4.3 Implement all recommendations of Ensure dam safety and minimise Lenders JSCNH Prior to works at Sign off by IPOE
the IPOE risk of flooding to downstream requirements EPC Contractor any site where
communities Georgian IPOE
legislation recommendation
has not been
signed off
Environmental & Social Risks Requirement Target and Evaluation
No. Action (Legislative, Policy, Responsibility Timetable Criteria for Successful Status
(Liability/Benefits) Good Practice) Implementation
4.4 Ensure through the OHS Good JSCNH Throughout on-site job- and task-
management system that no new International EPC Contractor construction and specific hazard
activity/work starts unless an on-site Practice operation analysis carried-out
job- and task-specific hazard analysis
was undertaken in presence of the
staff and of a qualified OHS
supervisor/manager, including the
following aspects:
• Staff’s own language(s)
• Personal and Collective
Protection Equipment
• Record-keeping, including near
misses and incidents
Toolbox talks to share
information on risks, accident
prevention, etc.
Environmental & Social Risks Requirement Target and Evaluation
No. Action (Legislative, Policy, Responsibility Timetable Criteria for Successful Status
(Liability/Benefits) Good Practice) Implementation
PR5 EBRD PR5 - Land Acquisition, Involuntary Resettlement and Economic Displacement
S6 EIB S6 - Involuntary Resettlement
PS5 IFC PS5 - Land Acquisition and Involuntary Resettlement
5.1 Monitor implementation of LALRP Ensure appropriate compensation Lenders JSCNH Monthly internal Details recorded of
through; is paid to project affected persons requirements Georgian monitoring and all affected persons,
● internal monitoring by JSCNH Georgian government reporting during their compensation
including detailed records of all legislation first 3 years of entitlements and the
aspects of compensation LALRP status of payment in
entitlements and payments implementation the Project database.
● external monitoring by
then quarterly Details maintained as
until LALRP up to date and
independent consultant to report
completion. accurate on a
to the Lenders
continuous basis.
External Monitoring reports
monitoring and issued, including
reporting to options for corrective
Lenders every 6 measures.
months
Undertake Livelihood Restoration Lender’s JSCNH 3 years after Audit signed off by
completion audit requirements completion of IPOE and issued to
LALRP lenders
Environmental & Social Risks Requirement Target and Evaluation
No. Action (Legislative, Policy, Responsibility Timetable Criteria for Successful Status
(Liability/Benefits) Good Practice) Implementation
PR8 EBRD PR8 - Cultural Heritage
S5 EIB S5 – Cultural Heritage
PS8 IFC PS8 – Cultural Heritage
8.1 Prepare and implement Chance Minimise risk of impacts on cultural Lenders EPC Contractor Prior to Plan prepared and
Finds Procedure heritage requirements construction submitted to Lenders
Georgian for review and non-
legislation objection received
prior to
implementation
Records of
implementation held
for Lender review
PR10 EBRD PR10 - Information Disclosure and Stakeholder Engagement
S10 EIB S10 - Stakeholder Engagement
PS1 IFC PS1- Assessment and Management of Environmental and Social Risks and Impacts
10.1 Implement Stakeholder Engagement Ensure effective stakeholder Lenders JSCNH SEP to be fully SEP signed off by
Plan (SEP) which includes project engagement and maintain good requirements EPC Contractor implemented IPOE
level grievance mechanism community relations prior to first Regular community
Monitor effectiveness of SEP disbursement. meeting minutes and
implementation Then, ongoing billboard
through early notifications available
works and for Lender review
construction Minutes of public
consultations on E&S
Studies and
Management Plans
Regular maintenance
and updating of
Project website
Records of
engagement with
NGOs and national
level Stakeholders
Environmental & Social Risks Requirement Target and Evaluation
No. Action (Legislative, Policy, Responsibility Timetable Criteria for Successful Status
(Liability/Benefits) Good Practice) Implementation
10.2 Develop a project level external Ensure effective stakeholder Lenders JSCNH Prior to financial Communication plan
communication plan engagement and maintain good requirements close
community relations
10.3 Maintain an effective community Ensure effective stakeholder Lenders JSCNH Ongoing through Record of Grievance
grievance mechanism (established in engagement and maintain good requirements EPC Contractor early works, Resolution
July 2016) community relations construction and Committees
Operation meetings
Monthly and six- Grievance registers
monthly reports available in Naki and
during early works Chuberi Town halls
and construction Grievance database
maintained.
Monthly and six-
monthly reports on
Grievance
management are
available and contain
agreed information.
Annual public
awareness campaigns
on EPP and Dam
Safety
10.4 Maintain access to environmental Ensure effective stakeholder Voluntary and JSCNH Ongoing ESIA package and
and social documents of interest to engagement and maintain good best practice throughout other relevant
the public community relations Project lifetime documents available
on the company
website