NO JENIS PEKERJAAN VOLUME SAT KETERANGAN
SELESAI BELUM SELESAI PERBAIKAN
1. PEKERJAAN TANAH
1 Galian tanah untuk poer, pondasi dan tie beam 264.75 m³
2 Urugan tanah kembali 88.25 m³
3 Pemadatan tanah 2,680.00 m²
4 Urug pasir pasang bawah pondasi / poer / tie beam t = 10 cm 15.53 m³
5 Lantai kerja , t = 5 cm dibawah pondasi /poer / tie beam 155.32 m²
6 Sirtu dibawah slab lantai workshop t = 20 cm 326.70 m³
7 Sirtu dibawah slab lantai office t = 20 cm 41.40 m³
8 Sirtu dibawah slab lantai Oil Storage t = 20 cm 16.00 m³
9 Sirtu pada ujung ramp t = 20 cm 36.00 m³
10 Plastik cor 2,680.00 m²
2 Cable Leeder 300 x 100 c/w fitting, support and accessories 170.00 mtr
Safety Wire for maintenance 110.00 mtr
3 Armature
HPIT Lamp LED 160 Watt 36.00 nos
HPI-BU Lamp LED 160 Watt nos
Swicth Handle 16.00 nos
Panel Box 400x500x200 – Receptacle (1Ph/16A, 3Ph/32A, 3Ph/63A) 6.00 nos
4 Instalation
Cable dari SDP WS – PP WS 15.00 mtr
Cable dari SDP WS - PP Office WS 15.00 mtr
Cable dari SDP WS – PP UPS 15.00 mtr
Installation lampu HPIT 400 Watt 36.00 nos
Installation lampu HPI-BU 400 Watt
Installation Receptacle Panel Box 6.00 nos