Reason For Audit: Future Launch Current Partial Other Safety Related Part ? Yes No N/A
Type of Audit: Initial Follow Up Run at Rate (GP9 Attachement B) Product Validation/Qualification Complete: Yes No N/A
Driver of Audit: APQP Confirmation Mgmt. Request Plant Request Run @ Rate CPIP/Warranty
Top Focus CSL-1 CSL-2 Major Disruption Shutdown/Start Up Audit
Component Check Plan Critical Fastner (D02) D/PFMEA DD&W Other
Focus of Audit: Part / Assembly Line /Cell Operation / Machine Complete Mfg. System Quality System - Ongoing Documentation
Approved Approved, but need Documentation Not Approved Follow-Up Audit Date:
24. Do your supplier's provide evidance of approved material for all components
needed for the assembled part?
Revised 9-1-07
25. Are controls in place to ensure only approved incoming material released for
production?
26. When parts require traceability, do controls link component traceability to the final
part?
27. Is the workplace properly configured and matches Process Flow Diagram?
28. Are all tools and gauges properly identified?
29. Are all gauges calibrated?
30 Are all tools and gauges certified?
31. Is gauge Repeatability and Reproducabilty less than 10%?
32. Do all gauges have proper operator instructions?
33. Are proper operator instructions available for each operation?
34. Are Standardized Work instructions detailed to run the job properly, including
handling of non-conforming parts?
35. Is there Standardized Work?
36. Is the Standradized Work being followed?
37. Do the operators understand the instructions?
38. Have operators been properly trained?
39. Are boundary samples (BS) available to operators?
40. Are boundary samples (BS) in use?
41. Are Master Parts or samples available to confirm inspection?
42. Are Master Parts available for error proofing devices?
43. Is there a Preventive Maintenance (PM) plan on tools and is it followed?
44. Is there standardized work (or control plan) for part quality verification
following a tool change?
45. Is there a Preventive Maintenance (PM) plan on equipment and is it followed?
46. Are listed tests and inspections per control plan, actually performed as stated?
47. Where the Process Control Plan calls for SPC are the data properly recorded?
48. Are the Upper Control Limits (ULC) current?
49. Are the Lower Control Limits (LCL) current?
50. Does the data make sense and are reasonable control limits shown?
51. Are out of control points noted with the corrective action taken?
52. Are product audits showing acceptable results for Final Product?
53. Does the manufacturing process demonstrate the required capability or
54. performance?
Does packaging and material handling protect parts from damage?
55. Are instructions for handling Work In Process (WIP) and final product followed
56. throughout
Are all partsthe
andprocess to shipping
components area;
labeled including repair/rework areas?
properly?
QUALITY SYSTEM IMPLEMENTATION BY MANAGEMENT
57. Is there a process for documenting and tracking Downtime?
58. Is there a process for documenting and tracking Scrap?
59. Is there a process for documenting and tracking First Time Quality?
60. Is there a process for documenting and tracking Premium Freight?
61. Is there a process for documenting and tracking Plant Problem Reports?
62. Does leadership ensure that Out of Control Conditions are managed?
63. Are Action Plans (AP) followed?
64. Is responsibility for implementation assigned and do people understand their
65. responsibility?
Are problems quickly communicated to people who can help?
Auditors Comments:
Revised 9-1-07
423911364.xls Summary Printed 06/11/2019
0 39. Boundary Samples Available 0 40. Boundary Samples in Use 0 41. Master Parts/Samples Available
0 54. Packaging and Material Handling 0 55. WIP for Final Product 0 56. Parts and Components Label
0 66. Support System for Operators 0 67. Information across all shifts 0 68. Check Requirements Performed
0 69. Results Documented 0 70. Actions for Deviations 0 71. QSB Audit
0 Total Potential 60 0%
Revised 01-21-05
423911364.xls Worksheet Printed 06/11/2019
Assure Gauging/Inspection
Does the Process Flow Diagram include matches the Process Flow
10 Process Flow Diagram R
gauging/inspection? Diagram and what is observed on
the shop floor.
Is there a Process Control Plan (PCP) Updated Process Control Verify current dates, etc. of PCP
16 R
available? Plan document.
Is the Process Control Plan (PCP)
PCP, Changed Log,
acceptable (numbers match PFMEA and
Meeting Minutes or Verify that PFMEA is updated as
Process Flow, including
17 Similar History (Linking required and matches Process R
KPCs/PQCs/KCCs/DRs/ITFs, GP-12 if
all Documents), Control Plan.
applicable and latest EWO/ODM
Blue Print
included)?
4 of 12 Revised 01-21-05
423911364.xls Worksheet Printed 06/11/2019
5 of 12 Revised 01-21-05
423911364.xls Worksheet Printed 06/11/2019
Standardized
36 Is the Standradized Work being followed? Layered Audits. R
Worksheets
Ask operator to demonstrate use
Do the operators understand the of gage and explain implication of
37 Operator Instructions R
instructions? conforming and non-conforming
parts.
Ask operator to demonstrate use
of gage and explain implication of
conforming and non-conforming
38 Have operators been properly trained? Operator Instructions R
parts.
Certification Training Record or
Plan.
6 of 12 Revised 01-21-05
423911364.xls Worksheet Printed 06/11/2019
Are instructions for handling Work In Check to make sure all operators
WIP Instructions
Process (WIP) and final product followed and material handling personnel
55 Final Shipping R
throughout the process to shipping area; are aware of and following WIP
Instructions
including repair/rework areas? instructions.
7 of 12 Revised 01-21-05
423911364.xls Worksheet Printed 06/11/2019
8 of 12 Revised 01-21-05
423911364.xls Worksheet Printed 06/11/2019
9 of 12 Revised 01-21-05
Process Performance SUPPLIER ACTION PLAN REPORT Rev. 7 1/7/02
"Color Codes"
G Green - Task Completed on Time
Y Yellow - Task May Be Late
R Red - Task is Late
W White - Task Re-Timed, No Status
B Blue - Task Status is Incorrect / Not Updated
On Track (Bold Box/No Color)
TOTAL TOTAL STATUS
0 0
STATUS HISTORY
TARGET ACTUAL
ACTION DATE LAST
ITEM ACTION ITEM CLOSE CLOSE Most COUNTER MEASURES
LEADER OPENED UPDATE
DATE DATE Oldest Recent
# 1 2 3 4 5 6
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
"Color Codes"
G Green - Task Completed on Time
Y Yellow - Task May Be Late
R Red - Task is Late
W White - Task Re-Timed, No Status
B Blue - Task Status is Incorrect / Not Updated
On Track (Bold Box/No Color)
TOTAL TOTAL STATUS
0 0
STATUS HISTORY
TARGET ACTUAL
ACTION DATE LAST
ITEM ACTION ITEM CLOSE CLOSE Most COUNTER MEASURES
LEADER OPENED UPDATE
DATE DATE Oldest Recent
# 1 2 3 4 5 6
24
25
26
27
28
29
B5: Person at supplier that prepared the form for the GM SQE. (If applicable)
C16: ACTION ITEM: The item that requires action to improve the process or quality of the product being produced.
D16: ACTION LEADER: The person that leads the team to make the improvements. This should be the suppliers person but may be a GM Management person.
E15: Formula: DO NOT TYPE IN THIS CELL, UNLESS YOUR ARE MODIFYING THE FORMULA
E16: START DATE: The date the action item was identified and listed in the action item column
F16: TARGET CLOSE DATE: The date the supplier will complete the action item.
This date may change. If the date changes, you are required to entry the correct color code in the pass status and present status columns.
A comment on why the change to be entered in the comment field
G15: Formula: DO NOT TYPE IN THIS CELL, UNLESS YOUR ARE MODIFYING THE FORMULA
G16: ACTUALCLOSE DATE: The date the action item was closed TO INCLUDE VALIDATION.
The SQE should validate the action item as being closed and RESOLVED.
H16: LAST UPDATE: The date the SQE reviewed the action item.
I16: PAST STATUS: The cell is filled in when the status changes. Oldest status to the left
If status is WHITE put a "W" in the cell. Do not leave blank.
Copy the cell for the correct color.
COLOR CODE:
GREEN: Task Completed on Time
YELLOW: Action item is in trouble and may affect target date.
RED: Action item has missed target date.
WHITE: Task Re-Timed, No Status
BLUE: Task Status is incorrect / Not Updated