PRSADA JAYA
GENERAL CONTRACTOR AND SUPPLIER
Alamat : Jl,Aw.Syahrani No .28/RT.26 ,Samarinda KALTIMANTAN TIMUR
Tlep/Fax :( 0541) 6252150
REKAPITULASI KEMAJUA
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 1
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
13.36 - - - 0.00
100.00 - 0.99 0.99 -1.40
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 1
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
13.36 - - - 0.00
100.00 0.99 8.08 9.06 5.08
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 1
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
13.36 - - - 0.00
100.00 9.06 0.54 9.60 3.69
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
HARGA
BIAYA
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A KONSTRUKSI
1 Renovasi Kantor Koramil 1 Bh 149.00 M² Rp 4,557,208.22 Rp 679,024,024.85
MAJU LAMBAT
KETERANGAN
ADI KAMARUDIN
Serma NRP 3910251940669 MAYOR CZI NRP 11
EMAJUAN FISIK
PROGRES MINGGU LALU (%) PROGRES FISIK MINGGU INI (%) PRESTASI FISIK S/D MINGGU INI
TERHADAP TERHADAP TERHADAP DIVIASI
TERHADAP TERHADAP TERHADAP
BOBOT BOBOT BOBOT BOBOT
KONTRAK KONTRAK KONTRAK
SENDIRI SENDIRI SENDIRI
7 8 9 10 11 12 13 14
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04
5.76 -
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19
3 Ringbalk 15/20 2.75 M³ 1.33
4 Plat Sunscreen 3.60 M³ 2.97
5.68 -
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62
5.17 -
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35
2 Jack Shower 3.00 Bh 0.15
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07
10 Memasang floor drain stainless 3.00 Bh 0.04
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52
2.67 -
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
N PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 1 (SATU)
PRIODE : 07 Mei 2018 - 13 Mei 2018
RENCANA : 2.39 %
REALISASI : 0.99 %
DIVIASI : -1.40 %
PROGRES MINGGU INI : 0.99 %
MINGGU INI SAMPAI MINGGU INI
KOMULAT RENCANA DIVIASI
BOBOT BOBOT
VOL VOL IF
(%) (%)
c d e=(a+c) f g h i=(e-h)
- - 0% 0.83 (0.83)
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% 0.80 (0.80)
- - 1.63 (1.63)
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
MINGGU INI SAMPAI MINGGU INI
KOMULAT RENCANA DIVIASI
BOBOT BOBOT
VOL VOL IF
(%) (%)
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
MINGGU INI SAMPAI MINGGU INI
KOMULAT RENCANA DIVIASI
BOBOT BOBOT
VOL VOL IF
(%) (%)
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
MINGGU INI SAMPAI MINGGU INI
KOMULAT RENCANA DIVIASI
BOBOT BOBOT
VOL VOL IF
(%) (%)
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
MINGGU INI SAMPAI MINGGU INI
KOMULAT RENCANA DIVIASI
BOBOT BOBOT
VOL VOL IF
(%) (%)
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
0.99 0.99 2.39 (1.40)
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
0.99 0.99 2.39 (1.40)
MINGGU INI SAMPAI MINGGU INI
KOMULAT RENCANA DIVIASI
BOBOT BOBOT
VOL VOL IF
(%) (%)
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEK
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 - -
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 - -
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 -
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 - -
2 Kolom utama20/20 cm 0.32 M³ 0.19 - -
3 Ringbalk 15/20 2.75 M³ 1.33 - -
4 Plat Sunscreen 3.60 M³ 2.97 - -
5.68 -
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 - -
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 - -
5.17 -
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 - -
2 Jack Shower 3.00 Bh 0.15 - -
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 - -
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 - -
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 - -
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 - -
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 - -
10 Memasang floor drain stainless 3.00 Bh 0.04 - -
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 - -
2.67 -
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 2 (DUA)
PRIODE : 14 Mei 2018 - 20 Mei 2018
RENCANA : 3.98 %
REALISASI : 9.06 %
DIVIASI : 5.08 %
PROGRES MINGGU INI : 8.08 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
- - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
8.08 9.06 3.98 5.08
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
8.08 9.06 3.98 5.08
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 - -
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 - -
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 -
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 - -
2 Kolom utama20/20 cm 0.32 M³ 0.19 - -
3 Ringbalk 15/20 2.75 M³ 1.33 - -
4 Plat Sunscreen 3.60 M³ 2.97 - -
5.68 -
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 - -
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 - -
5.17 -
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 - -
2 Jack Shower 3.00 Bh 0.15 - -
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 - -
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 - -
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 - -
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 - -
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 - -
10 Memasang floor drain stainless 3.00 Bh 0.04 - -
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 - -
2.67 -
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
N PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 3 (TIGA)
PRIODE : 21 Mei 2018 - 27 Mei 2018
RENCANA : 5.92 %
REALISASI : 9.60 %
DIVIASI : 3.69 %
PROGRES MINGGU INI : 0.54 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
- - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
0.54 9.60 5.92 3.69
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
0.54 9.60 5.92 3.69
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
a
I PEKERJAAN PENDAHULUAN
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 -
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%)
VOL
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 -
2 Kolom utama20/20 cm 0.32 M³ 0.19 -
3 Ringbalk 15/20 2.75 M³ 1.33 -
4 Plat Sunscreen 3.60 M³ 2.97 -
5.68
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 -
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 -
5.17
3 Penutup plafon GRC board 4 mm lengkap dgn rangka hollow 56.00 M² 0.94 -
4 List plafon bahan kayu kamper samarinda papan 1 x 5 cm 123.70 M¹ 0.39 -
5.02
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 -
2 Jack Shower 3.00 Bh 0.15 -
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 -
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 -
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 -
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 -
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 -
10 Memasang floor drain stainless 3.00 Bh 0.04 -
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 -
2.67
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
JUAN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 4 (EMPAT)
PRIODE : 28 Mei 2018 - 03 Juni 2018
RENCANA : 7.87 %
REALISASI : 12.68 %
DIVIASI : 4.81 %
PROGRES MINGGU INI : 3.08 %
MINGGU LALU MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%) (%)
b c d e=(a+c) f g h i=(e-h)
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - -
- - - - 0% - -
- - - - 0% - -
MINGGU LALU MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%) (%)
- - - - 0% - -
- - - - 0% - -
- - - - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
MINGGU LALU MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%) (%)
- - - - 0% - -
- - - - 0% - -
- -
- - - - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - -
MINGGU LALU MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%) (%)
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - -
9.60 2.89 12.49 7.87 4.62
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- - - - 0% - -
- 1.00 0.19 1.00 0.19 100% - 0.19
- 0.19 0.19 - 0.19
9.60 3.08 12.68 7.87 4.81
MINGGU LALU MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%) (%)
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 36.70 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 37.63 0.63
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 1.29
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 2.90 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19 - -
3 Ringbalk 15/20 2.75 M³ 1.33 - -
4 Plat Sunscreen 3.60 M³ 2.97 - -
5.68 1.19
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 - -
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 - -
5.17 -
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 - -
2 Jack Shower 3.00 Bh 0.15 - -
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 - -
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 - -
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 - -
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 - -
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 - -
10 Memasang floor drain stainless 3.00 Bh 0.04 - -
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 - -
2.67 -
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 5 (EMPAT)
PRIODE : 04 Juni 2018 - 10 Juni 2018
RENCANA : 12.78 %
REALISASI : 17.32 %
DIVIASI : 4.54 %
PROGRES MINGGU INI : 4.64 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
3.11 15.60 12.78 2.82
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 36.70 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 206.98 3.45
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 4.11
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 2.90 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19 0.32 0.19
3 Ringbalk 15/20 2.75 M³ 1.33 - -
4 Plat Sunscreen 3.60 M³ 2.97 - -
5.68 1.38
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 - -
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 - -
5.17 -
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 - -
2 Jack Shower 3.00 Bh 0.15 - -
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 - -
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 - -
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 - -
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 - -
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 - -
10 Memasang floor drain stainless 3.00 Bh 0.04 - -
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 - -
2.67 -
XV
PEKERJAAN PRASARANA LINGKUNGAN - DRAINASE
1 Parit cucuran atap pasang bata 60.00 M¹ 4.80 - -
3 Plat duiker lbr saluran 1 m tb. Plat 15 cm 6.00 M² 1.25 - -
4 Pembuatan taman 1.00 Ls 0.69 - -
6.74 -
A PEKERJAAN KONSTRUKSI 86.64 15.60
B PRASARANA
1 Pemb. Sumur bor manual 3 paket
- Biaya pengeboran sumur 1.00 Peket 1.53 1.00 1.53
- Menara kayu ulin t= 3 m 1.00 Bh 0.31 - -
- Profil tank 1200 ltr 1.00 Bh 0.22 - -
- Pasang instalasi pipa air 1.00 Ls 0.11 - -
2 Pembangunan pagar tembok termasuk Hollow 71.00 M¹ 10.99 - -
3 Biaya Penyambungan Listrik PLN 1.00 Ls 0.19 1.00 0.19
13.36 1.72
100.00 17.32
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 6 (ENAM)
PRIODE : 11 Juni 2018 - 17 Juni 2018
RENCANA : 19.30 %
REALISASI : 17.32 %
DIVIASI : -1.98 %
PROGRES MINGGU INI : 0.00 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- 15.60 15.24 0.36
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 36.70 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 206.98 3.45
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 4.11
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 2.90 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19 0.32 0.19
3 Ringbalk 15/20 2.75 M³ 1.33 - -
4 Plat Sunscreen 3.60 M³ 2.97 - -
5.68 1.38
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 - -
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 - -
5.17 -
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 - -
2 Jack Shower 3.00 Bh 0.15 - -
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 - -
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 - -
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 - -
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 - -
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 - -
10 Memasang floor drain stainless 3.00 Bh 0.04 - -
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 - -
2.67 -
XV
PEKERJAAN PRASARANA LINGKUNGAN - DRAINASE
1 Parit cucuran atap pasang bata 60.00 M¹ 4.80 - -
3 Plat duiker lbr saluran 1 m tb. Plat 15 cm 6.00 M² 1.25 - -
4 Pembuatan taman 1.00 Ls 0.69 - -
6.74 -
A PEKERJAAN KONSTRUKSI 86.64 15.60
B PRASARANA
1 Pemb. Sumur bor manual 3 paket
- Biaya pengeboran sumur 1.00 Peket 1.53 1.00 1.53
- Menara kayu ulin t= 3 m 1.00 Bh 0.31 - -
- Profil tank 1200 ltr 1.00 Bh 0.22 - -
- Pasang instalasi pipa air 1.00 Ls 0.11 - -
2 Pembangunan pagar tembok termasuk Hollow 71.00 M¹ 10.99 - -
3 Biaya Penyambungan Listrik PLN 1.00 Ls 0.19 1.00 0.19
13.36 1.72
100.00 17.32
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 7 (TUJUH)
PRIODE : 18 Juni 2018 - 24 Juni 2018
RENCANA : 26.90 %
REALISASI : 23.17 %
DIVIASI : -3.73 %
PROGRES MINGGU INI : 5.85 %
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
2.17 17.77 19.84 (2.07)
CV.PRASADA JAYA
0 PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 36.70 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 303.49 5.06
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 5.72
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 2.90 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19 0.32 0.19
3 Ringbalk 15/20 2.75 M³ 1.33 - -
4 Plat Sunscreen 3.60 M³ 2.97 - -
5.68 1.38
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 73.40 0.56
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 - -
5.17 0.56
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 - -
2 Jack Shower 3.00 Bh 0.15 - -
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 - -
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 - -
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 - -
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 - -
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 - -
10 Memasang floor drain stainless 3.00 Bh 0.04 - -
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 - -
2.67 -
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 8 (DELAPAN)
PRIODE : 25 Juni 2018 - 01 Juli 2018
RENCANA : 36.45 %
REALISASI : 34.45 %
DIVIASI : -1.99 %
PROGRES MINGGU INI : 11.47 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
- - 0% 0.50 (0.50)
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0.50 (0.50)
- - 0% - -
- - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
- - 0% - -
- - 0% - -
- - 0% - -
- - - -
5.54 23.30 24.27 (0.97)
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 36.70 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 303.49 5.06
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 5.72
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 2.90 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19 0.32 0.19
3 Ringbalk 15/20 2.75 M³ 1.33 1.65 0.80
4 Plat Sunscreen 3.60 M³ 2.97 2.16 1.78
5.68
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 73.40 0.56
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 364.18 2.77
5.17 3.33
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 - -
2 Jack Shower 3.00 Bh 0.15 - -
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 - -
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 - -
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 - -
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 - -
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 - -
10 Memasang floor drain stainless 3.00 Bh 0.04 - -
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 - -
2.67 -
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 9 (SEMBILAN)
PRIODE : 02 Juli 2018 - 08 Juli 2018
RENCANA : 43.67 %
REALISASI : 39.84 %
DIVIASI : -3.83 %
PROGRES MINGGU INI 5.20 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
- - - - 0% 1.01 (1.01)
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - 1.01 (1.01)
- - - 0% - -
- - - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
4.88 28.18 30.31 (2.13)
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 36.70 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 303.49 5.06
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 5.72
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 2.90 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19 0.32 0.19
3 Ringbalk 15/20 2.75 M³ 1.33 1.93 0.93
4 Plat Sunscreen 3.60 M³ 2.97 2.52 2.08
5.68 4.39
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 73.40 0.56
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 485.58 3.69
5.17 4.25
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 - -
2 Jack Shower 3.00 Bh 0.15 - -
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 - -
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 - -
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 - -
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 - -
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 - -
10 Memasang floor drain stainless 3.00 Bh 0.04 - -
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 - -
2.67 -
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 10 (SEPULUH)
PRIODE : 09 Juli 2018 - 15 Juli 2018
RENCANA : 53.82 %
REALISASI : 49.31 %
DIVIASI : -4.51 %
PROGRES MINGGU INI 0.00 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
- - - 0% 0.87 (0.87)
- - - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - 0.87 (0.87)
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 36.70 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 303.49 5.06
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 5.72
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 2.90 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19 0.32 0.19
3 Ringbalk 15/20 2.75 M³ 1.33 2.75 1.33
4 Plat Sunscreen 3.60 M³ 2.97 2.52 2.08
5.68 4.79
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 73.40 0.56
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 485.58 3.69
5.17 4.25
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 - -
2 Jack Shower 3.00 Bh 0.15 - -
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 - -
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 - -
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 - -
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 - -
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 - -
10 Memasang floor drain stainless 3.00 Bh 0.04 - -
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 - -
2.67 -
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 11 (SEBELAS)
PRIODE : 06 Juli 2018 - 22 Juli 2018
RENCANA : 63.81 %
REALISASI : 50.66 %
DIVIASI : -13.16 %
PROGRES MINGGU INI 1.35 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
- - - 0% 1.74 (1.74)
- - - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - 1.74 (1.74)
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% 0.07 (0.07)
- - - 0% 0.09 (0.09)
- - - 0% 0.65 (0.65)
- - - 0% 0.07 (0.07)
- - - 0% - -
- - - 0% - -
- - 0.88 (0.88)
- - - 0% 0.14 (0.14)
- - - 0% 0.04 (0.04)
-
- - - 0% 0.12 (0.12)
- -
- - - 0% 0.14 (0.14)
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% 0.12 (0.12)
- - - 0% 0.11 (0.11)
- - - 0% - -
- - - 0% - -
- - 0.67 (0.67)
- - - 0% 0.61 (0.61)
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - 0.61 (0.61)
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% 0.55 (0.55)
- - 0.55 (0.55)
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 36.70 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 303.49 5.06
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 5.72
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 2.90 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19 0.32 0.19
3 Ringbalk 15/20 2.75 M³ 1.33 2.75 1.33
4 Plat Sunscreen 3.60 M³ 2.97 2.52 2.08
5.68 4.79
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 73.40 0.56
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 485.58 3.69
5.17 4.25
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 - -
2 Jack Shower 3.00 Bh 0.15 - -
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 - -
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 - -
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 - -
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 - -
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 - -
10 Memasang floor drain stainless 3.00 Bh 0.04 - -
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 - -
2.67 -
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 12 (DUA BELAS)
PRIODE : 23 Juli 2018 - 29 Juli 2018
RENCANA : 68.35 %
REALISASI : 61.22 %
DIVIASI : -7.13 %
PROGRES MINGGU INI 10.56 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
- - - 0% 2.17 (2.17)
- - - 0% - -
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - 2.17 (2.17)
- - - 0% 0.09 (0.09)
- - - 0% - -
- - - 0% - -
- - - 0% 0.07 (0.07)
- - - 0% 0.09 (0.09)
- - - 0% 0.65 (0.65)
- - - 0% 0.07 (0.07)
- - - 0% - -
- - - 0% - -
- - 0.97 (0.97)
- - - 0% 0.28 (0.28)
- - - 0% 0.09 (0.09)
- - - 0% 0.24 (0.24)
-
- - - 0% 0.27 (0.27)
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% 0.23 (0.23)
- - - 0% 0.22 (0.22)
- - - 0% - -
- - - 0% - -
- - 1.34 (1.34)
- - - 0% - -
- - - 0% - -
- - - 0% - -
185.13 3.17 185.13 3.17 61% - 3.17
- - - 0% - -
3.17 3.17 - 3.17
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% - -
- - - 0% 0.55 (0.55)
- - 0.55 (0.55)
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 36.70 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 303.49 5.06
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 5.72
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 2.90 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19 0.32 0.19
3 Ringbalk 15/20 2.75 M³ 1.33 2.75 1.33
4 Plat Sunscreen 3.60 M³ 2.97 3.60 2.97
5.68 5.68
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 73.40 0.56
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 606.97 4.62
5.17 5.17
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 - -
2 Jack Shower 3.00 Bh 0.15 - -
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 - -
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 - -
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 - -
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 - -
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 - -
10 Memasang floor drain stainless 3.00 Bh 0.04 - -
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 - -
2.67 -
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 13 (TIGA SEBELAS)
PRIODE : 30 Juli 2018 - 05 Agustus 2018
RENCANA : 75.49 %
REALISASI : 64.42 %
DIVIASI : -11.07 %
PROGRES MINGGU INI 2.87 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
- - - 0% 2.61 (2.61)
- - - 0% 1.09 (1.09)
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% 0.94 (0.94)
- - - 0% 0.39 (0.39)
- - 5.02 (5.02)
- - - 0% 0.18 (0.18)
- - - 0% - -
- - - 0% - -
- - - 0% 0.07 (0.07)
- - - 0% 0.09 (0.09)
- - - 0% 0.65 (0.65)
- - - 0% 0.07 (0.07)
- - - 0% - -
- - - 0% - -
- - 1.06 (1.06)
- - - 0% 0.28 (0.28)
- - - 0% 0.09 (0.09)
- - - 0% 0.24 (0.24)
-
- - - 0% 0.27 (0.27)
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% 0.23 (0.23)
- - - 0% 0.22 (0.22)
- - - 0% 0.12 (0.12)
- - - 0% 0.02 (0.02)
- - 1.48 (1.48)
- - - 0% - -
- - - 0% - -
- - - 0% - -
45.52 0.78 230.65 3.96 76% - 3.96
- - - 0% - -
0.78 3.96 - 3.96
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% 0.19 (0.19)
- - - 0% 0.07 (0.07)
- - - 0% 0.04 (0.04)
- - - 0% 0.08 (0.08)
- - - 0% 0.55 (0.55)
- - 0.92 (0.92)
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 36.70 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 303.49 5.06
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 5.72
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 2.90 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19 0.32 0.19
3 Ringbalk 15/20 2.75 M³ 1.33 2.75 1.33
4 Plat Sunscreen 3.60 M³ 2.97 3.60 2.97
5.68 5.68
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 73.40 0.56
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 606.97 4.62
5.17 5.17
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 - -
2 Jack Shower 3.00 Bh 0.15 - -
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 - -
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 - -
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 - -
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 - -
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 - -
10 Memasang floor drain stainless 3.00 Bh 0.04 - -
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 - -
2.67 -
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 14 ( EMPAT BELAS)
PRIODE : 06 Agustus 2018 - 12 Agustus 2018
RENCANA : 81.46 %
REALISASI : 75.22 %
DIVIASI : -6.25 %
PROGRES MINGGU INI 10.80 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
- - - 0% 0.27 (0.27)
- - - 0% 0.15 (0.15)
- - - 0% 0.73 (0.73)
- - - 0% 0.07 (0.07)
- - - 0% 0.09 (0.09)
- - - 0% 0.65 (0.65)
- - - 0% 0.07 (0.07)
- - - 0% 0.04 (0.04)
- - - 0% 0.52 (0.52)
- - 2.59 (2.59)
- - - 0% 0.28 (0.28)
- - - 0% 0.09 (0.09)
- - - 0% 0.24 (0.24)
-
- - - 0% 0.27 (0.27)
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% 0.23 (0.23)
- - - 0% 0.22 (0.22)
- - - 0% 0.12 (0.12)
- - - 0% 0.02 (0.02)
- - 1.48 (1.48)
- - - 0% 0.12 (0.12)
- - - 0% 0.54 (0.54)
- - - 0% 0.43 (0.43)
30.35 0.52 261.00 4.48 86% 0.74 3.73
- - - 0% 0.04 (0.04)
0.52 4.48 1.86 2.62
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% 0.38 (0.38)
- - - 0% 0.13 (0.13)
- - - 0% 0.08 (0.08)
- - - 0% 0.15 (0.15)
- - - 0% 0.55 (0.55)
- - 1.29 (1.29)
(4.44)
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 36.70 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 303.49 5.06
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 5.72
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 2.90 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19 0.32 0.19
3 Ringbalk 15/20 2.75 M³ 1.33 2.75 1.33
4 Plat Sunscreen 3.60 M³ 2.97 3.60 2.97
5.68 5.68
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 73.40 0.56
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 606.97 4.62
5.17 5.17
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 - -
2 Jack Shower 3.00 Bh 0.15 - -
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 - -
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 - -
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 - -
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 - -
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 - -
10 Memasang floor drain stainless 3.00 Bh 0.04 - -
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 - -
2.67 -
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 15(LIMA BELAS)
PRIODE : 13 Agustus 2018 - 19 Agustus 2018
RENCANA : 85.90 %
REALISASI : 78.63 %
DIVIASI : -7.27 %
PROGRES MINGGU INI 3.41 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
- - - 0% 0.35 (0.35)
- - - 0% 0.15 (0.15)
- - - 0% 0.73 (0.73)
- - - 0% 0.07 (0.07)
- - - 0% 0.09 (0.09)
- - - 0% 0.65 (0.65)
- - - 0% 0.07 (0.07)
- - - 0% 0.04 (0.04)
- - - 0% 0.52 (0.52)
- - 2.67 (2.67)
- - - 0% 0.28 (0.28)
- - - 0% 0.09 (0.09)
- - - 0% 0.24 (0.24)
-
- - - 0% 0.27 (0.27)
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% 0.23 (0.23)
- - - 0% 0.22 (0.22)
- - - 0% 0.12 (0.12)
- - - 0% 0.02 (0.02)
- - 1.48 (1.48)
- - - - 0% 0.24 (0.24)
113.07 1.12 113.07 1.12 30% 1.07 0.05
61.50 0.89 61.50 0.89 30% 0.85 0.04
- 261.00 4.48 86% 1.49 2.99
- - - 0% 0.07 (0.07)
2.02 6.49 3.72 2.78
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
- - - 0% 0.57 (0.57)
- - - 0% 0.20 (0.20)
- - - 0% 0.11 (0.11)
- - - 0% 0.23 (0.23)
- - - 0% 0.55 (0.55)
- - 1.66 (1.66)
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 36.70 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 303.49 5.06
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 5.72
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 2.90 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19 0.32 0.19
3 Ringbalk 15/20 2.75 M³ 1.33 2.75 1.33
4 Plat Sunscreen 3.60 M³ 2.97 3.60 2.97
5.68 5.68
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 73.40 0.56
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 606.97 4.62
5.17 5.17
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 - -
2 Jack Shower 3.00 Bh 0.15 - -
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 - -
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 - -
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 - -
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 - -
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 - -
10 Memasang floor drain stainless 3.00 Bh 0.04 - -
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 - -
2.67 -
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 16 ( ENAM BELAS)
PRIODE : 20 Agustus 2018 - 26 Agustus 2018
RENCANA : 88.82 %
REALISASI : 83.66 %
DIVIASI : -5.16 %
PROGRES MINGGU INI 5.03 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
- - - - 0% 0.35 (0.35)
131.91 1.31 244.98 2.43 65% 1.61 0.83
61.50 0.89 123.00 1.79 60% 1.28 0.51
- 261.00 4.48 86% 2.23 2.25
- - - 0% 0.07 (0.07)
2.21 8.70 5.54 3.16
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 36.70 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 303.49 5.06
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 5.72
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 2.90 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19 0.32 0.19
3 Ringbalk 15/20 2.75 M³ 1.33 2.75 1.33
4 Plat Sunscreen 3.60 M³ 2.97 3.60 2.97
5.68 5.68
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 73.40 0.56
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 606.97 4.62
5.17 5.17
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 0.90 0.11
2 Jack Shower 3.00 Bh 0.15 0.90 0.05
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 0.90 0.22
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 10.20 0.02
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 3.60 0.03
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 8.40 0.19
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 0.90 0.02
10 Memasang floor drain stainless 3.00 Bh 0.04 0.90 0.01
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 0.30 0.16
2.67 0.80
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 17 ( TUJUH BELAS)
PRIODE : 27 Agustus 2018 - 03 September 2018
RENCANA : 91.74 %
REALISASI : 86.96 %
DIVIASI : -4.78 %
PROGRES MINGGU INI 3.30 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
- - - - 0% 0.47 (0.47)
131.91 1.31 376.89 3.75 100% 2.14 1.61
- 123.00 1.79 60% 1.70 0.09
- 261.00 4.48 86% 2.97 1.50
- - - 0% 0.07 (0.07)
1.31 10.01 7.36 2.65
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 36.70 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 303.49 5.06
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 5.72
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 2.90 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19 0.32 0.19
3 Ringbalk 15/20 2.75 M³ 1.33 2.75 1.33
4 Plat Sunscreen 3.60 M³ 2.97 3.60 2.97
5.68 5.68
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 73.40 0.56
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 606.97 4.62
5.17 5.17
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 1.20 0.14
2 Jack Shower 3.00 Bh 0.15 1.20 0.06
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 1.20 0.29
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 13.60 0.03
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 4.80 0.04
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 11.20 0.26
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 1.20 0.03
10 Memasang floor drain stainless 3.00 Bh 0.04 1.20 0.02
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 0.40 0.21
2.67 1.07
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 18 ( DELAPAN BELAS)
PRIODE : 3 September-10 september 2018
RENCANA : 94.20 %
REALISASI : 88.57 %
DIVIASI : -5.63 %
PROGRES MINGGU INI 1.61 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
- - - 0% 0.56 (0.56)
- 376.89 3.75 100% 2.54 1.20
- 123.00 1.79 60% 2.02 (0.23)
- 261.00 4.48 86% 3.53 0.94
- - - 0% 0.07 (0.07)
- 10.01 8.73 1.28
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 36.70 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 303.49 5.06
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 5.72
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 2.90 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19 0.32 0.19
3 Ringbalk 15/20 2.75 M³ 1.33 2.75 1.33
4 Plat Sunscreen 3.60 M³ 2.97 3.60 2.97
5.68 5.68
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 73.40 0.56
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 606.97 4.62
5.17 5.17
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 1.50 0.18
2 Jack Shower 3.00 Bh 0.15 1.50 0.08
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 1.50 0.37
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 17.00 0.03
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 6.00 0.05
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 14.00 0.32
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 1.50 0.03
10 Memasang floor drain stainless 3.00 Bh 0.04 1.50 0.02
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 0.50 0.26
2.67 1.34
89.75
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 19 ( SEMBILAN BELAS)
PRIODE : 10 September-17 september 2018
RENCANA : 95.16 %
REALISASI : 89.75 %
DIVIASI : -5.41 %
PROGRES MINGGU INI 1.18 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
- - - 0% 0.56 (0.56)
- 376.89 3.75 100% 2.54 1.20
- 123.00 1.79 60% 2.02 (0.23)
- 261.00 4.48 86% 3.53 0.94
- - - 0% 0.07 (0.07)
- 10.01 8.73 1.28
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
95.16
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 36.70 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 303.49 5.06
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 5.72
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 2.90 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19 0.32 0.19
3 Ringbalk 15/20 2.75 M³ 1.33 2.75 1.33
4 Plat Sunscreen 3.60 M³ 2.97 3.60 2.97
5.68 5.68
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 73.40 0.56
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 606.97 4.62
5.17 5.17
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 2.10 0.25
2 Jack Shower 3.00 Bh 0.15 2.10 0.11
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 2.10 0.51
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 23.80 0.05
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 8.40 0.06
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 19.60 0.45
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 2.10 0.05
10 Memasang floor drain stainless 3.00 Bh 0.04 2.10 0.03
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 0.70 0.36
2.67 1.87
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 20 ( DUA PULUH)
0 PRIODE : 17 September-24 september 2018
RENCANA : 95.75 %
REALISASI : 90.58 %
DIVIASI : -5.17 %
PROGRES MINGGU INI 0.83 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
- - - 0% 0.56 (0.56)
- 376.89 3.75 100% 2.54 1.20
- 123.00 1.79 60% 2.02 (0.23)
- 261.00 4.48 86% 4.10 0.38
- - - 0% 0.07 (0.07)
- 10.01 9.29 0.72
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
90.58 95.75
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 36.70 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 303.49 5.06
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 5.72
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 2.90 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19 0.32 0.19
3 Ringbalk 15/20 2.75 M³ 1.33 2.75 1.33
4 Plat Sunscreen 3.60 M³ 2.97 3.60 2.97
5.68 5.68
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 73.40 0.56
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 606.97 4.62
5.17 5.17
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 2.70 0.32
2 Jack Shower 3.00 Bh 0.15 2.70 0.14
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 2.70 0.66
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 30.60 0.06
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 10.80 0.08
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 25.20 0.58
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 2.70 0.06
10 Memasang floor drain stainless 3.00 Bh 0.04 2.70 0.03
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 0.90 0.47
2.67 2.41
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 21 ( DUA PULUH SATU)
0 PRIODE : 24 September-01 Oktober 2018
RENCANA : 98.06 %
REALISASI : 92.47 %
DIVIASI : -5.59 %
PROGRES MINGGU INI 1.89 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
LOPORAN KEMAJUAN PEKE
KEGIATAN : RENOVASI KANTOR DAN PRASARANA KORAMIL 0902-07 TALISAYAN KODIM BERAU KALTIM ( PAKET-VII )
PEKERJAAN : RENOVASI MAKORAMIL 0902-07/TALISAYAN
LOKASI : MAKORAMIL 0902-07/TALISAYAN BERAU - KALTIM
TAHUN : 2018
IV PEKERJAAN DINDING
1 Pasang dinding bata merah 1/2 bata 1 : 2 36.70 M² 0.66 36.70 0.66
BOBOT MINGGU LALU
NO URAIAN PEKERJAAN VOL. SAT.
(%) BOBOT
VOL
(%)
2 Pasang dinding bata merah 1/2 bata 1 : 4 303.49 M² 5.06 303.49 5.06
Pasang rollag bata merah 1 : 4 (2lapis bata) 0.84 M³ 0.04 - -
5.76 5.72
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19 2.90 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19 0.32 0.19
3 Ringbalk 15/20 2.75 M³ 1.33 2.75 1.33
4 Plat Sunscreen 3.60 M³ 2.97 3.60 2.97
5.68 5.68
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56 73.40 0.56
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62 606.97 4.62
5.17 5.17
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35 3.00 0.35
2 Jack Shower 3.00 Bh 0.15 3.00 0.15
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73 3.00 0.73
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07 34.00 0.07
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09 12.00 0.09
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65 28.00 0.65
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07 3.00 0.07
10 Memasang floor drain stainless 3.00 Bh 0.04 3.00 0.04
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52 1.00 0.52
2.67 2.67
PENGAWAS LAPANGAN
ADI KAMARUDIN
Serma NRP 3910251940669
AN PEKERJAAN
PELAKSANA KEGIATAN : CV.PRASADA JAYA
MINGGU KE- : 22 ( DUA PULUH DUA)
PRIODE : 01 Oktober -03 Oktober 2018
RENCANA : 100.00 %
REALISASI : 100.00 %
DIVIASI : 0.00 %
PROGRES MINGGU INI 7.53 %
MINGGU INI SAMPAI MINGGU INI
RENCANA DIVIASI
BOBOT BOBOT KOMULATIF
VOL VOL
(%) (%)
c d e=(a+c) f g h i=(e-h)
CV.PRASADA JAYA
PELAKSANA KEGIATAN
GAZALI RACHMAN,ST
Site Manager
JADWAL PELAKS
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
BOBOT
NO URAIAN PEKERJAAN VOL. SAT.
(%) MEI 2018
IV PEKERJAAN DINDING
BOBOT
NO URAIAN PEKERJAAN VOL. SAT.
(%) MEI 2018
V PEKERJAAN BETON
1 Sloof beton uk. 15/30 cm 2.90 M³ 1.19
2 Kolom utama20/20 cm 0.32 M³ 0.19
3 Ringbalk 15/20 2.75 M³ 1.33
4 Plat Sunscreen 3.60 M³ 2.97
5.68 - - -
VI PEKERJAAN PLASTERAN
1 Plesteran 1 : 2 tbl. 15 mm 73.40 M² 0.56
2 Plasteran 1 : 4 tb. 15 mm 606.97 M² 4.62
5.17 - - -
X PEKERJAAN SANITASI
1 Memasang closet duduk/monoblok (tidak sederhana) 3.00 Bh 0.35
2 Jack Shower 3.00 Bh 0.15
3 Memasang bak mandi batu bata vol 0.3 m3 3.00 Bh 0.73
4 Memasang pipa PVC tipe AW dia. 1/2" 34.00 Bh 0.07
5 Memasang pipa PVC tipe AW dia. 2" 12.00 M¹ 0.09
6 Memasang pipa PVC tipe AW dia. 4" 28.00 M¹ 0.65
8 Memasang kran air dia. 3/4 atau 1/2 stainless 3.00 Bh 0.07
10 Memasang floor drain stainless 3.00 Bh 0.04
12 Membuat tanki septik tank kap. 1,7 x 0,85 m dalam 1,3 m 1.00 Bh 0.52
2.67 - - -
WAKTU PELAKSANAAN
2018 JUNI 2018 JULI 2018 AGUSTUS 2018 SEPTEMB
28-03 04-10 11-17 18-24 25-01 02-08 09-15 16-22 23-29 30-05 06-12 13-19 20-26 27-03
M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17
0.09
0.10
0.46
- 0.65
1.96 1.96
1.96 1.96
WAKTU PELAKSANAAN
2018 JUNI 2018 JULI 2018 AGUSTUS 2018 SEPTEMB
28-03 04-10 11-17 18-24 25-01 02-08 09-15 16-22 23-29 30-05 06-12 13-19 20-26 27-03
0.33 0.33
1.01 1.01 1.01 1.01 1.01
0.04
- 1.34 1.38 1.01 1.01 1.01
0.96 0.23
0.19
0.66 0.66
1.49 1.49
- 0.96 1.08 2.15 1.49
0.28 0.28
1.15 1.15 1.15 1.15
- - - 1.43 1.43 1.15 1.15
28-03 04-10 11-17 18-24 25-01 02-08 09-15 16-22 23-29 30-05 06-12 13-19 20-26 27-03
0.14 0.14
0.04 0.04
0.12 0.12
0.14 0.14
0.12 0.12
0.11 0.11
0.12
WAKTU PELAKSANAAN
2018 JUNI 2018 JULI 2018 AGUSTUS 2018 SEPTEMB
28-03 04-10 11-17 18-24 25-01 02-08 09-15 16-22 23-29 30-05 06-12 13-19 20-26 27-03
0.02
- - - - - - - 0.67 0.67 0.14 - - - -
3.57 1.23
0.15 0.28 0.28 0.28 0.28
0.14 0.14 0.14 0.14
WAKTU PELAKSANAAN
2018 JUNI 2018 JULI 2018 AGUSTUS 2018 SEPTEMB
28-03 04-10 11-17 18-24 25-01 02-08 09-15 16-22 23-29 30-05 06-12 13-19 20-26 27-03
- - - - - - 3.57 1.38 0.41 0.41 0.41 0.41 - -
1.53
0.31
0.22
0.11
1.70 3.00 5.11 1.18 - - - -
0.19
- - 4.06 3.00 5.11 1.18 - - - - - - - -
1.96 4.91 6.52 7.60 9.55 7.22 10.15 10.00 4.53 7.14 5.97 4.44 2.92 2.92
7.87 12.78 19.30 26.90 36.45 43.67 53.82 63.81 68.35 75.49 81.46 85.90 88.82 91.74
SEPTEMBER 2018 OKTOBER 2018
- - -
0.65 0.65
0.03
0.07
0.35 0.30 0.03 0.03
1.10 0.96 0.03 0.03 - -
0.10 0.10
0.03 0.03
0.02 0.02
0.04 0.04
- - - 0.19 0.19 -
0.14
SEPTEMBER 2018 OKTOBER 2018
- - - - - -
2.46 0.96 0.59 2.31 1.94 -
94.20 95.16 95.75 98.06 100.00 100.00
SLAMET PRIYADI
Direktur
SCHEDUL PELAKS
CV.P RASADA JAYA
GENERAL CONTRACTOR AND SUPPLIER
Alamat : Jl,Aw.Syahrani No .28/RT.26 ,Samarinda KALTIMANTAN TIMUR
Tlep/Fax :( 0541) 6252150
Kegiatan : Renovasi Kantor dan Prasarana Koramil 0902-07 Talisayan Kodim Berau Kaltim ( Paket-VII )
Pekerjaan :Renovasi Makoramil 0902-07/Talisayan
Lokasi : Makoramil 0902-07/Talisayan Berau - Kaltim
Tahun : 2018
BOBOT
NO URAIAN PEKERJAAN MEI 2018 JUNI 2018 JULI
(%) 07-13 14-20 21-27 28-03 04-10 11-17 18-24 25-01 02-08
III PEKERJAAN PASANGAN BATU KALI/BELAH 5.51 - 0.47 1.13 1.96 1.96
VII PEKERJAAN KUSEN DAN DAUN PINTU/JENDELA KAYU 5.59 0.50 0.50
(%) 07-13 14-20 21-27 28-03 04-10 11-17 18-24 25-01 02-08
Rencana 100.00 2.39 1.59 1.93 1.96 4.91 6.52 7.60 9.55 7.22
Komulatif Rencana - 2.39 3.98 5.92 7.87 12.78 19.30 26.90 36.45 43.67
Realisasi - 0.99 9.06 9.60 12.68 17.32 17.32 23.17 34.45 39.84
Diviasi (1.40) 5.08 3.69 4.81 4.54 (1.98) (3.73) (1.99) (3.83)
LAKSANAAN
WAKTU PELAKSANAAN
09-15 16-22 23-29 30-05 06-12 13-19 20-26 27-03 03-10 10-17 17-24 24-1 01-08 08-15
100
75
1.15
09-15 16-22 23-29 30-05 06-12 13-19 20-26 27-03 03-10 10-17 17-24 24-1 01-08 08-15
- 0.61 1.26 1.61 1.70 1.70 1.10 1.10 1.10 0.96 0.03 0.03 -
25
- - - - 0
10.15 10.00 4.53 7.14 5.97 4.44 2.92 2.92 2.46 0.96 0.59 2.31 1.94 -
53.82 63.81 68.35 75.49 81.46 85.90 88.82 91.74 94.20 95.16 95.75 98.06 100.00 100.00
49.31 50.66 61.22 64.42 75.22 78.63 83.66 86.96 88.57 89.75 90.58 92.47 100.00 100.00
(4.51) (13.16) (7.13) (11.07) (6.25) (7.27) (5.16) (4.78) (5.63) (5.41) (5.17) (5.59) - -
CV.PRASADA JAYA
PELAKSANA KEGIATAN
SLAMET PRIYADI
WAKTU PELAKSANAAN
09-15 16-22 23-29 30-05 06-12 13-19 20-26 27-03 03-10 10-17 17-24 24-1 01-08 08-15
DIREKTUR
HARGA
NO URAIAN QTY SAT
SATUAN
1 KANTOR MAKORAMIL
Pintu Type P1 2.00 Bh 950,000.00
Pintu Type P2 5.00 Bh 750,000.00
Pintu Type P3 3.00 Bh 750,000.00
Jendela Type J1 2.00 Bh 350,000.00
Jendela Type J2 18.00 Bh 350,000.00
Boven P2 5.00 Bh 250,000.00
Boven J1 2.00 Bh 250,000.00
Boven J2 18.00 Bh 250,000.00
TOTAL
JUMLAH
KETERANGAN
HARGA
1,900,000.00 =0.60*1.85*(2)Kaca 8 mm
3,750,000.00
2,250,000.00
700,000.00 =1.65*0.55*(2) Kaca 5 mm
6,300,000.00 =1.25*0.5*(18) Kaca 5 mm
1,250,000.00 =0.8*0.2*(5) Kaca 5 mm
500,000.00 =0.45*0.2*(2) Kaca 5 mm
4,500,000.00 =0.4*0.2*(18) Kaca 5 mm
Rp 21,150,000.00
HARGA
NO URAIAN QTY SAT
SATUAN
1 RUMDIS TYPE 70
Pintu Type PJ1 3.00 Bh Rp 650,000.00
Pintu Type P2 3.00 Bh Rp 650,000.00
Pintu Type P3 2.00 Bh Rp 650,000.00
2 RUMDIS TYPE 45
Pintu PJ1 4.00 Bh Rp 650,000.00
Pintu P2 4.00 Bh Rp 650,000.00
Pintu P3 2.00 Bh Rp 650,000.00
3 RUMDIS TYPE 45 ( 2)
Pintu PJ1 4.00 Bh Rp 650,000.00
Pintu P2 4.00 Bh Rp 650,000.00
Pintu P3 2.00 Bh Rp 650,000.00
Rp 1,950,000.00
Rp 1,950,000.00 Kamar Tidur
Rp 1,300,000.00 Kamar Mandi
Rp 2,600,000.00
Rp 2,600,000.00
Rp 1,300,000.00
Rp 2,600,000.00
Rp 2,600,000.00
Rp 1,300,000.00