Anda di halaman 1dari 6

INSPECTION AND TEST PLAN FOR ADIPL/6907/STSTRL/ITP-

STEEL STRUCTURAL 005- REV-0

Name of Work : Construction of 132m3/hr DM Water Plant Package for BCPL Project,
Lepetkata, Dibrugarh, Assam
Owner : Brahmaputra Cracker and Polymer Limited
Consultant : Engineers India Limited
Contractor : Aqua Designs (I) Pvt. Ltd.

INSPECTION AND TEST PLAN FOR STEEL STRUCTURAL

ITP No. – ADIPL/6907/STSTRL/ITP-005- REV-0

DATE Prepared By Checked By Reviewed By Approved By Reviewed/Approved By


ADIPL ADIPL ADIPL ADIPL EIL
INSPECTION AND TEST PLAN FOR ADIPL/6907/STSTRL/ITP-
STEEL STRUCTURAL 005- REV-0

CONTENTS

SL. NO. DESCRIPTION

1 Legend
2 Abbreviations
3 Inspection & Test Plan
4 Inspection and Test Documents

DATE Prepared By Checked By Reviewed By Approved By Reviewed/Approved By


ADIPL ADIPL ADIPL ADIPL EIL
INSPECTION AND TEST PLAN FOR ADIPL/6907/STSTRL/ITP-
STEEL STRUCTURAL 005- REV-0

LEGEND

HP : Hold Point
A point which requires witnessing/inspection/verification and inspection by
Owner/EIL before any further processing is permitted.

W : Witness Point
An activity which requires witnessing/inspection/verification by Owner/EIL when
The activity is performed

Rw : Review of ADIPL's documentation.

S : Surveillance
Inspection by Owner/EIL

WC : 100% Examination by ADIPL

DATE Prepared By Checked By Reviewed By Approved By Reviewed/Approved By


ADIPL ADIPL ADIPL ADIPL EIL
INSPECTION AND TEST PLAN FOR ADIPL/6907/STSTRL/ITP-
STEEL STRUCTURAL 005- REV-0

ABBREVIATIONS

AFC : Approved For Construction.

LTCS : Low Temperature Carbon Steel.

NDT : Non Destructive Testing.

NACE : National American Corrosion Engineers.

WPS : Welding Procedure Specification.

PQR : Procedure Qualification Record.

PT : Penetrate Testing

MT : Magnetic Particle Testing

PWHT : Post Weld Heat Treatment.

DATE Prepared By Checked By Reviewed By Approved By Reviewed/Approved By


ADIPL ADIPL ADIPL ADIPL EIL
INSPECTION AND TEST PLAN FOR ADIPL/6907/STSTRL/ITP-
STEEL STRUCTURAL 005- REV-0
SL ACTIVITY ADIPL EIL RECORDS TO BE SUBMITTED/
NO FORMAT NO
A PRIOR TO FABRICATION
1 Incoming Material ADIPL/6907/IMIR/ITP-01/F-001
- Document Review WC HP
- Physical Verification WC W
3 Welding Filler Material Approval / Qualification MECH-1-REV-0
a) Review of manufacturer’s Test Certificate/Documents WC HP
b) Laboratory Testing; if any
i) Carbon Steel WC Rw
4 WPS/PQR

a) Review of proposed procedure WC HP


b) Testing
i) Carbon Steel WC Rw
c) Approval of final WPS/PQR WC HP
5 a) Welder performance qualification test WC S
b) Certification & approval of welders WC HP
6 NDT Procedure Qualification
i) Review of proposed procedure WC HP
ii) Witnessing of proposed procedure Testing WC HP
iii) Approval of Qualified Procedure WC HP
B FABRICATION& ERECTION( Shop & Field)
1 Material as per AFC drg./CODE/STD WC S
2 Dimensional checks WC S MECH/4(STRL)-REV-0
3 Fit-up check WC S MECH/4(STRL)-REV-0
4 Preheat (if any) WC S
7 Backing of electrodes ( as applicable) WC S
9 Visual check of welding WC S MECH/4 (STRL)-REV-0
10 Monitoring of PWHT cycle, review of time-tempr. WC S
Graph ( if any)
11 Hardness test, PT/MT ( if any) WC W
12 Identification of joint for radiography (For random WC W
radiography only ), if any
13 Review of radiographs interpreted by the contractor WC W/S
14 Lifting arrangement WC W
15 Test certificates for lifting tackles WC Rw
C INSPECTION & TEST DOCUMENTS
1 Review Test & Inspection Documents WC Rw

DATE Prepared By Checked By Reviewed By Approved By Reviewed/Approved By


ADIPL ADIPL ADIPL ADIPL EIL

Anda mungkin juga menyukai