TIME SCHEDULE

PEKERJAAN PEMBANGUNAN GEDUNG PENDIDIKAN FITK DAN FEBI 5200 M2


INSTITUT AGAMA ISLAM NEGERI SURAKARTA
TAHUN ANGGARAN 2017

WAKTU PELAKSANAAN
BULAN I BULAN II BULAN III BULAN IV BULAN V BULAN VI
BOBOT
NO. URAIAN PEKERJAAN HARGA Mg ke 1 Mg ke 2 Mg ke 3 Mg ke 4 Mg ke 5 Mg ke 6 Mg ke 7 Mg ke 8 Mg ke 9 Mg ke 10 Mg ke 11 Mg ke 12 Mg ke 13 Mg ke 14 Mg ke 15 Mg ke 16 Mg ke 17 Mg ke 18 Mg ke 19 Mg ke 20 Mg ke 21 Mg ke 22 Mg ke 23 Mg ke 24 Mg ke 25 Mg ke 26 PROSENTASE KETRANGAN
(%)

1-7 8-14 15-21 22-28 29-35 36-42 43-49 50-56 57-63 64-70 71-77 78-84 85-91 92-98 99-105 106-112 113-119 120-126 127-133 134-140 141-147 148-154 155-161 162-168 167-175 176-180

I PEKERJAAN PERSIAPAN 80,700,000.00 0.320 0.0400 0.0400 0.0400 0.0400 0.0400 0.0400 0.0400 0.0400 Waktu Pelaksanaan Pekerjaan
100
= 180 Hari Kalender

II GEDUNG A
`
A PEKERJAAN STANDAR
1 PEKERJAAN PERSIAPAN 7,551,900.00 0.030 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012

2 PEKERJAAN STRUKTUR
2.1. PEKERJAAN TANAH 314,901,714.67 1.248 0.2079 0.2079 0.2079 0.2079 0.2079 0.2079
2.2. PEKERJAAN STRUKTUR BAWAH 770,036,402.21 3.051 1.0170 1.0170 1.0170
2.3. PEKERJAAN STRUKTUR ATAS
A. LANTAI 1 (SATU) 483,458,661.71 1.916 0.6385 0.6385 0.6385
B. LANTAI 2 (DUA) 960,320,998.21 3.805 1.2683 1.2683 1.2683
C. LANTAI 3 (TIGA) 858,553,347.01 3.402 1.1339 1.1339 1.1339
D. LANTAI ATAP 705,875,640.87 2.797 0.9323 0.9323 0.9323
E. LANTAI RING BALOK 82,553,487.66 0.327 0.1090 0.1090 0.1090
F. PEKERJAAN ATAP 497,989,992.89 1.973 0.6577 0.6577 0.6577

3 PEKERJAAN ARSITEK
3.1. PEKERJAAN PASANGAN DAN PELAPIS DINDING 1,380,981,116.44 5.472 0.4560 0.4560 0.4560 0.4560 0.4560 0.4560 0.4560 0.4560 0.4560 0.4560 0.4560 0.4560
3.2. PEKERJAAN PASANGAN LANTAI 645,574,858.72 2.558 0.2558 0.2558 0.2558 0.2558 0.2558 0.2558 0.2558 0.2558 0.2558 0.2558
3.3. PEKERJAAN PASANGAN PLAFOND 311,999,782.49 1.236 0.1236 0.1236 0.1236 0.1236 0.1236 0.1236 0.1236 0.1236 0.1236 0.1236
3.4. PEKERJAAN PASANGAN PINTU DAN JENDELA 1,067,700,000.00 4.230 0.3846 0.3846 0.3846 0.3846 0.3846 0.3846 0.3846 0.3846 0.3846 0.3846 0.3846
3.5. PEKERJAAN PASANGAN SANITAIR 116,145,470.00 0.460 0.0767 0.0767 0.0767 0.0767 0.0767 0.0767
3.6. PEKERJAAN PENGECATAN 186,289,488.91 0.738 0.1054 0.1054 0.1054 0.1054 0.1054 0.1054 0.1054
3.7. PEKERJAAN BESI RAILLING DAN TANGGA 85,420,000.00 0.338 0.0564 0.0564 0.0564 0.0564 0.0564 0.0564
3.8. PEKERJAAN PENUTUP ATAP 220,895,200.00 0.875 0.2917 0.2917 0.2917

4 PEKERJAAN PLUMBING
80
4.1. PEKERJAAN AIR BERSIH 180,534,145.00 0.715 0.0894 0.0894 0.0894 0.0894 0.0894 0.0894 0.0894 0.0894
4.2. PEKERJAAN AIR KOTOR 24,392,000.00 0.097 0.0121 0.0121 0.0121 0.0121 0.0121 0.0121 0.0121 0.0121
4.3. PEKERJAAN AIR HUJAN 20,900,000.00 0.083 0.0104 0.0104 0.0104 0.0104 0.0104 0.0104 0.0104 0.0104

5 PEKERJAAN ELEKTRIKAL
5.1. PEKERJAAN PANEL DAN KABEL FEEDER 324,209,600.00 1.285 0.1835 0.1835 0.1835 0.1835 0.1835 0.1835 0.1835
5.2. PEKERJAAN PENERANGAN DAN DAYA STOP KONTAK 228,110,000.00 0.904 0.0452 0.0452 0.0452 0.0452 0.0452 0.0452 0.0452 0.0452 0.1808 0.1808 0.1808

B PEKERJAAN NON STANDAR

1 PEKERJAAN STRUKTUR
1.1. PEKERJAAN PONDASI TIANG PANCANG 327,936,376.19 1.299 0.4331 0.4331 0.4331
1.2. PEKERJAAN WATERPROOFING TOILET 20,359,950.00 0.081 0.0134 0.0134 0.0134 0.0134 0.0134 0.0134

2 PEKERJAAN ARSITEK
2.1. PEKERJAAN PASANGAN DAN PELAPIS DINDING 494,175,552.50 1.958 0.2447 0.2447 0.2447 0.2447 0.2447 0.2447 0.2447 0.2447

3 PEKERJAAN MEKANIKAL
4.1. PEKERJAAN AIR CONDITIONING 21,450,000.00 0.085 0.0106 0.0106 0.0106 0.0106 0.0106 0.0106 0.0106 0.0106
4.2. PEKERJAAN VENTILASI 44,927,500.00 0.178 0.0223 0.0223 0.0223 0.0223 0.0223 0.0223 0.0223 0.0223
4.3. PEKERJAAN HYDRANT & FIRE EXTINGUISHER 25,200,000.00 0.100 0.0250 0.0250 0.0250 0.0250

4 PEKERJAAN ELEKTRIKAL ARUS KUAT


5.1. RAK KABEL 43,050,000.00 0.171 0.0284 0.0284 0.0284 0.0284 0.0284 0.0284
5.2. PENANGKAL PETIR DAN GROUNDING 69,773,360.00 0.276 0.0461 0.0461 0.0461 0.0461 0.0461 0.0461

5 PEKERJAAN ELEKTRIKAL ARUS LEMAH (ELEKTRONIK)


6.1. PEKERJAAN FIRE ALARM 97,915,000.00 0.388 0.0194 0.0194 0.0194 0.0194 0.0194 0.0194 0.0194 0.0194 0.0776 0.0776 0.0776
6.2. PEKERJAAN CCTV 9,980,000.00 0.040 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0020 0.0079 0.0079 0.0079
60
6.3. PEKERJAAN DATA 11,250,000.00 0.045 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.0022 0.0089 0.0089 0.0089
6.4. PEKERJAAN TELEPHONE 17,434,000.00 0.069 0.0035 0.0035 0.0035 0.0035 0.0035 0.0035 0.0035 0.0035 0.0138 0.0138 0.0138
6.5. PEKERJAAN MATV 8,742,000.00 0.035 0.0017 0.0017 0.0017 0.0017 0.0017 0.0017 0.0017 0.0017 0.0069 0.0069 0.0069
6.6. PEKERJAAN TATA SUARA 85,040,000.00 0.337 0.0168 0.0168 0.0168 0.0168 0.0168 0.0168 0.0168 0.0168 0.0674 0.0674 0.0674

III GEDUNG B

A PEKERJAAN STANDAR

1 PEKERJAAN PERSIAPAN 7,551,900.00 0.030 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012

2 PEKERJAAN STRUKTUR
2.1. PEKERJAAN TANAH 314,903,211.80 1.248 0.1560 0.1560 0.1560 0.1560 0.1560 0.1560 0.1560 0.1560
2.2. PEKERJAAN STRUKTUR BAWAH 769,840,064.81 3.050 1.0167 1.0167 1.0167
2.3. PEKERJAAN STRUKTUR ATAS
A. LANTAI 1 (SATU) 854,282,720.42 3.385 1.1283 1.1283 1.1283
B. LANTAI 2 (DUA) 960,320,998.21 3.805 1.2683 1.2683 1.2683
C. LANTAI 3 (TIGA) 858,553,347.01 3.402 1.1339 1.1339 1.1339
D. LANTAI ATAP 705,955,105.71 2.797 0.9324 0.9324 0.9324
E. LANTAI RING BALOK 82,553,487.66 0.327 0.1090 0.1090 0.1090
F. PEKERJAAN ATAP 497,989,992.89 1.973 0.6577 0.6577 0.6577

3 PEKERJAAN ARSITEK
3.1. PEKERJAAN PASANGAN DAN PELAPIS DINDING 1,385,483,946.29 5.489 0.4575 0.4575 0.4575 0.4575 0.4575 0.4575 0.4575 0.4575 0.4575 0.4575 0.4575 0.4575
3.2. PEKERJAAN PASANGAN LANTAI 648,234,211.38 2.568 0.2568 0.2568 0.2568 0.2568 0.2568 0.2568 0.2568 0.2568 0.2568 0.2568
3.3. PEKERJAAN PASANGAN PLAFOND 314,725,640.17 1.247 0.1247 0.1247 0.1247 0.1247 0.1247 0.1247 0.1247 0.1247 0.1247 0.1247
3.4. PEKERJAAN PASANGAN PINTU DAN JENDELA 1,086,900,000.00 4.306 0.3915 0.3915 0.3915 0.3915 0.3915 0.3915 0.3915 0.3915 0.3915 0.3915 0.3915
3.5. PEKERJAAN PASANGAN SANITAIR 124,707,320.00 0.494 0.0824 0.0824 0.0824 0.0824 0.0824 0.0824
40
3.6. PEKERJAAN PENGECATAN 209,407,496.62 0.830 0.1185 0.1185 0.1185 0.1185 0.1185 0.1185 0.1185
3.7. PEKERJAAN RAILLING DAN HAND RAILLING 90,574,000.00 0.359 0.0598 0.0598 0.0598 0.0598 0.0598 0.0598
3.8. PEKERJAAN PENUTUP ATAP 220,895,200.00 0.875 0.2917 0.2917 0.2917

4 PEKERJAAN PLUMBING
4.1. PEKERJAAN AIR BERSIH 184,334,145.00 0.730 0.0913 0.0913 0.0913 0.0913 0.0913 0.0913 0.0913 0.0913
4.2. PEKERJAAN AIR KOTOR 23,592,000.00 0.093 0.0117 0.0117 0.0117 0.0117 0.0117 0.0117 0.0117 0.0117
4.3. PEKERJAAN AIR HUJAN 20,900,000.00 0.083 0.0104 0.0104 0.0104 0.0104 0.0104 0.0104 0.0104 0.0104

5 PEKERJAAN ELEKTRIKAL
5.1. PEKERJAAN PANEL DAN KABEL FEEDER 268,664,600.00 1.064 0.1521 0.1521 0.1521 0.1521 0.1521 0.1521 0.1521
5.2. PEKERJAAN PENERANGAN DAN DAYA STOP KONTAK 241,590,000.00 0.957 0.0479 0.0479 0.0479 0.0479 0.0479 0.0479 0.0479 0.0479 0.1914 0.1914 0.1914

B PEKERJAAN NON STANDAR

1 PEKERJAAN STRUKTUR
1.1. PEKERJAAN PONDASI TIANG PANCANG 327,936,376.19 1.299 0.4331 0.4331 0.4331
1.2. PEKERJAAN WATERPROOFING TOILET 20,612,800.00 0.082 0.0136 0.0136 0.0136 0.0136 0.0136 0.0136

2 PEKERJAAN ARSITEK
2.1. PEKERJAAN PASANGAN DAN PELAPIS DINDING 478,315,952.50 1.895 0.2369 0.2369 0.2369 0.2369 0.2369 0.2369 0.2369 0.2369

3 PEKERJAAN MEKANIKAL
3.1. PEKERJAAN AIR CONDITIONING 18,480,000.00 0.073 0.0092 0.0092 0.0092 0.0092 0.0092 0.0092 0.0092 0.0092
3.2. PEKERJAAN VENTILASI 41,677,500.00 0.165 0.0206 0.0206 0.0206 0.0206 0.0206 0.0206 0.0206 0.0206
3.3. PEKERJAAN HYDRANT & FIRE EXTINGUISHER 25,200,000.00 0.100 0.0250 0.0250 0.0250 0.0250

4 PEKERJAAN ELEKTRIKAL ARUS KUAT


4.1 RAK KABEL 48,150,000.00 0.191 0.0318 0.0318 0.0318 0.0318 0.0318 0.0318
20
4.2. Instalasi Grounding System 69,773,360.00 0.276 0.0461 0.0461 0.0461 0.0461 0.0461 0.0461

5 PEKERJAAN ELEKTRIKAL ARUS LEMAH (ELEKTRONIK)


5.1. PEKERJAAN FIRE ALARM 108,925,000.00 0.432 0.0216 0.0216 0.0216 0.0216 0.0216 0.0216 0.0216 0.0216 0.0863 0.0863 0.0863
5.2. PEKERJAAN CCTV 14,980,000.00 0.059 0.0030 0.0030 0.0030 0.0030 0.0030 0.0030 0.0030 0.0030 0.0119 0.0119 0.0119
5.3. PEKERJAAN DATA 20,270,000.00 0.080 0.0040 0.0040 0.0040 0.0040 0.0040 0.0040 0.0040 0.0040 0.0161 0.0161 0.0161
5.4. PEKERJAAN TELEPON 25,672,000.00 0.102 0.0051 0.0051 0.0051 0.0051 0.0051 0.0051 0.0051 0.0051 0.0203 0.0203 0.0203
5.5. PEKERJAAN MATV 16,469,000.00 0.065 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0131 0.0131 0.0131
5.6. PEKERJAAN TATA SUARA 105,760,000.00 0.419 0.0210 0.0210 0.0210 0.0210 0.0210 0.0210 0.0210 0.0210 0.0838 0.0838 0.0838

IV PEKERJAAN SITE DEVELOPMENT DAN UTILYTAS

1 PEKERJAAN TANAH DAN JALAN 439,424,527.23 1.741 0.1741 0.1741 0.1741 0.1741 0.1741 0.1741 0.1741 0.1741 0.1741 0.1741

2 PEKERJAAN MEKANIKAL
2.1. Instalasi Air Bersih 291,960,960.00 1.157 0.1928 0.1928 0.1928 0.1928 0.1928 0.1928
2.2. Instalasi Air Kotor, Bekas dan Vent 423,999,996.79 1.680 0.1400 0.1400 0.1400 0.1400 0.1400 0.1400 0.1400 0.1400 0.1400 0.1400 0.1400 0.1400

3 PEKERJAAN ELEKTRIKAL
3.1. Panel dan Kabel Feeder 1,375,972,200.00 5.452 0.7788 0.7788 0.7788 0.7788 0.7788 0.7788 0.7788

4 PEKERJAAN BANGUNAN POWER HOUSE 597,793,353.42 2.369 0.3384 0.3384 0.3384 0.3384 0.3384 0.3384 0.3384

5 PEKERJAAN POS JAGA 83,230,171.21 0.330 0.0471 0.0471 0.0471 0.0471 0.0471 0.0471 0.0471

JUMLAH 25,238,890,130.78 100.000


0

RENCANA MINGGU INI 0.002 0.042 0.839 0.839 1.856 2.495 3.512 4.891 4.745 5.413 4.927 4.359 4.950 4.171 4.957 5.055 4.288 5.153 5.677 6.369 6.077 5.561 5.810 4.083 3.652 0.276
RENCANA SAMPAI DENGAN MINGGU INI - 0.002 0.045 0.884 1.723 3.579 6.074 9.586 14.477 19.222 24.635 29.562 33.921 38.871 43.042 47.999 53.054 57.342 62.495 68.172 74.541 80.618 86.179 91.989 96.072 99.724 100.000
REALISAI MINGGUAN 0.026 - 0.967 1.534 1.097 1.925 2.181 3.006 3.909 2.863 2.042
KOMULATIP REALISASI MINGGUAN 0.002 0.002 0.969 2.502 3.599 5.524 7.705 10.712 14.621 17.484 19.526
MENDAHULUI ( + ),TERLAMBAT ( - ) 0.000 0.043 (0.085) 0.694 (0.759) (0.570) (1.331) (1.885) (0.836) (2.550) (2.884)

1 2 3 4 5 6 7 8 9 10 11 12 13 14
98.0000 Dibuat Oleh :

Pejabat Pembuat Komitmen Konsultan Manajemen Konstruksi PT. SINAR CERAH SEMPURNA
IAIN Surakarta PT. BINA KARYA (PERSERO)

JAROT SUSENA, S.Sos BAMBANG TRI MARTONO, ST Ir. H. SOEHARTO, MT


NIP. 19780517 200901 1 001 Team Leader Direktur Utama