Bar bending schedule (BBS) of an concrete footing provides the reinforcement details and th
×
Get Noti cations
required for the footing construction. The BBS and quantity of steel reinforcement required
footing are calculated and explained by means of a workout example.
https://theconstructor.org/concrete/footing-bar-bending-schedule/25936/ 1/10
14/05/2019 Footing Bar Bending Schedule (BBS) – Estimation of Steel Quantity
×
Get Noti cations
Fig.1. Plan and Cross-Sectional View of an Isolated Footing
1. Length of Footing = X
https://theconstructor.org/concrete/footing-bar-bending-schedule/25936/ 2/10
14/05/2019 Footing Bar Bending Schedule (BBS) – Estimation of Steel Quantity
SPONSORED SEARCHES
construction drawings
building footing
diamond saw
calculate concrete mix
concrete foundation construction
×
Get Noti cations
2. Number of Distribution Reinforcement Bars ( Y-Bars)
From the figure-1(c), the x-bars are distributed along the y-direction. Hence the number of b
https://theconstructor.org/concrete/footing-bar-bending-schedule/25936/ 3/10
14/05/2019 Footing Bar Bending Schedule (BBS) – Estimation of Steel Quantity
From Figure-1 (c), the y-bars are distributed along X-axis. Hence the number of bars
×
Get Noti cations
Cm1 = [Length of Footing – 2(cover)] +2[ Thickness of footing -2(cover)] – 2[Bend]
https://theconstructor.org/concrete/footing-bar-bending-schedule/25936/ 4/10
14/05/2019 Footing Bar Bending Schedule (BBS) – Estimation of Steel Quantity
Cm = Nm x Cm1
×
Get Noti cations
Cd = Nd x Cd1
W = D2L/162 Eq.7
Where, V= Area of steel x length of the steel; Density of Steel = 7850 kg/m3
https://theconstructor.org/concrete/footing-bar-bending-schedule/25936/ 5/10
14/05/2019 Footing Bar Bending Schedule (BBS) – Estimation of Steel Quantity
×
Get Noti cations
Fig.1. Example of Plan and Cross-Sectional View of an Isolated Footing
1. Length of Footing = X = 2m
https://theconstructor.org/concrete/footing-bar-bending-schedule/25936/ 6/10
14/05/2019 Footing Bar Bending Schedule (BBS) – Estimation of Steel Quantity
From Eq.1
Nm = (1.6/.15)+1
Nm= 12nos
From Eq.2
Nd = (2/.15)+1
×
Get Noti cations
Nd= 14nos
From Eq.3
Cm1 = 1.9+.4-.048
Cm1=2.252m
Cm = 11 x 2.252
Cm = 24.772m
https://theconstructor.org/concrete/footing-bar-bending-schedule/25936/ 7/10
14/05/2019 Footing Bar Bending Schedule (BBS) – Estimation of Steel Quantity
From Eq.5,
Cd1 = 1.5+.4-.048
Cd1 = 1.852m
Cd = Nd x Cd1
×
Get Noti cations
Cd = 14 x 1.852
Cd = 25.928m
From Eq.7,
W = D2L/162;
Wm = (12 x 12 x 24.772)/162
Wm= 22kg
Wd=(12x12x25.928)/162
Wd =23.05kg
https://theconstructor.org/concrete/footing-bar-bending-schedule/25936/ 8/10
14/05/2019 Footing Bar Bending Schedule (BBS) – Estimation of Steel Quantity
Dia:
No: Total
SL. of Bar Length of
Bar Type Shape of Bar of Length of
No Bar(m)
Bar Bar(m)
(mm)
Main
×
Get Noti cations
1 Reinforcement (X- 12 11 2.252 24.772
Bars)
Distribution
Reinforcement
2 12 14 1.852 23.05
(Y-Bars)
https://theconstructor.org/concrete/footing-bar-bending-schedule/25936/ 9/10
14/05/2019 Footing Bar Bending Schedule (BBS) – Estimation of Steel Quantity
Neenu is a Civil and Structural Engineer and has experience in Design of Concrete and Steel Stru