Overall rating and summary of findings Overview

Satisfactory The vast majority


Represents an assessment of a control environment of internal audits
that is satisfactory and supports meeting carried out during
management’s objectives. the period received
a ‘pass’ grade and
there were no ‘high
Adequate with opportunity for further development –
Medium priority for management to address priority’ observations.
Represents an assessment of an adequate control However, there were
environment that broadly supports management’s a small number of
objectives but has further opportunities for development. ‘medium priority’
and ‘low priority’
observations which
are discussed in
more detail below.
Unsatisfactory – High priority for management to Overall, the control
address
environment is in
A high number of control deficiencies or business issues good order and
where the potential financial, operational or reputation risk management are
exposure to XYZ is significant and management should working to resolve
address these issues immediately. the issues identified
during the audits.

Performance improvement opportunities (‘PIOs’) High Priority


Observation
s
Status High Medium Low Total No high priority
Priority Priority Priority observations were
noted.
New PIOs 0

Accepted PIOs 0
Governance, Code & Ethics
Finance & Commercial
Procurement
People
Quality
Information Systems

0 5 10 15 20 25 30

Pass Low Priority Medium Priority High Priority


Overview
A summary of the control environment and process improvement opportunities
identified as part of this internal audit is provided below:
Area Compliance/Good Practice Process improvement/
efficiency opportunity

Governance
, Conduct
and Ethics

Finance and
Commercial

Etc.

Detailed findings
This section summarises in the form of performance improvement observations
(PIOs) the issues arising from this review that we believe require action. PIOs are
rated using the scale in the legend below:

Priority rating for performance improvement observations raised

HIGH: Issues referring to MEDIUM: Issues referring LOW: Issues arising that
important matters that are mainly to matters that have an would, if corrected,
fundamental to XYZ’s system of important effect on XYZ’s improve XYZ’s internal
internal control.We believe that controls, but do not require control in general,
the matters observed might immediate action. A business but are not vital to the
cause a business objective not objective may still be met in full or overall system of
to be met or leave a risk in part or a risk adequately internal control.
unmitigated and need to be mitigated, but the weakness
addressed as represents a significant deficiency
a matter of urgency. in the system.
No Priority Issue Risk Performance Management Responsibility/
Improvement Response Date
Observation

Governance, Conduct and Ethics

1 LOW

Finance and Commercial

2 HIGH

MEDIUM

Etc.

3
Appendix: Scope of work and audit approach

Objective Issues/controls being reviewed Internal audit approach