HARGA

No. URAIAN SATUAN VOLUME HARGA


SATUAN

(Rp) (Rp)

D-01 1 M3 Membuat Beton Tumbuk adk 1pc:3ps:5kr

Semen
Kg 218.0000 1,548.00 337,464.00
Portland

Pasir Beton M3 0.5200 255,400.00 132,808.00

Batu Pecah
M3 0.8700 218,268.00 189,893.16
Mesin 2/3

Pekerja Oh 1.6500 67,000.00 110,550.00

Tukang Batu Oh 0.2500 70,000.00 17,500.00

Kepala Tukang Oh 0.0250 80,000.00 2,000.00

Mandor Oh 0.0800 85,000.00 6,800.00

Jumlah 797,015.16

797,015.00

D-02 1 M3 Membuat Beton Tumbuk adk 1pc:3ps:6kr

Semen
Kg 197.0000 1,548.00 304,956.00
Portland

Pasir Beton M3 0.4700 255,400.00 120,038.00


Batu Pecah
M3 0.9400 218,268.00 205,171.92
Mesin 2/3

Pekerja Oh 1.6500 67,000.00 110,550.00

Tukang Batu Oh 0.2500 70,000.00 17,500.00

Kepala Tukang Oh 0.0250 80,000.00 2,000.00

Mandor Oh 0.0800 85,000.00 6,800.00

Jumlah 767,015.92

767,016.00

D-03 1 M3 Membuat Beton Tumbuk 1pc:2ps:3kr

Semen
Kg 336.0000 1,548.00 520,128.00
Portland

Pasir Beton M3 0.5400 255,400.00 137,916.00

Batu Pecah
M3 0.8100 218,268.00 176,797.08
Mesin 2/3

Pekerja Oh 2.0000 67,000.00 134,000.00

Tukang Batu Oh 0.3500 70,000.00 24,500.00

Kepala Tukang Oh 0.0350 80,000.00 2,800.00

Mandor Oh 1.0000 85,000.00 85,000.00

Jumlah 1,081,141.08
1,081,141.00

D-04 1 M3 Membuat Beton Tumbuk adk 1pc:2ps:4kr

Semen
Kg 291.0000 1,548.00 450,468.00
Portland

Pasir Beton M3 0.4700 255,400.00 120,038.00

Batu Pecah
M3 0.9300 218,268.00 202,989.24
Mesin 2/3

Pekerja Oh 2.0000 67,000.00 134,000.00

Tukang Batu Oh 0.3500 70,000.00 24,500.00

Kepala Tukang Oh 0.0350 80,000.00 2,800.00

Mandor Oh 1.0000 85,000.00 85,000.00

Jumlah 1,019,795.24

1,019,795.00

D-05 1 Kg Pembesian Dengan Besi Polos/ulir

Besi Beton (
Kg 1.0500 16,500.00 17,325.00
Polos / Ulir )

Kawat Beton Kg 0.0150 30,500.00 457.50

Pekerja Oh 0.0070 67,000.00 469.00

Tukang Besi Oh 0.0070 70,000.00 490.00


Kepala Tukang Oh 0.0007 80,000.00 56.00

Mandor Oh 0.0003 85,000.00 25.50

Jumlah 18,823.00

18,823.00

D-06 1 M2 Pasang Bekesting Untuk Pondasi

Kayu papan
M3 0.0400 2,950,000.00 118,000.00
terentang

Paku Biasa 2″ –
Kg 0.3000 24,000.00 7,200.00
5″

Pekerja Oh 0.3000 67,000.00 20,100.00

Tukang Kayu Oh 0.2600 70,000.00 18,200.00

Kepala Tukang Oh 0.0260 80,000.00 2,080.00

Mandor Oh 0.0050 85,000.00 425.00

Jumlah 166,005.00

166,005.00

D-07 1 M2 Pasang Bekisting Untuk Sloof

Kayu papan
M3 0.0450 2,950,000.00 132,750.00
terentang
Paku Biasa 2″ –
Kg 0.3000 24,000.00 7,200.00
5″

Pekerja Oh 0.3000 67,000.00 20,100.00

Tukang Kayu Oh 0.2600 70,000.00 18,200.00

Kepala Tukang Oh 0.0260 80,000.00 2,080.00

Mandor Oh 0.0050 85,000.00 425.00

Jumlah 180,755.00

180,755.00

D-08

Kayu papan
M3 0.0400 2,950,000.00 118,000.00
terentang

Paku Biasa 2″ –
Kg 0.4000 24,000.00 9,600.00
5″

Kayu balok
M3 0.0150 2,705,000.00 40,575.00
terentang

MultiPlek 9 mm
Lbr 0.3500 215,000.00 75,250.00
120 x 240

Dolken Ø-8-
Btg 2.0000 30,800.00 61,600.00
10/4m

Pekerja Oh 0.3000 67,000.00 20,100.00

Tukang Kayu Oh 0.3300 70,000.00 23,100.00


Kepala Tukang Oh 0.0330 80,000.00 2,640.00

Mandor Oh 0.0060 85,000.00 510.00

Jumlah 351,375.00

351,375.00

D-09 1 M2 Pasang Bekesting Untuk Balok

Kayu papan
M3 0.0400 2,950,000.00 118,000.00
terentang

Paku Biasa 2″ –
Kg 0.4000 24,000.00 9,600.00
5″

Kayu balok
M3 0.0180 2,705,000.00 48,690.00
terentang

MultiPlek 9 mm
Lbr 0.3500 215,000.00 75,250.00
120 x 240

Dolken Ø-8-
Btg 2.0000 30,800.00 61,600.00
10/4m

Pekerja Oh 0.3000 67,000.00 20,100.00

Tukang Kayu Oh 0.3300 70,000.00 23,100.00

Kepala Tukang Oh 0.0330 80,000.00 2,640.00

Mandor Oh 0.0060 85,000.00 510.00

Jumlah 359,490.00
359,490.00

D-10 1 M2 Pasang Bekesting Untuk Lantai

Kayu papan
M3 0.0400 2,950,000.00 118,000.00
terentang

Paku Biasa 2″ –
Kg 0.4000 24,000.00 9,600.00
5″

Minyak
Ltr 0.2000 45,000.00 9,000.00
Bekisting

Kayu balok
M3 0.0150 2,705,000.00 40,575.00
terentang

MultiPlek 9 mm
Lbr 0.3500 215,000.00 75,250.00
120 x 240

Dolken Ø-8-
Btg 6.0000 30,800.00 184,800.00
10/4m

Pekerja Oh 0.3000 67,000.00 20,100.00

Tukang Kayu Oh 0.3300 70,000.00 23,100.00

Kepala Tukang Oh 0.0330 80,000.00 2,640.00

Mandor Oh 0.0060 85,000.00 510.00

Jumlah 483,575.00

Kayu papan
M3 0.0300 2,950,000.00 88,500.00
terentang
Paku Biasa 2″ –
Kg 0.4000 24,000.00 9,600.00
5″

Kayu balok
M3 0.0150 2,705,000.00 40,575.00
terentang

MultiPlek 9 mm
Lbr 0.3500 215,000.00 75,250.00
120 x 240

Dolken Ø-8-
Btg 2.0000 30,800.00 61,600.00
10/4m

Pekerja Oh 0.3200 67,000.00 21,440.00

Tukang Kayu Oh 0.3300 70,000.00 23,100.00

Kepala Tukang Oh 0.0330 80,000.00 2,640.00

Mandor Oh 0.0060 85,000.00 510.00

Jumlah 323,215.00

323,215.00

D-12 1 M3 Membuat Beton Cor Mutu K-225

Semen
Kg 388.0000 1,548.00 600,624.00
Portland

Pasir Beton m3 0.6500 255,400.00 166,010.00

Batu Pecah
M3 0.6500 218,268.00 141,874.20
Mesin 2/3

Air ltr 215.0000 3,500.00 752,500.00


Pekerja Oh 6.0000 67,000.00 402,000.00

Tukang Batu Oh 1.0000 70,000.00 70,000.00

Kepala Tukang Oh 0.1000 80,000.00 8,000.00

Mandor Oh 0.3000 85,000.00 25,500.00

Jumlah 2,166,508.20

2,166,508.00

D-13 1 M3 Membuat Beton Cor Mutu K-275

Semen
Kg 400.0000 1,548.00 619,200.00
Portland

Pasir Beton M3 0.4000 255,400.00 102,160.00

Koral Beton 2/3 M3 0.8200 218,268.00 178,979.76

Air ltr 215.0000 3,500.00 752,500.00

Pekerja Oh 6.0000 67,000.00 402,000.00

Tukang Batu Oh 1.0000 70,000.00 70,000.00

Kepala Tukang Oh 0.1000 80,000.00 8,000.00

Mandor Oh 0.3000 85,000.00 25,500.00

Jumlah 2,158,339.76
2,158,340.00

D-14 1 M3 Pondasi Beton Tulang (150 kg besi + bekisting)

Kayu papan
M3 0.2000 2,950,000.00 590,000.00
terentang

Paku Biasa 2″ –
Kg 1.5000 24,000.00 36,000.00
5″

Besi beton Kg 150.0000 16,500.00 2,475,000.00

Kawat Beton Kg 2.2500 30,500.00 68,625.00

Semen
Kg 323.0000 1,548.00 500,004.00
Portland

Pasir Beton M3 0.5200 255,400.00 132,808.00

Koral Beton 2/3 M3 0.7800 218,268.00 170,249.04

Pekerja Oh 3.9000 67,000.00 261,300.00

Tukang Batu Oh 0.3500 70,000.00 24,500.00

Tukang Kayu Oh 1.0400 70,000.00 72,800.00

Tukang Besi Oh 1.0500 70,000.00 73,500.00

Kepala Tukang Oh 0.2450 80,000.00 19,600.00

Mandor Oh 0.1650 85,000.00 14,025.00

Jumlah 4,438,411.04
4,438,411.00

D-15 1 M3 Sloof Beton Tulang 15/20, (180 kg besi + bekisting)

Kayu papan
M3 0.2700 2,950,000.00 796,500.00
terentang

Paku biasa 2″ –
Kg 2.0000 24,000.00 48,000.00
5″.

Besi beton Kg 180.0000 16,500.00 2,970,000.00

Kawat beton Kg 3.0000 30,500.00 91,500.00

Semen portland Kg 323.0000 1,548.00 500,004.00

Pasir beton M3 0.5200 255,400.00 132,808.00

Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3

Pekerja Oh 4.8500 67,000.00 324,950.00

Tukang batu Oh 0.3500 70,000.00 24,500.00

Tukang kayu Oh 1.5600 70,000.00 109,200.00

Tukang besi Oh 1.4000 70,000.00 98,000.00

Kepala tukang Oh 0.3310 80,000.00 26,480.00

Mandor Oh 0.1700 85,000.00 14,450.00

Jumlah 5,306,641.04
5,306,640.00

D- 1 M3 Sloof Beton Tulang 15/18 ( 201 kg besi + bekisting ) 6 dia 10 – Dia


15.Hr 8 – 15 Cm.

Kayu papan
M3 0.2700 2,950,000.00 796,500.00
terentang

Paku biasa 2″ –
Kg 2.0000 24,000.00 48,000.00
5″.

Besi beton Kg 201.0000 16,500.00 3,316,500.00

Kawat beton Kg 3.0000 30,500.00 91,500.00

Semen portland Kg 323.0000 1,548.00 500,004.00

Pasir beton M3 0.5200 255,400.00 132,808.00

Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3

Pekerja Oh 4.8500 67,000.00 324,950.00

Tukang Batu Oh 0.3500 70,000.00 24,500.00

Tukang Kayu Oh 1.5600 70,000.00 109,200.00

Tukang Besi Oh 1.4000 70,000.00 98,000.00

Kepala Tukang Oh 0.3310 80,000.00 26,480.00

Mandor Oh 0.1700 85,000.00 14,450.00


Jumlah 5,653,141.04

5,653,141.00

D- 1 M3 Sloof Beton Tulang 15/20 ( 180 kg besi + bekisting ) 4 dia 13 – Dia


15.Hr 8 – 15 Cm.

Kayu papan
M3 0.2700 2,950,000.00 796,500.00
terentang

Paku biasa 2″ –
Kg 2.0000 24,000.00 48,000.00
5″.

Besi beton Kg 180.0000 16,500.00 2,970,000.00

Kawat beton Kg 3.0000 30,500.00 91,500.00

Semen portland Kg 323.0000 1,548.00 500,004.00

Pasir beton M3 0.5200 255,400.00 132,808.00

Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3

Pekerja Oh 4.8500 67,000.00 324,950.00

Tukang Batu Oh 0.3500 70,000.00 24,500.00

Tukang Kayu Oh 1.5600 70,000.00 109,200.00

Tukang Besi Oh 1.4000 70,000.00 98,000.00

Kepala Tukang Oh 0.3310 80,000.00 26,480.00


Mandor Oh 0.1700 85,000.00 14,450.00

Jumlah 5,306,641.04

5,306,641.00

1 M3 Sloof Beton Tulang 20/30 ( 176 kg besi + bekisting )5dia 16 – Dia 8


– 15 Cm.

Kayu papan
M3 0.2700 2,950,000.00 796,500.00
terentang

Paku biasa 2″ –
Kg 2.0000 24,000.00 48,000.00
5″.

Besi beton Kg 176.0000 16,500.00 2,904,000.00

Kawat beton Kg 3.0000 30,500.00 91,500.00

Semen portland Kg 323.0000 1,548.00 500,004.00

Pasir beton M3 0.5200 255,400.00 132,808.00

Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3

Pekerja Oh 4.8500 67,000.00 324,950.00

Tukang Batu Oh 0.3500 70,000.00 24,500.00

Tukang Kayu Oh 1.5600 70,000.00 109,200.00

Tukang Besi Oh 1.4000 70,000.00 98,000.00


Kepala Tukang Oh 0.3310 80,000.00 26,480.00

Mandor Oh 0.1700 85,000.00 14,450.00

Jumlah 5,240,641.04

5,240,641.00

D- 1 M3 Kolom Beton Tulang,15/18 ( 201 kg besi + bekisting ) 6 Dia 10 –


16.Hr Dia 8 – 15 Cm.

Kayu papan
M3 0.4000 2,950,000.00 1,180,000.00
terentang

Paku biasa 2″ –
Kg 4.0000 24,000.00 96,000.00
5″.

Besi beton Kg 172.0000 16,500.00 2,838,000.00

Kawat beton Kg 1.8000 30,500.00 54,900.00

Semen portland Kg 323.0000 1,548.00 500,004.00

Pasir beton M3 0.5200 255,400.00 132,808.00

Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3

Kayu Balok
M3 0.1500 2,705,000.00 405,750.00
Terentang

MultiPlek 9 mm
Lbr 3.5000 –
120 x 240
Dolken Ø-8-
Btg 20.0000 –
10/4m

Pekerja Oh 7.3000 67,000.00 489,100.00

Tukang batu Oh 0.3500 70,000.00 24,500.00

Tukang kayu Oh 3.3000 70,000.00 231,000.00

Tukang besi Oh 2.1000 70,000.00 147,000.00

Kepala tukang Oh 0.5700 80,000.00 45,600.00

Mandor Oh 0.2500 85,000.00 21,250.00

Jumlah 6,336,161.04

6,336,161.00

1 M3 Kolom Beton Tulang,20/20 (140 kg besi + bekisting) 4 Dia 12 + Dia


D-16
8 – 15 Cm

Kayu papan
M3 0.4000 2,950,000.00 1,180,000.00
terentang

Paku biasa 2″ –
Kg 4.0000 24,000.00 96,000.00
5″.

Besi beton Kg 140.0000 16,500.00 2,310,000.00

Kawat beton Kg 1.8000 30,500.00 54,900.00

Semen portland Kg 323.0000 1,548.00 500,004.00


Pasir beton M3 0.5200 255,400.00 132,808.00

Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3

Kayu Balok
M3 0.1500 2,705,000.00 405,750.00
Terentang

MultiPlek 9 mm
Lbr 3.5000 – –
120 x 240

Dolken Ø-8-
Btg 20.0000 – –
10/4m

Pekerja Oh 7.3000 67,000.00 489,100.00

Tukang batu Oh 0.3500 70,000.00 24,500.00

Tukang kayu Oh 3.3000 70,000.00 231,000.00

Tukang besi Oh 2.1000 70,000.00 147,000.00

Kepala tukang Oh 0.5700 80,000.00 45,600.00

Mandor Oh 0.2500 85,000.00 21,250.00

Jumlah 5,808,161.04

5,808,161.00

1 M3 Kolom Beton Tulang,20/20 (210 kg besi + bekisting) 4 Dia 16 + Dia


D-16
8 – 15 Cm

Kayu papan
M3 0.4000 2,950,000.00 1,180,000.00
terentang
Paku biasa 2″ –
Kg 4.0000 24,000.00 96,000.00
5″.

Besi beton Kg 210.0000 16,500.00 3,465,000.00

Kawat beton Kg 1.8000 30,500.00 54,900.00

Semen portland Kg 323.0000 1,548.00 500,004.00

Pasir beton M3 0.5200 255,400.00 132,808.00

Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3

Kayu Balok
M3 0.1500 2,705,000.00 405,750.00
Terentang

MultiPlek 9 mm
Lbr 3.5000 – –
120 x 240

Dolken Ø-8-
Btg 20.0000 – –
10/4m

Pekerja Oh 7.3000 67,000.00 489,100.00

Tukang batu Oh 0.3500 70,000.00 24,500.00

Tukang kayu Oh 3.3000 70,000.00 231,000.00

Tukang besi Oh 2.1000 70,000.00 147,000.00

Kepala tukang Oh 0.5700 80,000.00 45,600.00

Mandor Oh 0.2500 85,000.00 21,250.00


Jumlah 6,963,161.04

6,963,161.00

1 M3 Kolom Beton Tulang,20/30 (118 kg besi + bekisting)6 Dia 12 + Dia


D-16
8 – 15 Cm

Kayu papan
M3 0.4000 2,950,000.00 1,180,000.00
terentang

Paku biasa 2″ –
Kg 4.0000 24,000.00 96,000.00
5″.

Besi beton Kg 118.0000 16,500.00 1,947,000.00

Kawat beton Kg 1.8000 30,500.00 54,900.00

Semen portland Kg 323.0000 1,548.00 500,004.00

Pasir beton M3 0.5200 255,400.00 132,808.00

Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3

Kayu Balok
M3 0.1500 2,705,000.00 405,750.00
Terentang

MultiPlek 9 mm
Lbr 3.5000 – –
120 x 240

Dolken Ø-8-
Btg 20.0000 – –
10/4m

Pekerja Oh 7.3000 67,000.00 489,100.00


Tukang batu Oh 0.3500 70,000.00 24,500.00

Tukang kayu Oh 3.3000 70,000.00 231,000.00

Tukang besi Oh 2.1000 70,000.00 147,000.00

Kepala tukang Oh 0.5700 80,000.00 45,600.00

Mandor Oh 0.2500 85,000.00 21,250.00

Jumlah 5,445,161.04

5,445,161.00

D- 1 M3 Kolom Beton Tulang,15/18 ( 201 kg besi + bekisting ) 6 Dia 10 –


17.Hr Dia 8 – 15 Cm.

Kayu papan
M3 0.4000 2,950,000.00 1,180,000.00
terentang

Paku biasa 2″ –
Kg 4.0000 24,000.00 96,000.00
5″.

Besi beton Kg 201.0000 16,500.00 3,316,500.00

Kawat beton Kg 2.4000 30,500.00 73,200.00

Semen portland Kg 323.0000 1,548.00 500,004.00

Pasir beton M3 0.5200 255,400.00 132,808.00

Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3
Kayu Balok
M3 0.1500 2,705,000.00 405,750.00
Terentang

MultiPlek 9 mm
Lbr 3.5000 – –
120 x 240

Dolken Ø-8-
Btg 20.0000 – –
10/4m

Pekerja Oh 7.3000 67,000.00 489,100.00

Tukang batu Oh 0.3500 70,000.00 24,500.00

Tukang kayu Oh 3.3000 70,000.00 231,000.00

Tukang besi Oh 2.1000 70,000.00 147,000.00

Kepala tukang Oh 0.5700 80,000.00 45,600.00

Mandor Oh 0.2500 85,000.00 21,250.00

Jumlah 6,832,961.04

6,832,961.00

D- 1 M3 Kolom Beton Tulang,13/18( 220 kg besi + bekisting ) 6 Dia 10 –


17.Hr Dia 8 – 15 Cm.

Kayu papan
M3 0.4000 2,950,000.00 1,180,000.00
terentang

Paku biasa 2″ –
Kg 4.0000 24,000.00 96,000.00
5″.

Besi beton Kg 220.0000 16,500.00 3,630,000.00


Kawat beton Kg 2.4000 30,500.00 73,200.00

Semen portland Kg 323.0000 1,548.00 500,004.00

Pasir beton M3 0.5200 255,400.00 132,808.00

Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3

Kayu Balok
M3 0.1500 2,705,000.00 405,750.00
Terentang

MultiPlek 9 mm
Lbr 3.5000 – –
120 x 240

Dolken Ø-8-
Btg 20.0000 – –
10/4m

Pekerja Oh 7.3000 67,000.00 489,100.00

Tukang batu Oh 0.3500 70,000.00 24,500.00

Tukang kayu Oh 3.3000 70,000.00 231,000.00

Tukang besi Oh 2.1000 70,000.00 147,000.00

Kepala tukang Oh 0.5700 80,000.00 45,600.00

Mandor Oh 0.2500 85,000.00 21,250.00

Jumlah 7,146,461.04

7,146,461.00
D-17. 1 M3 Kolom Beton Tulang,15/20 (180 kg besi + bekisting)

Kayu papan
M3 0.4000 2,950,000.00 1,180,000.00
terentang

Paku biasa 2″ –
Kg 4.0000 24,000.00 96,000.00
5″.

Besi beton Kg 180.0000 16,500.00 2,970,000.00

Kawat beton Kg 3.0000 30,500.00 91,500.00

Semen portland Kg 323.0000 1,548.00 500,004.00

Pasir beton M3 0.5200 255,400.00 132,808.00

Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3

Kayu Balok
M3 0.1500 2,705,000.00 405,750.00
Terentang

MultiPlek 9 mm
Lbr 3.5000 – –
120 x 240

Dolken Ø-8-
Btg 20.0000 – –
10/4m

Pekerja Oh 7.3000 67,000.00 489,100.00

Tukang batu Oh 0.3500 70,000.00 24,500.00

Tukang kayu Oh 3.3000 70,000.00 231,000.00

Tukang besi Oh 2.1000 70,000.00 147,000.00


Kepala tukang Oh 0.5700 80,000.00 45,600.00

Mandor Oh 0.2500 85,000.00 21,250.00

Jumlah 6,504,761.04

6,504,760.00

D-17. 1 M3 Kolom Beton Tulang,30/30 (176kg besi + bekisting)

Kayu papan
M3 0.4000 2,950,000.00 1,180,000.00
terentang

Paku biasa 2″ –
Kg 4.0000 24,000.00 96,000.00
5″.

Besi beton Kg 176.0000 16,500.00 2,904,000.00

Kawat beton Kg 3.0000 30,500.00 91,500.00

Semen portland Kg 323.0000 1,548.00 500,004.00

Pasir beton M3 0.5200 255,400.00 132,808.00

Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3

Kayu Balok
M3 0.1500 2,705,000.00 405,750.00
Terentang

MultiPlek 9 mm
Lbr 3.5000 166,500.00 582,750.00
120 x 240

Dolken Ø-8-
Btg 20.0000 – –
10/4m
Pekerja Oh 7.3000 67,000.00 489,100.00

Tukang batu Oh 0.3500 70,000.00 24,500.00

Tukang kayu Oh 3.3000 70,000.00 231,000.00

Tukang besi Oh 2.1000 70,000.00 147,000.00

Kepala tukang Oh 0.5700 80,000.00 45,600.00

Mandor Oh 0.2500 85,000.00 21,250.00

Jumlah 7,021,511.04

7,021,510.00

D-17. 1 M3 Kolom Beton Tulang,25/25 (176kg besi + bekisting)

Kayu papan
M3 0.4000 2,950,000.00 1,180,000.00
terentang

Paku biasa 2″ –
Kg 4.0000 24,000.00 96,000.00
5″.

Besi beton Kg 128.0000 16,500.00 2,112,000.00

Kawat beton Kg 3.0000 30,500.00 91,500.00

Semen portland Kg 323.0000 1,548.00 500,004.00

Pasir beton M3 0.5200 255,400.00 132,808.00

Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3
Kayu Balok
M3 0.1500 2,705,000.00 405,750.00
Terentang

MultiPlek 9 mm
Lbr 3.5000 166,500.00 582,750.00
120 x 240

Dolken Ø-8-
Btg 20.0000 – –
10/4m

Pekerja Oh 7.3000 67,000.00 489,100.00

Tukang batu Oh 0.3500 70,000.00 24,500.00

Tukang kayu Oh 3.3000 70,000.00 231,000.00

Tukang besi Oh 2.1000 70,000.00 147,000.00

Kepala tukang Oh 0.5700 80,000.00 45,600.00

Mandor Oh 0.2500 85,000.00 21,250.00

Jumlah 6,229,511.04

6,229,510.00

D-18 1 M3 Kolom Beton Tulang Praktis 12/12 ( 237 kg besi + bekisting )

Kayu papan
M3 0.0400 2,950,000.00 118,000.00
terentang

Paku biasa 2″ –
Kg 0.4000 24,000.00 9,600.00
5″.

Besi beton Kg 237.0000 16,500.00 3,910,500.00


Kawat beton Kg 3.5000 30,500.00 106,750.00

Semen portland Kg 323.0000 1,548.00 500,004.00

Pasir beton M3 0.5200 255,400.00 132,808.00

Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3

Kayu Balok
M3 0.1500 2,705,000.00 405,750.00
Terentang

MultiPlek 9 mm
Lbr 3.5000
120 x 240

Dolken Ø-8-
Btg 20.0000 –
10/4m

Pekerja Oh 7.3000 67,000.00 489,100.00

Tukang batu Oh 0.3500 70,000.00 24,500.00

Tukang kayu Oh 3.3000 70,000.00 231,000.00

Tukang besi Oh 2.1000 70,000.00 147,000.00

Kepala tukang Oh 0.5700 80,000.00 45,600.00

Mandor Oh 0.2500 85,000.00 21,250.00

Jumlah 6,312,111.04

6,312,110.00
1 M3 Balok Beton Tulang 15/20,sopi-sopi,ring balk+balok portal ( 180 kg
D-19
besi + bekisting )

Kayu papan
M3 0.3200 2,950,000.00 944,000.00
terentang

Paku biasa 2″ –
Kg 3.2000 24,000.00 76,800.00
5″.

Besi beton Kg 180.0000 16,500.00 2,970,000.00

Kawat beton Kg 3.0000 30,500.00 91,500.00

Semen portland Kg 323.0000 1,548.00 500,004.00

Pasir beton M3 0.5200 255,400.00 132,808.00

Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3

Kayu balok
M3 0.1800 2,705,000.00 486,900.00
terentang

MultiPlek 9 mm
Lbr 3.5000 – –
120 x 240

Dolken Ø-8-
Btg 20.0000 – –
10/4m

Pekerja Oh 7.3000 67,000.00 489,100.00

Tukang batu Oh 0.3500 70,000.00 24,500.00

Tukang kayu Oh 3.3000 70,000.00 231,000.00


Tukang besi Oh 2.1000 70,000.00 147,000.00

Kepala tukang Oh 0.5700 80,000.00 45,600.00

Mandor Oh 0.2500 85,000.00 21,250.00

Jumlah 6,330,711.04

6,330,710.00

1 M3 Balok Beton Tulang 15/20,sopi-sopi,ring balk+balok portal ( 180 kg


D-19
besi + bekisting )

Kayu papan
M3 0.3200 2,950,000.00 944,000.00
terentang

Paku biasa 2″ –
Kg 3.2000 24,000.00 76,800.00
5″.

Besi beton Kg 130.0000 16,500.00 2,145,000.00

Kawat beton Kg 3.0000 30,500.00 91,500.00

Semen portland Kg 323.0000 1,548.00 500,004.00

Pasir beton M3 0.5200 255,400.00 132,808.00

Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3

Kayu balok
M3 0.1800 2,705,000.00 486,900.00
terentang

MultiPlek 9 mm
Lbr 3.5000 166,500.00 582,750.00
120 x 240
Dolken Ø-8-
Btg 20.0000 24,900.00 498,000.00
10/4m

Pekerja Oh 7.3000 67,000.00 489,100.00

Tukang batu Oh 0.3500 70,000.00 24,500.00

Tukang kayu Oh 3.3000 70,000.00 231,000.00

Tukang besi Oh 2.1000 70,000.00 147,000.00

Kepala tukang Oh 0.5700 80,000.00 45,600.00

Mandor Oh 0.2500 85,000.00 21,250.00

Jumlah 6,586,461.04

6,586,460.00

D-19 1 M3 Balok Beton Tulang 30/60, ( 130 kg besi + bekisting )

Kayu papan
M3 0.3200 2,950,000.00 944,000.00
terentang

Paku biasa 2″ –
Kg 3.2000 24,000.00 76,800.00
5″.

Besi beton Kg 176.0000 16,500.00 2,904,000.00

Kawat beton Kg 3.0000 30,500.00 91,500.00

Semen portland Kg 323.0000 1,548.00 500,004.00

Pasir beton M3 0.5200 255,400.00 132,808.00


Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3

Kayu balok
M3 0.1800 2,705,000.00 486,900.00
terentang

MultiPlek 9 mm
Lbr 3.5000 166,500.00 582,750.00
120 x 240

Dolken Ø-8-
Btg 20.0000 24,900.00 498,000.00
10/4m

Pekerja Oh 7.3000 67,000.00 489,100.00

Tukang batu Oh 0.3500 70,000.00 24,500.00

Tukang kayu Oh 3.3000 70,000.00 231,000.00

Tukang besi Oh 2.1000 70,000.00 147,000.00

Kepala tukang Oh 0.5700 80,000.00 45,600.00

Mandor Oh 0.2500 85,000.00 21,250.00

Jumlah 7,345,461.04

1 M3 Balok Beton Tulang 13/18,sopi-sopi,ring balk+balok portal ( 220 kg


D-19
besi + bekisting )

Kayu papan
M3 0.3200 2,950,000.00 944,000.00
terentang
Paku biasa 2″ –
Kg 3.2000 24,000.00 76,800.00
5″.

Besi beton Kg 220.0000 16,500.00 3,630,000.00

Kawat beton Kg 3.0000 30,500.00 91,500.00

Semen portland Kg 323.0000 1,548.00 500,004.00

Pasir beton M3 0.5200 255,400.00 132,808.00

Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3

Kayu balok
M3 0.1800 2,705,000.00 486,900.00
terentang

MultiPlek 9 mm
Lbr 3.5000 – –
120 x 240

Dolken Ø-8-
Btg 20.0000 – –
10/4m

Pekerja Oh 7.3000 67,000.00 489,100.00

Tukang batu Oh 0.3500 70,000.00 24,500.00

Tukang kayu Oh 3.3000 70,000.00 231,000.00

Tukang besi Oh 2.1000 70,000.00 147,000.00

Kepala tukang Oh 0.5700 80,000.00 45,600.00

Mandor Oh 0.2500 85,000.00 21,250.00


Jumlah 6,990,711.04

6,990,710.00

D- 1 M3 Balok BetonLintel 11/11 ( 275 kg besi + bekisting ) 4 Dia 10 + Dia 8


19.A – 15 Cm

Kayu papan
M3 0.4000 2,950,000.00 1,180,000.00
terentang

Paku biasa 2″ –
Kg 4.0000 24,000.00 96,000.00
5″.

Besi beton Kg 275.0000 16,500.00 4,537,500.00

Kawat beton Kg 4.0000 30,500.00 122,000.00

Semen portland Kg 323.0000 1,548.00 500,004.00

Pasir beton M3 0.5200 255,400.00 132,808.00

Batu pecah
M3 0.7800 218,268.00 170,249.04
mesin 2/3

Kayu balok
M3 0.1800 2,705,000.00 486,900.00
terentang

MultiPlek 9 mm
Lbr 3.5000 –
120 x 240

Dolken Ø-8-
Btg 20.0000 – –
10/4m

Pekerja Oh 7.3000 67,000.00 489,100.00


Tukang batu Oh 0.3500 70,000.00 24,500.00

Tukang kayu Oh 3.3000 70,000.00 231,000.00

Tukang besi Oh 2.1000 70,000.00 147,000.00

Kepala tukang Oh 0.5700 80,000.00 45,600.00

Mandor Oh 0.2500 85,000.00 21,250.00

Jumlah 8,183,911.04

8,183,911.00

D-20 1 M3 Tangga Beton Tulang (200 kg besi + bekisting)

Kayu papan
M3 0.2500 2,950,000.00 737,500.00
terentang

Paku Biasa 2″ –
Kg 3.0000 24,000.00 72,000.00
5″

Besi beton Kg 200.0000 16,500.00 3,300,000.00

Kawat Beton Kg 3.0000 30,500.00 91,500.00

Semen
Kg 323.0000 1,548.00 500,004.00
Portland

Pasir Beton M3 0.5200 255,400.00 132,808.00


Batu Pecah
M3 0.7800 218,268.00 170,249.04
Mesin 2/3

Kayu Balok
M3 0.1050 2,705,000.00 284,025.00
Terentang

MultiPlek 9 mm
Lbr 2.5000 – –
120 x 240

Dolken Ø-8-
Btg 14.0000 – –
10/4m

Pekerja Oh 5.6000 67,000.00 375,200.00

Tukang batu Oh 0.3500 70,000.00 24,500.00

Tukang kayu Oh 2.3000 70,000.00 161,000.00

Tukang besi Oh 2.1000 70,000.00 147,000.00

Kepala tukang Oh 0.4050 80,000.00 32,400.00

Mandor Oh 0.2020 85,000.00 17,170.00

Jumlah 6,045,356.04

6,045,356.00

D-20 1 M3 Lisplank Beton Tulang (50 kg besi + bekisting)

Kayu papan
M3 0.2500 2,950,000.00 737,500.00
terentang

Paku Biasa 2″ –
Kg 3.0000 24,000.00 72,000.00
5″
Besi beton Kg 50.0000 16,500.00 825,000.00

Kawat Beton Kg 3.0000 30,500.00 91,500.00

Semen
Kg 323.0000 1,548.00 500,004.00
Portland

Pasir Beton M3 0.5200 255,400.00 132,808.00

Batu Pecah
M3 0.7800 218,268.00 170,249.04
Mesin 2/3

Kayu Balok
M3 0.1050 2,705,000.00 284,025.00
Terentang

MultiPlek 9 mm
Lbr 2.5000 –
120 x 240

Dolken Ø-8-
Btg 14.0000 24,900.00 348,600.00
10/4m

Pekerja Oh 5.6000 67,000.00 375,200.00

Tukang batu Oh 0.3500 70,000.00 24,500.00

Tukang kayu Oh 2.3000 70,000.00 161,000.00

Tukang besi Oh 2.1000 70,000.00 147,000.00

Kepala tukang Oh 0.4050 80,000.00 32,400.00

Mandor Oh 0.2020 85,000.00 17,170.00

Jumlah 3,918,956.04
3,918,956.00

D-21 1 M3 Pelat Lantai Beton Tulang T= 10 cm (90 kg besi + bekisting)

Beton tulang
ad. 1Pc : 2Ps : M3 1.0000 1,019,795.24 1,019,795.24
3Kr

Pasang
Bekisting untuk M2 10.0000 483,575.00 4,835,750.00
lantai

Besi Beton
Kg 90.0000 18,823.00 1,694,070.00
Polos

Jumlah 7,549,615.24

7,549,615.00

D-22 1 M3 Pelat Lantai Beton Tulang T= 12 cm (110 kg besi + bekisting)

Beton bertulang
ad. 1Pc : 2Ps : M3 1.0000 1,019,795.24 1,019,795.24
3Kr

Pasang
Bekisting untuk M2 8.3300 483,575.00 4,028,179.75
lantai

Besi Beton
Kg 110.0000 18,823.00 2,070,530.00
Polos

Jumlah 7,118,504.99

7,118,505.00
D-23 1 M3 Pelat Lantai Beton Tulang T= 12 cm (130 kg besi + bekisting)

Beton bertulang
ad. 1Pc : 2Ps : M3 1.0000 1,019,795.24 1,019,795.24
3Kr

Pasang
Bekisting untuk M2 8.3300 483,575.00 4,028,179.75
lantai

Besi Beton
Kg 130.0000 18,823.00 2,446,990.00
Polos

Jumlah 7,494,964.99

7,494,965.00

D-24 1 M3 Pelat Lantai Beton Tulang T= 15 cm (90 kg besi + bekisting)

Beton bertulang
ad. 1Pc : 2Ps : M3 1.0000 1,019,795.24 1,019,795.24
3Kr

Pasang
Bekisting untuk M2 6.6700 483,575.00 3,225,445.25
lantai

Besi Beton
Kg 90.0000 18,823.00 1,694,070.00
Polos

Jumlah 5,939,310.49

Dibulatkan 5,939,310.00

D-25 1 M3 Pelat Lantai Beton Tulang T= 15 cm (115 kg besi + bekisting)


Beton bertulang
ad. 1Pc : 2Ps : M3 1.0000 1,019,795.24 1,019,795.24
3Kr

Pasang
Bekisting untuk M2 6.6700 483,575.00 3,225,445.25
lantai

Besi Beton
Kg 115.0000 18,823.00 2,164,645.00
Polos

Jumlah 6,409,885.49

6,409,885.00