RAB Pagar Batako
RAB Pagar Batako
I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi Ls 1.00 1,500,000.00 1,500,000.00
2 Pengukuran dan Pasang Buowplank Ls 1.00 2,250,000.00 2,250,000.00
3 Administrasi dan Dokumentasi Ls 1.00 3,500,000.00 3,500,000.00
Sub Total 7,250,000.00
II Pekerjaan Tanah / Pasir
1 Galian Tanah Kontruksi M³ 113.20 46,900.00 5,309,080.00
2 Urugan Kembali Bekas Galian M³ 28.30 21,350.00 604,205.00
3 Urugan Pasir Bawah Galian M³ 15.30 85,260.00 1,304,478.00
Sub Total 7,217,763.00
III Pekerjaan Pagar Batako Type I = 60 mtr
1 Pasangan Batu Kosong M³ 7.20 458,134.20 3,298,566.24
2 Pasangan Pondasi Batu Kali M³ 18.90 838,734.00 15,852,072.60
3 Pasangan Dinding Batako M² 103.68 125,617.00 13,023,970.56
4 Plesteran Dinding M² 207.36 55,784.00 11,567,370.24
5 Acian Dinding M² 207.36 32,383.00 6,714,938.88
6 Plesteran Pondasi M² 36.00 55,784.00 2,008,224.00
7 Acian Pondasi M² 36.00 32,383.00 1,165,788.00
8 Sloof 15/20 beton K 225 M³ 1.73 5,445,373.36 9,420,495.91
9 Kolom 20/20 beton K 225 M³ 3.90 6,151,185.16 23,989,622.11
10 Ring Balok 15/20 beton K 225 M³ 1.73 5,445,373.36 9,420,495.91
Sub Total 96,461,544.44
IV Pekerjaan Pagar Batako Type II = 32,50 mtr
1 Pasangan Batu Kosong M³ 3.90 458,134.20 1,786,723.38
2 Pasangan Pondasi Batu Kali M³ 13.16 838,734.00 11,037,739.44
3 Pasangan Batako M² 56.16 125,617.00 7,054,650.72
4 Plesteran Dinding M² 112.32 55,784.00 6,265,658.88
5 Acian Dinding M² 112.32 32,383.00 3,637,258.56
6 Plesteran Pondasi M² 26.00 55,784.00 1,450,384.00
7 Acian Pondasi M² 26.00 32,383.00 841,958.00
8 Sloof 15/20 beton K 225 M³ 0.94 5,445,373.36 5,118,650.95
9 Kolom 20/20 beton K 225 M³ 2.33 6,151,185.16 14,332,261.41
10 Ring Balok 15/20 beton K 225 M³ 0.94 5,445,373.36 5,118,650.95
Sub Total 56,643,936.30
V Pekerjaan Pagar Batako Type III = 140 mtr
1 Pasangan Batu Kosong M³ 16.80 458,134.20 7,696,654.56
2 Pasangan Pondasi Batu Kali M³ 56.70 838,734.00 47,556,217.80
3 Pasangan Batako M² 239.40 125,617.00 30,072,709.80
4 Plesteran Dinding M² 478.80 55,784.00 26,709,379.20
5 Acian Dinding M² 478.80 32,383.00 15,504,980.40
6 Plesteran Pondasi M² 98.00 55,784.00 5,466,832.00
7 Acian Pondasi M² 98.00 32,383.00 3,173,534.00
8 Sloof 15/20 beton K 225 M³ 3.57 5,445,373.36 19,439,982.88
No. Uraian Pekerjaan Satuan Volume Harga Satuan Jumlah Harga
1 2 3 4 5 6
Terbilang : " Tujuh Ratus Lima Belas Juta Tujuh Ratus Delapan Puluh Ribu Rupiah "
ANALISA HARGA SATUAN
9 1 M² Plesteran
Semen PC Zak 0.125 85,000.00 10,625.00
Pasir M³ 0.024 203,000.00 4,872.00
Pekerja Org 0.300 74,200.00 22,260.00
Tukang Org 0.150 98,000.00 14,700.00
Kepala Tukang Org 0.015 109,800.00 1,647.00
Mandor Org 0.015 112,000.00 1,680.00
Total Harga Rp. 55,784.00
10 1 M² Acian
Semen PC Zak 0.065 85,000.00 5,525.00
Pekerja Org 0.200 74,200.00 14,840.00
Tukang Org 0.100 98,000.00 9,800.00
Kepala Tukang Org 0.010 109,800.00 1,098.00
Mandor Org 0.010 112,000.00 1,120.00
Total Harga Rp. 32,383.00
II Pekerjaan Beton
1 1 M² Rabat Beton
Semen PC Zak 4.360 85,000.00 370,600.00
Pasir M³ 0.520 203,000.00 105,560.00
Batu Pecah 2/3 M³ 0.870 350,000.00 304,500.00
Pekerja Org 1.650 74,200.00 122,430.00
Tukang Org 0.250 98,000.00 24,500.00
Kepala Tukang Org 0.050 109,800.00 5,490.00
Mandor Org 0.080 112,000.00 8,960.00
Total Harga Rp. 942,040.00
3 10 Kg Pekerjaan Pembesian
Besi Beton Kg 11.000 19,500.00 214,500.00
Kawat Beton M³ 0.300 25,000.00 7,500.00
Pekerja Org 0.070 74,200.00 5,194.00
Tukang Besi Org 0.070 98,000.00 6,860.00
Kepala Tukang Org 0.007 109,800.00 768.60
Mandor Org 0.004 112,000.00 448.00
Total Harga Rp. 235,270.60
Per Kg Besi Rp. 23,527.06
4 1 M² Pekerjaan Begesting
Kayu Kelas III M³ 0.030 1,500,000.00 45,000.00
Paku Biasa Kg 0.400 20,000.00 8,000.00
Mould Oil Ltr 0.200 40,000.00 8,000.00
Multiplex 6mm Lbr 0.350 130,000.00 45,500.00
Kayu Doken Btg 0.500 18,000.00 9,000.00
Pekerja Org 0.300 74,200.00 22,260.00
Tukang Org 0.260 98,000.00 25,480.00
Kepala Tukang Org 0.026 109,800.00 2,854.80
Mandor Org 0.005 112,000.00 560.00
Total Harga Rp. 166,654.80