PRINCE2®
Practitioner Training
PRINCE2: History
1996: PRINCE2:
PRojects IN Controlled
1989: PRINCE: Environments 2
PRojects IN Controlled
Environments
1975: PROMPTII:
Project Resource Organization Management
and Planning Techniques
1
8/4/17
vTarget Audience
This qualification is aimed at project managers and aspiring project managers. It is also
relevant to other key staff involved in the design, development and delivery of projects.
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
2
8/4/17
vTarget Audience
This qualification is aimed at project managers and aspiring project managers. It is also
relevant to other key staff involved in the design, development and delivery of projects.
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
PRINCE2: Introduction
vPRINCE2 (PRojects IN a Controlled Environment)
3
8/4/17
PRINCE2: Introduction
The Project
PROCESSES Environment
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
4
8/4/17
PRINCE2: 07 Principles
5
8/4/17
PRINCE2: 07 Principles
PRINCE2: 07 Principles
6
8/4/17
PRINCE2: 07 Principles
Continued business justification
• There is a justifiable reason to start it
• The justification should remain valid throughout the life of the project
• The justification is documented and approved
Manage by stages
• Dividing the project into a number of management stages
• Having a high-level Project Plan and a detailed Stage Plan
• Planning, delegating, monitoring and controlling the project on a stage-by-stage basis.
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
PRINCE2: 07 Principles
Manage by exception
• Delegating authority from one management level to the next by setting tolerances
against Time, Scope, Cost, Risks, Benefits, Quality
• Setting up controls so that if those tolerances are forecast to be exceeded, they are
immediately referred up to the next management layer
• Putting an assurance mechanism in place so that each management layer can be
confident that such controls are effective.
Focus on products
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
7
8/4/17
PRINCE2: 07 Themes
PRINCE2: 07 Themes
Business Case: Why?
Organization: Who?
Quality: What?
Plans: How? How much?
Themes
When?
Risk: What if?
8
8/4/17
PRINCE2: 07 Themes
Business Case: Why?
Organization: Who?
Quality: What?
Plans: How? How much?
Themes
When?
Risk: What if?
9
8/4/17
on estimated costs, risks and the expected vOutcome is the result of the change
benefits. derived from using the project’s outputs
Purpose (Why?):
vBenefit is the measurable improvement
üMechanisms to judge whether the project resulting from an outcome.
is (and remains) viable and achievable,
vDis-benefit is an outcome perceived as
therefore worthwhile investing in. negative by one or more stakeholders.
When?
üThe Business Case is developed at the
Benefits Review Plan is used to define
beginning of the project. how and when a measurement of the
üFormally verified by the Project Board at achievement of the project’s benefits can be
made.
each key decision points (stages).
10
8/4/17
Develop:
•At the beginning of the project
•Getting the right information upon which decisions can be made
Verify:
•Throughout the life of the project
•Assessing whether the project is (still) worthwhile
Maintain:
•By the Project Board at each key decision point
•To update the Business Case with actual costs and benefits and current forecasts for costs
and benefits
Confirm:
•Throughout the period as the benefits accrue
•Assessing whether the intended benefits have been (or will be) realized. Confirming
benefits will mostly take place post project
Executive: Responsible for the Business Case for the duration of the project.
Project Manager: Prepares the Business Case on behalf of the Executive.
11
8/4/17
12
8/4/17
PRINCE2: 07 Themes
Business Case: Why?
Organization: Who?
Quality: What?
Plans: How? How much?
Themes
When?
Risk: What if?
Copyright © AXELOS Limited 2009. Material is reproduced under licence from AXELOS. Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
13
8/4/17
Directing
Managing
Delivering
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
14
8/4/17
•Introduction
•Communication procedure •Timing of communication
Senior User
•The role represents the interests of all those who will use the project’s products (including
operations and maintenance)
•Provide the customer’s quality expectations and define acceptance criteria
•Ensure that the project produces products that will deliver the desired outcomes, and meet
•user requirements
•Resolve user requirements and priority conflicts
•Undertake Project Assurance from the user perspective
15
8/4/17
Role Responsibilities
Corporate or Appoint the Executive and (possibly) the Project Manager.
programme Provide information to the project as defined in the Communication
management Management Strategy.
Appoint the Project Manager (if not done by corporate or programme
management).
Executive Confirm the appointments to the project management team and the
structure of the project management team.
Approve the Communication Management Strategy.
16
8/4/17
Project Support Provide administrative support for the project management team.
PRINCE2: 07 Themes
Business Case: Why?
Organization: Who?
Quality: What?
Plans: How? How much?
Themes
When?
Risk: What if?
17
8/4/17
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
18
8/4/17
19
8/4/17
20
8/4/17
PRINCE2: 07 Themes
Business Case: Why?
Organization: Who?
Quality: What?
Plans: How? How much?
Themes
When?
Risk: What if?
21
8/4/17
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
Exception Plans:
3 levels of plan: üPrepared for the appropriate management level to show
1. Project Plan the actions required to recover from the effect of a tolerance
2. Stage plans deviation.
üIf approved, the Exception Plan will replace the plan that is
3. Team plans in exception
22
8/4/17
23
8/4/17
24
8/4/17
25
8/4/17
26
8/4/17
PRINCE2: 07 Themes
Business Case: Why?
Organization: Who?
Quality: What?
Plans: How? How much?
Themes
When?
Risk: What if?
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
27
8/4/17
sum of money included within the project budget and set aside to fund specific management
Risk budget responses to the project’s risks
Risk owner Responsible for the management, monitoring and control of all aspects of a particular risk
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
28
8/4/17
Identify
Communicate
Implement Assess
Plan
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
•Risk owner
•Risk actionee
29
8/4/17
Project Support Assist the Project Manager in maintaining the project’s Risk Register.
30
8/4/17
PRINCE2: 07 Themes
Business Case: Why?
Organization: Who?
Quality: What?
Plans: How? How much?
Themes
When?
Risk: What if?
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
31
8/4/17
Issue: It can be a concern, query, request for change, suggestion or off specification raised during a
project.
Configuration Management Strategy: Defines the configuration management procedure, issue and change
control procedure, tools and techniques to use, records keeping, roles and responsibilities of configuration
management
Configuration Item (CI) Record: Provides a set of information such as the status, version and variant of
each configuration item and any details of important relationships between them.
Product Status Account: provide information about the state of the products within defined limits.
Issue Register: Issue Register captures and maintains information on all of the issues that are being
managed formally.
Issue Report: a report containing the description, impact assessment and recommendations for an issue
that need to handled formally.
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
Copyright © AXELOS Limited 2009. Material is reproduced under licence from AXELOS.
32
8/4/17
•Planning: Deciding what level of configuration management will be required and planning
how this level is to be achieved.
•Identification: Specifying and identifying all components of the project’s products (known as
configuration items) at the required level of control.
•Control: The ability to approve and baseline products and to make changes only with the
agreement of appropriate authorities.
•Status accounting: The reporting of all current and historical data concerning each product in
the form of a Product Status Account.
•Verification and audit: A series of reviews and configuration audits to compare the actual
status of all products against the authorized state of products as registered in the
Configuration Item Records.
33
8/4/17
34
8/4/17
PRINCE2: 07 Themes
Business Case: Why?
Organization: Who?
Quality: What?
Plans: How? How much?
Themes
When?
Risk: What if?
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
35
8/4/17
Event-driven controls: Take place when a specific event occurs (include organizational events that might
affect the project
Daily Log: used to record informal issues, required actions or significant events not caught by other
PRINCE2 registers or logs
Lessons Log: A project repository for lessons that apply to this project or future projects
Work Package: A set of information about one or more required products collated by the Project Manager
passed to a Team Manager or team member for work or delivery.
End Project Report: used during project closure to review how the project performed
End Stage Report: used to give a summary of progress to date, the overall project situation, and sufficient
information for a Project Board to decision on what to do next.
Lessons Report: used to pass on any lessons that can be usefully applied to other projects
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
Exception Report: produced when a Stage Plan or Project Plan is forecast to exceed tolerance levels set.
Highlight Report: used to provide the Project Board (and possibly other stakeholders) with a summary of
the stage status at intervals defined by them.
36
8/4/17
Project Board
Stage
tolerances Stage
exceptions
Project Manager
Work Packages
tolerances Work Packages
exceptions
Team Manager
37
8/4/17
38
8/4/17
PRINCE2:Processes
07
Processes
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
39
8/4/17
PRINCE2:Processes
PRINCE2 is a process-based approach for project management
PRINCE2:Processes
PRINCE2 is a process-based approach for project management
Initiation Final
Pre-Project Subsequent Stages Delivery
Stage Stage
Directing a Project
Directing
SU
SB SB CP
Managing Controlling a
IP Controlling a Stage Stage
SU = Starting up a Project
IP = Initiating a Project
SB = Managing a Stage Boundary
CP = Closing a Project Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
40
8/4/17
PRINCE2:Processes
PRINCE2 process model
Purpose Objective Context Activities
Activities
Activities
Actions
Actions
Actions
PRINCE2:Processes
Starting Up a Project
Initiation Final
Pre-Project Subsequent Stages Delivery
Stage Stage
Directing a Project
Directing
SU
SB SB CP
Managing Controlling a
IP Controlling a Stage Stage
SU = Starting up a Project
IP = Initiating a Project
SB = Managing a Stage Boundary
CP = Closing a Project Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
41
8/4/17
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
CONTEXT:
vPRINCE2 calls the trigger for a project as project mandate.
vDuring SU process board must have enough information to make the decision to initiate the
Project.
vThis this time the outline Business case & Project Brief are assembled.
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
42
8/4/17
43
8/4/17
•Project definition
•Outline Business Case
•Project Product Description
•Project approach
•Project management team structure
•Role descriptions
• References To any associated documents or products
44
8/4/17
PRINCE2:Processes
Directing a Project
Initiation Final
Pre-Project Subsequent Stages Delivery
Stage Stage
Directing a Project
Directing
SU
SB SB CP
Managing Controlling a
IP Controlling a Stage Stage
SU = Starting up a Project
IP = Initiating a Project
SB = Managing a Stage Boundary
CP = Closing a Project Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
45
8/4/17
OBJECTIVE:
vTo Ensure there is authority to initiate the project
vMaking sure there is authority to deliver the project’s products
vManagement direction provided throughout the project and that the project remains viable
vCorporate or programme management has an interface to the project
vThere is authority to close the project
vPlans for realizing the post-project benefits are managed and reviewed.
CONTEXT:
vIt does not cover the day-to-day activities of the Project Manager. It is for project board.
vThe Project Board manages by exception. It monitors via reports and controls through a
small number of decision points
vThis process provides a mechanism for the Project Board to achieve such assurance without
being overburdened by project activity
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
46
8/4/17
•Project definition
•Outline Business Case
•Project Product Description
•Project approach
•Project management team structure
•Role descriptions
• References To any associated documents or products
47
8/4/17
PRINCE2:Processes
Directing a Project
Initiation Final
Pre-Project Subsequent Stages Delivery
Stage Stage
Directing a Project
Directing
SU
SB SB CP
Managing Controlling a
IP Controlling a Stage Stage
SU = Starting up a Project
IP = Initiating a Project
SB = Managing a Stage Boundary
CP = Closing a Project Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
OBJECTIVE:
vTo Ensure there is authority to initiate the project
vMaking sure there is authority to deliver the project’s products
vManagement direction provided throughout the project and that the project remains viable
vCorporate or programme management has an interface to the project
vThere is authority to close the project
vPlans for realizing the post-project benefits are managed and reviewed.
CONTEXT:
vIt does not cover the day-to-day activities of the Project Manager. It is for project board.
vThe Project Board manages by exception. It monitors via reports and controls through a
small number of decision points
vThis process provides a mechanism for the Project Board to achieve such assurance without
being overburdened by project activity
48
8/4/17
Authorize initiation
•Review and approve the Project Brief
•Review and approve the Project Product Description
•Verify that the outline Business Case demonstrates a viable project
•Review and approve the Stage Plan for the initiation stage
•Inform all stakeholders the project is being initiated
•Authorize the Project Manager to proceed with the initiation stage.
49
8/4/17
PRINCE2:Processes
Initiating a Project
Initiation Final
Pre-Project Subsequent Stages Delivery
Stage Stage
Directing a Project
Directing
SU
SB SB CP
Managing Controlling a
IP Controlling a Stage Stage
SU = Starting up a Project
IP = Initiating a Project
SB = Managing a Stage Boundary
CP = Closing a Project Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
50
8/4/17
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
51
8/4/17
52
8/4/17
53
8/4/17
Business Case
Role descriptions
Project Plan
Project controls
Tailoring of PRINCE2
54
8/4/17
PRINCE2:Processes
Controlling a Stage
Initiation Final
Pre-Project Subsequent Stages Delivery
Stage Stage
Directing a Project
Directing
SU
SB SB CP
Managing Controlling a
IP Controlling a Stage Stage
SU = Starting up a Project
IP = Initiating a Project
SB = Managing a Stage Boundary
CP = Closing a Project Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
55
8/4/17
OBJECTIVE:
vTo Ensure that:
üThe Attention is focused on delivery of the stage’s products.
üRisks and issues are kept under control
üThe Business Case is kept under review
üThe agreed products for the stage are delivered to stated quality standards & within
agreed baseline
üDelivery is within the tolerances of the stage
CONTEXT:
vDescribes the work of the Project Manager in handling the day-to-day management of the
stage.
vAuthorize, monitor, review of work packages and triggering new ones
vWatching for, and assessing issues, risks and taking any necessary corrective action
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
56
8/4/17
Reporting Highlights
• Assemble the information from the Checkpoint Reports, Risk Register, Issue Register,
Quality Register, Lessons Log, Product Status Account
• Assemble a list of corrective actions
• Review the Highlight Report for the previous reporting period
• Produce the Highlight Report for the current reporting period
• Distribute the Highlight Report to the Project Board
57
8/4/17
Is Management
Stages & Technical
Stages the same?
58
8/4/17
PRINCE2:Processes
Initiation Final
Pre-Project Subsequent Stages Delivery
Stage Stage
Directing a Project
Directing
SU
SB SB CP
Managing Controlling a
IP Controlling a Stage Stage
SU = Starting up a Project
IP = Initiating a Project
SB = Managing a Stage Boundary
CP = Closing a Project Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
59
8/4/17
OBJECTIVE:
üAssure the Project Board that all products in the Stage Plan for the current stage have
been completed and approved
üPrepare the Stage Plan for the next stage
üReview and, if necessary, update the Project Initiation Documentation
üProvide the information needed for the Project Board to assess the continuing viability
of the project
CONTEXT:
vHelps predicate on dividing the project into management stages
vProvides a means by which an exception process can be implemented
vIf necessary, the project can be redirected or stopped to avoid wasting time and money.
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
•Check that the current Stage Plan is up to date with actual progress
•Revise the Project Plan to reflect forecasts
•Update the Issue Register and Risk Register
•Check whether there have been any changes to the risk appetite and risk capacity of the
organizations involved
•Update the Benefits Review Plan with the results from any benefits reviews undertaken during
the stage
•Examine and review: Benefits Review Plan, impact of approved changes, project risk profile,
Issue Register, costs & schedule
60
8/4/17
•For an Exception Plan: Depending on the point within the stage when the exception occurred
produce an End Stage Report
•For a Stage Plan: Review the status of the updated Business Case, team performance, product
performance.
•create a Lessons Report
•Seek approval from the Project Board of the Exception Plan or Stage Plan
•Review the Communication Management Strategy to see whether there is a requirement to
send copies of the End Stage Report
61
8/4/17
PRINCE2:Processes
Initiation Final
Pre-Project Subsequent Stages Delivery
Stage Stage
Directing a Project
Directing
SU
SB SB CP
Managing Controlling a
IP Controlling a Stage Stage
SU = Starting up a Project
IP = Initiating a Project
SB = Managing a Stage Boundary
CP = Closing a Project Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
62
8/4/17
OBJECTIVE:
vTo Ensure that:
üWork on products allocated to the team is authorized and agreed
üThe planned products are delivered to expectations and within tolerance
üAccurate progress information is provided to the Project Manager at an agreed
frequency
CONTEXT:
vViews the project from the Team Manager’s perspective
vAccepting, checking authorized Work Packages and creating a Team Plan for them
vDemonstrating that each product meets its quality criteria through the quality method(s)
vObtaining approval for completed products from the authorities
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
• Verify that all he quality activities associated with the Work Package are complete
• Verify that all the products to be delivered by the Work Package are approved
• Update the Team Plan to show that the Work Package is complete
Deliver a Work
• Notify the Project Manager that the Work Package is complete
Package
63
8/4/17
PRINCE2:Processes
Closing a Project
Initiation Final
Pre-Project Subsequent Stages Delivery
Stage Stage
Directing a Project
Directing
SU
SB SB CP
Managing Controlling a
IP Controlling a Stage Stage
SU = Starting up a Project
IP = Initiating a Project
SB = Managing a Stage Boundary
CP = Closing a Project Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
64
8/4/17
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
OBJECTIVE:
üVerify user acceptance of the project’s products
üReview the performance of the project against its baselines
üEnsure that provision has been made to address all open issues and risks, with follow-
on action recommendations.
CONTEXT:
vClosure activities should be planned as part of the Stage Plan for the final management
stage.
vEither the operational team must now take over the products from this project, or the
products become inputs into some subsequent project or larger programme
vThe project management team can be disbanded and costs should no longer be incurred
vTransfers ownership of the products to the customer and terminates the responsibility of the
project management team.
Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS
65
8/4/17
•Review the project’s original intent as agreed in the initiation stage and defined by the PID
baselined at that time
•Review the approved changes as defined by the current version
•prepare an End Project Report to include: Project Manager’s summary, assessment of the
results, review of how the project performed against its planned targets, review of team
performance, review of the project’s products
•prepare a Lessons Report to include: review of what went well, what went wrong, review of
effort required to create the products
•Any useful knowledge gained regarding the tailoring of PRINCE2
•Use the Communication Management Strategy to identify any organization or interested party
who needs to know that the project is closing
•Close the project’s Issue Register, Risk Register, Quality Register, Daily Log and Lessons Log
•All project information should be secured and archived
•Prepare and send a draft project closure notification for review by the Project Board
66
8/4/17
Records
•Configuration Item
Records Baseline management products
•Daily Log •Benefits Review Plan
•Issue Register •Business Case
•Lessons Log •Communication Management Strategy
•Quality Register •Configuration Management Strategy
•Risk Register. •Plan (covers Project, Stage and,
optionally, Team Plans)
•Product Description
•Project Brief Reports
•Project Initiation Documentation •Checkpoint Report
•Project Product Description •End Project Report
•Quality Management Strategy •End Stage Report
•Risk Management Strategy •Exception Report
•Work Package •Highlight Report
•Issue Report
•Lessons Report
•Product Status Account
67
8/4/17
Embedding Tailoring
Done by the organization to adopt PRINCE2. Done by the project management team to
adapt the method to the context of a specific
project.
Focus on: Focus on:
68