolt?from=list-product
tikerkacamurah.com/
ww.lemkayu.net/ini-daftar-harga-lem-kayu-tahun-2016-176.html
ww.sari-jati.com/harga-kusen-kayu-murah.html
oduct_owner=normal_seller

6l07UO1H7EuZJ-LECpSkIjSBLJjAc2h3_4zywFRAehoChDwQAvD_BwE
85zdBRB6EiwAov3Rip458B5nJZxfh8WGIq36E-ND3QlzF1_iRjWc7pg_2y02IrQuOieyThoCo2AQAvD_BwE

v0nUkXyFfWkq526SocnNRg_-Xvtz3sf1ubjsYCYxoCgC8QAvD_BwE&m_id=417509
6IGCoHs-YzktiAIJADm3dv8B_Fp3ufLFG0LBoCtJUQAvD_BwE
AxCEcL99ElHXjtr0usnBx4QoZ_4z5owQwjlUAfqngbUoJfIDnBoCbmAQAvD_BwE

0cm-flushbolt?from=list-product&product_owner=normal_seller

Anda mungkin juga menyukai