Harga
No Keterangan Qty Satuan
Harga Satuan Total
A Civil
1 Bowplank 17 m'
2 Galian tanah 5.1 m3
3 Urugan kembali 3.186 m3
4 Buang tanah sisa 1.914 m3
5 Lantai kerja 5 cm 0.229 m3
6 Urugan pasir 5 cm 0.229 m3
7 Pondasi
Beton 1:2:3 1.13 m3
Bekisting pond.plat setempat 6.48 m2
Besi D16mm 56.88
Besi D13mm 80 kg
Besi dia 10 mm 18 kg
8 Sloof
Beton 1:2:3 0.78 m3
Bekisting sloof 8 m2
Besi D13mm 54 kg
Besi dia 8mm 35 kg
9 Grouting t 25 mm 1 lot
B MEKANIKAL
STRUKTUR
H BEAM 200 x 200 x 10 x 16 x 12 Mtr 4.5 btg
UNP 150 x 75 x 6.5 x 6 Mtr 4 btg
SIKU 60 x 60 x 6 x 6 Mtr 20 btg
SIKU 50 x 50 x 5 x 6 Mtr 5 btg
Ms Plate 12 mm x 4' x 8' 0.5 btg
Ms Plate 8 mm x 4' x 8' 0.5 btg
Plat Bordes 4.5 mm x 4' x 8' 11 btg
Pipa Hitam Ø 1 1/4" 4 btg
Pipa Hitam Ø 1 " 2 btg
Plat Strip 6mm x 100 mm x 6 Mtr 2.5 btg