SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - August 2004)

SAIC NUMBER DATE APPROVED QR NUMBER


SAUDI ARAMCO INSPECTION CHECKLIST
Inspection of Support Foundation Prior to Structural or
SAIC-M-2006 18-May-05 MECH-
Equipment Installation
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A. General requirements

Location, orientation, elevation and conditions of support foundation 12-SAMSS-008


A1
conformed with the Project plan drawings. (PIP STS05130, Para. 6.2.10) Sec. 1

The top of concrete foundation shall be a minimum of 150 mm above


SAES-Q-005,
A2 finished grade. (Note: Not applicable to instrument stand pipe or
sect. 4.3.2 (a)
pedestals inside buildings not subjected to washdown water.)
Concrete foundation has reached the curing period up until the
SAES-Q-001
A3 compressive strength has reached 70% of the specified strength, but not
Sec. 10.3
less than 7 days after placement.

All column base plates have a minimum of four anchor bolts. SAES-M-001,
A4
(NOTE: This excludes posts, which weigh less than 300 pounds/136 kg.) sect 7.1.6 (a)

Leveling shims are installed with a minimum top elevation of 25 mm from


SAES-Q-005,
A5 the top of concrete foundation. This is to allow a minimum thickness of
Par. 4.3.2(c)
25mm of non-shrink cement based grout.
Top elevation of leveling shims conformed to construction drawing
A6 IFC Drawings
elevation plans.
Top of concrete has been roughened (per Std. Dwg. AA-036322-001) or
chipped with hammer to remove laitance, oil-soaked or damaged
SAES-Q-010,
A7 concrete to the level of sound concrete or to a minimum of the top 1 inch
Sec. IV
(25 mm) of concrete. (PIP STS-03600, Para. 6.2.1.1 for Non-Shrink
cement grout, and STS-03600, Para. 6.2.1.1 for epoxy grout).
The top of bearing surfaces and the bottom of base plates are cleaned. 12-SAMSS-008
A8
(PIP STS05130, Para. 6.4.1) Sec. 1

B. Dimensional checks on anchor bolts

Anchor bolt diameter conforms with the Equipment/Structure detail Equipment IFC
B1
drawing. Drawing
Thread length and bolt projection of anchor bolt comformed with the
dimensions indicated in Std. Dwg-AA-036322, Rev 07. SAES-Q-005,
B2
(Note: Actual projection length should allow for complete thread Para. 4.8.1
engagement after considering the thickness of grout and baseplate.)
Equipment IFC
B3 Number of bolts matches the number holes on the equipment/structure.
Drawing
Anchor bolt spacing and bolt circle diameter matched the actual bolt Equipment IFC
B4
holes of the equipment/structure base plate. Drawing

The variation in dimensions between the centers of any two anchor bolts
within an anchor bolt group shall be equal to or less than 1/8" (3mm). 12-SAMSS-008,
B5
(AISC Code of Standard Practice for Steel Buildings and Bridges, Para. Sec. I
7.5.1a and PIP STS05130, Para. 6.2.1)

Page 1 of 2
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Inspection of Support Foundation Prior to Structural or
SAIC-M-2006 18-May-05 MECH-
Equipment Installation
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

The variation in elevation of the tops of anchor rods shall be equal to or


less than plus or minus 1/2" (13mm). (AISC Code of Standard Practice 12-SAMSS-008,
B6
for Steel Buildings and Bridges, Para. 7.5.1c and PIP STS05130, Para. Sec. I
6.2.1)
The variation in dimension from the center of any anchor bolt group to
the established column line through that group shall be equal to or less
B7
than 1/4" (6mm). (AISC Code of Standard Practice for Steel Buildings
and Bridges, Para. 7.5.1e and PIP STS05130, Para. 6.2.1).
REMARKS:
Support foundation is released for structural or equipment installation
Support foundation is not released for structural or equipment installation.

REFERENCE DOCUMENTS:
1- SAES-M-001 -- Structural Design Criteria for Non-Building Structures, June 30 2004
2- SAES-Q-001 -- Criteria for Design and Construction of Concrete Structures, 29 October 2003
3- SAES-Q-005 -- Concrete Foundations, 31 October 2004
4- SAES-Q-010 -- Cement Based, Non-Shrink Grout for Structural and Equipment Grouting, 29 February 2004
5- SAES-Q-011 -- Epoxy Grout for Machinery Support, 29 February 2004
6- PIP STS03600 -- Nonshrink Cementitious Grout Specification, June 2002
7- PIP STS03601 -- Epoxy Grout Specification, October 2001
8-12-SAMSS-008 -- Erection of Structural and Miscellaneous Steel, 28 January 2004
9- PIP STS05130 -- Erection of Structural and Miscellaneous Steel Specification, February 2002
10- AISC -- Code of Standard Practice for Steel Buildings and Bridges, 7 March 2000
11- IFC Drawings (Plan Drawings and Structural or Equipment drawings)
NOTES:
1. Approved - Acceptable to the authority having jurisdiction (i.e., Saudi Aramco ID).
2. Identified - Recognizable as suitable for the specific application by a qualified testing laboratory (i.e., listing and/or labeling).
3. Listed - Equipment and materials included in a list published by an approved qualified organization concerned with evaluation of products
or services, that maintains periodic inspection of production of listed equipment or materials or periodic evaluation of services, and whose listing
that the equipment, material, or services either meets appropriate designated standards or has been tested and found suitable for a specified
4. Labeled - Equipment or materials to which has been attached a label, symbol, or other identifying mark of an approved qualified organization
with product evaluation, that maintains periodic inspection of production of labeled equipment or materials, and by whose labeling the
indicates compliance with appropriate standards or performance in a specified manner.

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Page 2 of 2