A) Operation subcontracting
B) Assembly subcontracting
ASSEMBLY SUBCONTRACTING
Due to some capacity problems or operational issues in manufacturing plant, entire Product is
asked to produce outside (at vendor place OR Third party Plant) and component materials are given
to vendor with a subcontracting Purchase Order. Vendor produces the Product and supplies the
Product to plant.
Process Flow:
1. Create material master for Header material ( Product ) and component materials – MM01
2. Make settings in Header material’s material master MRP 2 view for subcontracting. – MM02
Venkatesh Babu
Header material: PAPAYA SFG
Venkatesh Babu
Make settings for Header Material in MRP 2 view for subcontracting for special procurement as 30
as shown below
Venkatesh Babu
Create BOM for header material as shown below with CS01 with three components
as input materials.
Venkatesh Babu
MRP run for Header material – MD02
Convert Purchase Requisition to Purchase Order and provide the details like vendor,
Purch. Org, Purch. Group
Venkatesh Babu
Click on the component button and you will be able to see the components attached to this Purchase
Order..
Venkatesh Babu
Now check for the stock of the raw materials in MMBE they will be shown as Stock provided to
vendor as below
Venkatesh Babu
After vendor manufactures product he supplies the product to the plant.Goods receipt of the Product
material to be done.
Make 101 movement against the Purchase Order to receive the header material
(manufactured Product).