2.0 MATERIALS
2.1 General
Gravel material shall be obtained from approved sources in borrow areas or
cuts. Tests will have been made on potential borrow pits, cuts and on the
roadbed along the centre line of the existing road. The requirements to be
complied with by the material are set out on the Drawings and in the Project
Specifications for each of the 150mm layers. It shall be ensured that only
material which complies with the prescribed requirements is used in the
selected fill layers. Where natural gravel does not fully comply with the
requirements in respect of maximum size after having been broken down as
determined in Clause 3204 of SATCC specification, or after light crushing,
oversize material shall be removed as specified in Clause 3210.
3.0 EQUIPMENT
i. 2 No 140G Grader
ii. 1 No. Bull dozer
iii.1 No. Front End Loader
iv. 6 No 15 ton Tipper Trucks
v. 4 No Rollers (1No. grid roller, 2 No. Vibrating Steel Drum Rollers, 1 No.
Pneumatic Roller)
vi. 2 No Water Bowser (each of capacity 21,000 litres)
4.0 CONSTRUCTION
4.1 Requirements applying prior to the construction of the layer
Fill layers shall be constructed only where the underlying layer meets all the
specified requirements and has been approved by the Engineer. Before the
construction of any fill layer, and also before any material for a fill layer is
dumped on the road, the underlying layer shall be checked to establish
whether there is any damage, wet spots or other defects, which shall be
rectified in accordance with the instructions of the Engineer before the next
layer is constructed.
Where fill material cannot be suitably broken down to the required size in
excavation and during processing on the road, the Engineer may prescribe
that the material be crushed and screened or crushed only, all as specified in
Section 3200.
6.1 Level
The level tolerances referred to in Clause 7205 shall be as follows:
H90 .................................... 25 mm
Hmax ………………………………… 33 mm
6.3 Width
The average width of the layer shall not be less than the specified width, and
nowhere shall the outer edge deviate by more than the following from the
edge lines shown on the Drawings: 3400-4
Upgrading of approximately 104Km of the chipata Mfuwe rd Page 3
SELECTED layer Methodology
Selected layer . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80 mm
6.4 Cross-section
When tested with a 3 m straight-edge laid at right angles to the road centre
line, the surface shall not deviate from the bottom of the straight-edge by
more than 6 mm. At any cross-section the difference in level between any
two points shall not vary from their difference in level computed from the
cross-sections shown on the Drawings by more than 15 mm.
1 Site Engineer
1 Earthworks Foreman on site
1 Soils Technician
2 Laboratory Assistants
3 General Workers for checking levels
4 General Workers for picking rejected material
1 Machine Attendant for each item of plant and equipment
2 Mechanics for daily servicing and minor repairs
1 Bulldozer Operator
Upgrading of approximately 104Km of the chipata Mfuwe rd Page 4
SELECTED layer Methodology
1 Loader Operator
1 Operator for each Grader
1 Operator for each Roller
1 Driver for each Water tanker
1 Driver for each Tipper Truck
1 driver Tractor (disk harrow)
All works shall overally be supervised by a Site Engineer, who shall ensure
that a safe working environment is always maintained, and that on-site safety
procedures are followed at all times.
The Site Engineer shall see to it that adequate measures are taken to warn
and protect road users and construction workers. He shall instruct all
supervisors and foremen in safety measures including traffic control and use
of clean standard temporary road signs
All workers shall be provided with such protective clothing such as hand
gloves, overall suits, boots, reflective jackets and dust masks.
Only suitable hand tools and devices, free from any defect, shall be used.