Document Review Sheet

From: KEIL To: PETROJET


Contract: KEIL/SIBA/2015/C-051
Document Title: MCC for Amine Tank
Document No.: C-051-390-MCC-010-001 Revision: 1
Touchstone Document No.:
Please respond by: (Refer to Transmittal for Return Date)
The document as listed above has been reviewed and has been found to be:

Reviewed - no comment. Revise and re-submit. Revise and re-submit. Review not Required - for
Work may proceed subject to incorporation Work will NOT proceed. information only.
of comments.

*(Tick as appropriate)

Sl. No. Comments (Identify Section/Page/Paragraph) Response Conclusion


Mechanical/Piping
1 Is the dyke wall or paved area around the Amine Tank included in this
system or in another one? if included then please include its paved area is apart of this system and reports included Noted
in sec 5 and the drawing in sec 14
drawings and reports.
2 Include the redline markup PID (update spectacle blinds locations,
etc). Noted and covered Noted
3 Settlement readings are not signed by KEIL Noted and covered IN SEC 5 Noted
4 Tank Test Pack is not signed by KEIL. Noted and covered Noted
5 Reinstatement section of the Tank Test Pack is not signed by PTJ nor
by KEIL. Noted and covered Noted
6 Flange Management Map is not included. Noted and covered Noted
7
Golden Joints (witness joints) tags/labels to be included in the MCC. NO GOLDEN JOINTS IN THIS SYSTEM Noted
8 Line list of the project with the relevant lines highlightde to be As approved line list will be provided in final dossier Noted
included- either soft copy or hard copy
9 Some drawings provided are not the latest revision, for example the
roof structure document (provided one is Code3). NOTED AND COVERED IN SEC14 Noted
10 Insulation work for the Amine Tank is done. To add the Insulation
Report in this MCC Insulation report attached in sec 9 Noted
11
TQ for painting is not included. As we approved all TQ will be supmited in final dossier Noted

Instrumentation
1 02-LI-160107 grounding not connected with device. covered in MPL POINT NO. 7838 Noted
2 02-LZT -160106 impulse line tubing not having proper clamp. covered in MPL POINT NO. 7839 Noted
3 In list of instrument section 11.2 tag no. LT 02-LT-1601087 shall be
corrected to 02-LT-160107. noted and covered Noted

Civil
No Comments

Electrical
No Comments

Name: Afshin Name: Ahmed Salah Name: Mehdi


Date: 15/03/18 Date:8/4/2018 Date: 14 April
Note: Please add/ insert rows for additional comments/ response(s).Do not add additional column.