Anda di halaman 1dari 6

INSTITUTE OF TECHNOLOGY, NIRMA UNIVERSITY, AHMEDABAD – 382 481, 08-10 DECEMBER, 2011 1

Comparative Study between PHA (Process


Hazard Analysis) Evaluation Techniques for
Chemical Process Industries
Tapan Shukla, Parin D. Shah

Abstract-- Process Hazard Analysis (PHA) and Risk temperatures, high pressures, quantity of material used
Assessment Techniques are two of the most important etc. Each of these hazards impacts the overall process. A
elements of the PSM (Process Safety Management). The pursuit of safety is largely a matter of identifying hazards,
PSM allows the use of different analysis methods and eliminating them where possible or otherwise protecting
preventions of hazards in process industries, but the selected
against their consequences. Often two hazards need to be
method must be based on the process being analyzed.
HAZard and Operability studies (HAZOP) and Quantitative present simultaneously to cause a major accident. In Fig.
Risk Assessment (QRA) are part of the PHAs. HAZOP is 1 the techniques for identifying hazards and the
used to identify the hazards presents in the process and plant techniques for assessing those hazards have been shown
designing whereas QRA is a tool which gives us [2]. The best known measure for safety is risk, which is
quantification of hazards identified during the HAZOP defined as the possibility of loss. The problem of
process. QRA can also assess risk for the worst situation that awareness of risk can be seen as one of failure of
can be created by a process plant. In general there are lot of communication and of mismanagement. Risk by the
misconceptions and misunderstandings about applicability Chartered Insurance Institute (1974) is the mathematical
of HAZOP and QRA in industrial practise. This paper
probability of a specified undesired event occurring, in
compares results of HAZOP & QRA applied on hypothetical
case study. This comparison reveals difference between specified circumstances or within a specified period. In a
HAZOP and QRA for the discussed hypothetical study and process plant the losses may be such as damage to
it can be applied for all chemical process industries also. equipment, a loss of production or an environmental
damage as well as an injury or a death. Risk involves two
Key Words: HAZOP, QRA, Hazard, Risk, Process Hazard measurable parameters consequence and probability.
Evaluation Techniques, Process Safety Tools Some events are more probable to occur than others, but a
unique consequence of the sequence of events cannot be
I. INTRODUCTION predicted.
S afety is a concept covering hazard identification, risk
assessment and accident prevention. Safety should III. HAZOP
always come first and remain so despite of costs. Good
design and forethought can often bring increased safety at Hazop refers to HAZard and OPerability studies. HAZOP
less cost [1]. is a structured and systematic technique for examining a
defined system, with the objective of identifying potential
PSM is a part of safety management, which focuses hazards in the system. The hazards involved may include
on the concerns of major hazards impacting safety, both those essentially relevant only to the immediate area
environmental damage and business losses. Oil & Gas of the system and those with a much wider sphere of
companies are significant users of PSM (Process Safety influence, e.g. some environmental hazards.
Management) methods, particularly where there are
hazardous processes or large inventories of flammable or
toxic materials. Regulators expect operators of volatile
plants to implement measures to ensure that their plants
are operated and maintained in a safe manner. PSM
techniques are numerous - from process screening and
concept selection, through hazard identification,
consequence evaluation, risk assessment, ALARP study,
pre start-up action response auditing, to inspection and
auditing during operation. A hazard is a condition with the
potential of causing an injury or damage. A chemical
process normally has a number of potential hazards, for
example raw material and intermediate toxicity and Fig. 1: Methods of identifying and Assessing Hazards
reactivity, energy release from chemical reactions, high
INSTITUTE OF TECHNOLOGY, NIRMA UNIVERSITY, AHMEDABAD – 382 481, 08-10 DECEMBER, 2011 2

Identifying potential operability problems with the system • The two-dimensional nature of risk (likelihood and
and in particular identifying causes of operational consequence) has to be recognised for effective risk
disturbances and production deviations likely to lead to management.
nonconforming products. An important benefit of the • Not only the experts' world-view of risk, but that of the
Hazop study is resulting knowledge, obtained by non-expert should be given due consideration in the risk
identifying potential hazards and operability problems in a management process, if the latter have an input into
structured and systematic manner, is of great assistance in decision making.
determining appropriate remedial measures. A • A decision made based on risk assessment, followed by
characteristic feature of a HAZOP study is the the implementation of a risk management process would
“examination session” during which a multidisciplinary go a long way to ensuring project success.
team under the guidance of a study leader systematically
examines all relevant parts of a design or system. It This raises the question:
identifies deviations from the system design intent
utilizing a core set of guide words. The technique aims to 'How to know that a risk is low enough to be
stimulate the imagination of participants in a systematic acceptable? In other words, how low is low enough?'
way to identify hazards and operability problems. HAZOP
should be seen as an enhancement to sound design using To answer this question, some measures of risk
experience-based approaches such as codes of practice are required, so that relative risks can be compared [5].
rather than a substitute for such approaches [3].
The overall aims to which any HAZOP Study Risk measures can range from the purely
should be addressed are: qualitative to fully quantitative, accompanied by
uncertainty analysis. In most cases of risk management,
To identify all deviations from the way the design
measures are applied along a continuum in order to ensure
intended to work, their causes and all the hazards and
minimum work for the maximum effect. It is important
operability problems associated with these deviations.
that appropriate measures are used throughout the process
To decide whether action is required to control the hazard life cycle and within a particular project. It is also
or the operability problem, and if so, to identify the ways important that the measures used in a project are
in which the problems can be solved. commensurate with the stage of analysis and the level of
understanding. Fig. 2 shows the risk measurement
To identify cases where a decision cannot be taken
continuum with some examples of techniques in each
immediately and to decide on what information or action
class. Chemical process Quantitative Risk Analysis
is required.
(QRA) is a methodology designed to provide management
To ensure actions decided are followed through (i. e. with a tool to help evaluate overall process safety in the
HAZOP Close-out report) [4]. chemical process industry (CPI). Management systems
such as engineering codes, checklists and process safety
IV. ASSESSING THE RISK (QRA) management (PSM) provide layers of protection against
accidents. However, the potential for serious incidents
Risk is defined by the likelihood of an undesired cannot be totally eliminated. QRA provides a quantitative
event within a specified period. It is a complex function of method to evaluate risk and to identify areas for cost-
probability, consequences and vulnerability. effective risk reduction. The QRA methodology has
Why Risk Assessment is required? evolved since the early 1980s from its roots in the nuclear,
• All activities are associated with some risk. aerospace and electronics industries. The term "Chemical
• In order to make a commercial enterprise successful, it is Process Quantitative Risk Analysis"
necessary to identify and manage the risks.
is used throughout this book to emphasize the features of
this methodology as practiced in the chemical,
petrochemical, and oil processing industries. QRA
enables the engineer to evaluate risk. Individual
contributions to the overall risk from a process can be
identified and prioritized. A range of risk reduction
measures can be applied to the major hazard contributors
and assessed using cost-benefit methods. Comparison of
risk reduction strategies is a relative application of
Figure 2: Risk funnelling CPQRA. At each stage of increasing safety (decreasing
risk), the associated changes may be evaluated to see if
INSTITUTE OF TECHNOLOGY, NIRMA UNIVERSITY, AHMEDABAD – 382 481, 08-10 DECEMBER, 2011 3

they are worthwhile and cost-effective. Some those concerned, injury or damage will result next
organizations also use CPQRA in an absolute sense to time.
confirm that specific risk targets are achieved. Further risk e. Hazop and QRA can essentially be carried out at any
reduction, beyond such targets, may still be appropriate stage of a project. This need not be always true. In
where it can be accomplished in a cost-effective manner fact, in ICI, from where the technique originated,
[6]. There are different phases of a plant when risk 'Hazop and QRA were used to form a part of a series
management can be applied on it. But with different of six 'hazard studies': (i) Exploratory phase (ii) Flow
phases its applicability, cost and effectiveness varies with sheet phase (iii) Detailed design (iv) Construction (v)
reference to the phase on which it is being applied. Commissioning (vi) Post-commissioning The
Possible phases where Risk Management can be applied rigorous use of the Hazard and operability studies was
are with different phases its applicability, cost and carried out during the stage (iii), i.e. 'Detailed design'.
effectiveness varies with reference to the phase on which In other words, an organization can develop a strategy
it is being applied. Possible phases where Risk or a definite policy as to when and how to use the
Management can be applied are shown in Fig. 3 below. technique. Therefore, the thumb rule that the technique
must essentially be used at any stage of the project need
V. COMPARISON BETWEEN HAZOP AND QRA not always be true[9].
REVEALING SOME MISCONCEPTIONS. f. Hazop and QRA technique need not be rigorously
followed for computer-controlled plants. In computer-
a. 'Hazop and QRA' are two sides of a coin and are more controlled plants, the instructions to the computer (the
or less synonymous. 'Hazop and QRA are often applications software) should be studied as well as the
confused. The above figure 1 makes the difference line diagrams. For example, if the computer is
clear[7]. instructed to take a certain action when the
b. Once the Hazop and QRA exercise is carried out, temperature rises, the Hazop team should consider the
management competence is irrelevant and can be possible consequences of this action as well as the
overlooked. The assumption while utilising the consequences of the computer failing to take action. In
sophisticated technique of 'Hazop and QRA is that the a batch plant, the consequences may be different at
plant will be operated and maintained in the manner each stage of the batch. On a continuous plant, the
assumed by the design team and in accordance with consequences may be different during the various
good management and engineering practices. There is phases of the process, such as start-ups, shut-downs,
also another hidden assumption, that the protective catalyst regeneration, etc. Dangerous incidents have
systems will be tested regularly and repaired promptly, occurred because the 'Design and Operating Teams'
whenever necessary. If these assumptions are not true, assumed that the computer would always take care of
then 'Hazop and QRA are a waste of time. It is no use alarm situations and they need not consider in detail
identifying hazards or estimating their probability, if the consequences of each action at each stage.
no one wants to do anything about them. It is no use g. The team leader can be effective, if he is an expert in
installing trips and alarms, if no one is going to use or process engineering. It is possible for a team to get
maintain them. The time spent on a 'Hazop and QRA carried away by enthusiasm and install expensive
would be better spent on bringing the safety equipment to guard against unlikely hazards. The team
consciousness of employees and management up to leader must counter this by asking how often the
standard. This aspect is very important for developing hazard will occur and what will be the consequences.
countries like India [8]. The most effective team leader must therefore not only
c. By using the Hazop and QRA technique, we will be trained in 'Hazop' but also in 'QRA [10].
foresee every hazard and accidents will be eliminated. h. Since plant people do not have time, a design
Despite all our efforts, we shall fail to foresee every contractor can effectively carry out 'Hazop'. The user
hazard and some will result in accidents. This of the plant must be involved in the Hazop exercise
limitation must be clearly borne in mind while using because it will give the operating staff an
the 'Hazop and QRA technique. understanding of the reasons for the various design
d. Once hazards are identified by using Hazop technique, features and help them write the operating instructions.
accident history is irrelevant. As stated earlier, despite The only effective team is one that owns the problem.
all our efforts, we shall fail to foresee every hazard and The user is responsible for changes in the procedure.
some will result in accidents. One must, however, Hence, he should be involved in the 'Hazop' exercise
remember that people should learn from these along with the design contractor. However, the design
accidents. People should analyse not only the contractor cannot be a substitute for the plant user.
accidents, which have resulted in serious injury or i. 9. Leave it until the Hazop. Whenever someone
damage, but also from those which have not, e.g. leaks suggests a change in design, the design engineers react
that do not ignite. If these 'near misses' are not saying, 'Don't bother now. There will be a Hazop later
investigated and the lessons learned are not known to on. Let us talk about it then'. This is not a correct
INSTITUTE OF TECHNOLOGY, NIRMA UNIVERSITY, AHMEDABAD – 382 481, 08-10 DECEMBER, 2011 4

approach. A Hazop should be a final check on a temperature, level, concentration, composition,


basically sound design to make sure that no unforeseen viscosity etc. Here others parameter also can be
effects have been overlooked. It should not replace the selected but for the example study initiation flow
normal consultations and discussions during the design parameter is selected.
development; a Hazop meeting is not the right place 2. After selecting the parameter next step will be to
for redesigning the plant. applying the guidewords (i.e. Less, More, No,
j. 10. Computers can carry out a Hazop. Hazop is a Reverse etc.) Here less flow of TBC from tank 1 to
creative exercise. Factors such as intuition and flair vessel V 1 through the pump and strainer is being
play a very large part in thinking of the team members. considered.
The knowledge used in a Hazop is broad and deep. 3. Now next step is finding the cause. This is where the
The expert systems are suitable for narrow and deep brainstorming comes into the picture. After
knowledge. Hence, computers can certainly be used as discussion with the HAZOP team causes were found
an aid in Hazop studies. However, they presently for selected parameter deviation. In this case causes
cannot substitute a 'Hazop team'. of less flow are choking or pump strainer or pump
malfunctioning.
VI. COMPARISON BETWEEN HAZOP AND QRA ON A 4. After determining the cause it is found that what will
HYPOTHETICAL CASE STUDY
be the consequence if the cause takes place. Here the
consequence will be less mixing of TBC in line
mixture with butadiene resulting in less composition
of TBC in Butadiene storage. So as explained in
system description above less TBC can lead to self-
polymerization BD storage and further lead to over
pressurization and explosion. So maintaining TBC
appropriate composition in TBC is very critical.
5. Next step is evaluating the safeguards already
provided in the system we assume that there is a PDI
is already provided across the strainer to know
choking of strainer. This is the only safeguard
currently. This completes the study for one deviation
of selected parameter which in our case is less Flow.
Further study can be continued by discussing others
Fig. 3: A sample system of mixing TBC in Butadiene (Note that this is
deviation such as more flow, no flow, reverse flow
purely representational, and not intended to illustrate an actual system.)
etc. A sample worksheet is shown in Fig. 4, which is
Fig. 3 shows a simple system of mixing TBC (4- normally used for the recording of HAZOP
t-p-butyl catechol) in to butadiene. TBC is mixed into proceedings. Conclusion from this study is mentioned
Butadiene to prevent self-polymerization of Butadiene at the end of the article by comparing it with the
while its storage. Butadiene has tendency of self- conclusions of QRA of the same system [11].
polymerization whenever it comes into contact of oxygen.
But in the mixture of TBC and Butadiene, TBC acts as an This was about HAZOP, but now if QRA is to be
Oxygen Scavenger which does not allows butadiene to applied on the same above scenario then a different
undergo self-polymerization. Now, when butadiene approach has to be taken. Unlike HAZOP where
undergoes self-polymerization under a closed storage concentration was on finding the root cause of the
vessel, temperature in the vessel will increase due to problem. But QRA starts with the worst possible
exothermic nature of the polymerization process. This will consequence and studying its impacts, affecting area
also lead to pressurization of the vessel. After certain along with Risk Identification. When talking about Risk,
extent of pressure rise if pressure reduction measures are it by default considers likelihood of the accident as well as
not taken then pressure in vessel may go beyond the severity. Both are taken care during QRA studies. Here to
design pressure of the storage vessel and the final carry out QRA, Phast Risk Micro software is used which
consequences will be catastrophic rupture of the storage is developed by DNV AS Ltd., and which is licensed to
vessel leading to explosion and fire in the storage facility. M/S ZEPPELIN SYSTEMS INDIA LTD. To do risk
Now to apply HAZOP technique on the system identification of this scenario some assumption have been
which is shown in Figure 4 leads we have to select a made which were required for software inputs. Those
parameter first to start with. Step by step methodology assumptions are listed below
and learning from it are described as below: A random site layout has been taken here in which
1. Selecting a parameter from list of parameters location of BD storage tank is assumed.
provided by UK ICI, which are flow, pressure, All storage parameters and condition are assumed.
INSTITUTE OF TECHNOLOGY, NIRMA UNIVERSITY, AHMEDABAD – 382 481, 08-10 DECEMBER, 2011 5

An average whether category and random wind Second suggestion will be addition of duplex strainer
speed are assumed for the QRA results. so that if the PDI shows high PD (pressure difference)
Population data inside as well as around the site. operator can immediately go and isolate that choked
Failure frequency of the BD tank V 1. strainer and takes second strainer in line.
QRA recommendations: Fig 5 shows explosion contours.
Fig. 6 and 7 shows results of QRA done by the Phast Risk How much pressure will be experienced at a particular
software. Though here results are shown only in pictorial distance from the location of explosion if the BD storage
form, in practise a theoretical report which includes other tank explodes. And fig 6 is the risk contour, which shows
information like Conc v/s Distance data, radiation level individual risk. It means probability of one fatality with
distances, explosion overpressure distances, individual respect to duration of one year in and around the plant
risk, societal risk, toxic exposure distances, dispersion location. Whereas Fig 7 shows F-N curve representing
data, discharge data is also given with the QRA report. societal risks. The main recommendations from this study
This QRA report helps to mitigate the consequence and are
reduce the risk associated with the process plant. Looking at the explosion contour it can be seen that
the control room is coming within the overpressure
VII. DISSCUSION FROM RESULTS OF BOTH STUDIES. zone of 0.2068 bar which is the level at which heavy
damage to structures and 100% fatality is expected.
HAZOP recommendation: HAZOP always focuses on Therefore it is recommended that the control room
removing the cause of the consequences rather than should be shifted to a safer location.
applying mitigation measures. Looking at the Fireball contour it can be seen that the
In this case root cause of BD vessel explosion was admin building and the control room are falling in the
because of strainer choking. The first thing can be radiation zone of 4 KW/m2. At this level of radiation
done is to change the location of the strainer and take no significant burns are expected for the human body.
it to upstream of the TBC tank T 1. So we can remove
impurities at the inlet of tank only so it can’t come in
pump suction.

Figure 4: Sample worksheet for the recording of the HAZOP proceedings


INSTITUTE OF TECHNOLOGY, NIRMA UNIVERSITY, AHMEDABAD – 382 481, 08-10 DECEMBER, 2011 6

Looking at the overall risk contour it can be seen


that the maximum risk level that the plant is exposed
to due to the failure of Butadiene Tank is in the
range of 10-7 per average year which is the
acceptable level of risk according to the UK HSE’s
Risk Acceptance Criteria.
F-N curve shows that the societal risk is partially in
the acceptable region and partially in the ALAP
region.

VIII. CONCLUSIONS
A result of HAZOP identifies the hazards whereas a
result of QRA assesses the hazards.
HAZOP is a preferred technique and almost being
applied on every project, whereas QRA is being applied
on selective projects, especially where it is a legal
Fig. 5: Explosion Contours requirement.
HAZOP is a qualitative technique where QRA as its
name itself tells, it is a quantitative technique
HAZOP is a tool which requires a multi-disciplinary
team to carry out it, whereas QRA requires only one or
two engineers with good knowledge of QRA software.

IX. REFERENCES

[1] DOE HANDBOOK of CHEMICAL PROCESS HAZARDS


ANALYSIS; DOE-HDBK-1100-2004 August 2004, U.S.
Department of Energy, Washington, D.C. 20585, February 1996.
[2] Heikkilä; AnnaMari; “Inherent safety in process plant design An
indexbasedApproach;” TECHNICAL RESEARCH CENTRE
OF FINLANDESPOO 1999.
[3] Hazard and Operability Studies (HAZOP Studies) – Application
Guide. Hazop guideline BS IEC 61882. International Electro
technical Commission.
[4] Kletz, T.A., “HAZOP & HAZAN: Identifying and Assessing
Process Industry Hazards,” Fourth ed. Institution of Chemical
Engineers, Rugby, UK, 1999.
Fig. 6: Risk contours [5] Cameron, I. T.; “PROCESS SYSTEMS RISK
MANAGEMENT”; Department of Chemical Engineering;
Computer Aided Process Engineering Centre University of
Queensland; Brisbane, Australia
[6] GUIDELINES FOR Chemical Process Quantitative Risk
Analysis; SECOND EDITION, CENTER FOR CHEMICAL
PROCESS SAFETY of the AMERICAN INSTITUTE OF
CHEMICAL ENGINEERS;3 Park Avenue New York, New
York 10016-5991
[7] Raghu. Raman; “Safety Engineering and Risk Management”
Kellog Brown & Root Pty Ltd; ELSEVIER ACADEMIC
PRESS;Sydney, Australia 2005
[8] Gujar A. M.; “Myths of Hazop and Hazan Myths of Hazop and
Hazan”; J. Loss Prey. Process Ind. Vol. 9. No. 6. pp. 357-361.
1996
[9] 'Loss Prevention Bulletin', Issues 121, 122, 123. Institute of
Chemical Engineers, UK.
[10] P.A.M. Ujit de Haag, B.J.M. Ale, “Guidelines For Quantitative
Risk Assessment”, PGS 3 edition, Ministry Of Netherlands,
December 2005.
[11] Guidelines For Safety Studies, DOC no: APS-SSP-301;
Fig. 7: F-N Curve Diagram Zeppelin Systems India Pvt. Ltd.

Anda mungkin juga menyukai