Anda di halaman 1dari 24

National Highways & Infrastructure Development

Corporation Limited Ministry of Road Transport &


Highways
Project - Construction and Up gradation of existing road to 2-lane with paved shoulder from km 379.100 to km
380.275 of Gholteer landslide (Design km 378.900 to 380.075) of NH-07 under Chardham Paryojna on EPC basis in
the state of Uttarakhand (Design length-1.175 km)

MONTHLY PROGRESS REPORT


(May-2019)
SUBMITTED BY : EPC CONTRACTOR

BHARAT CONSTRUCTION
BHARAT CONSTRUCTION

Project - Construction and Up gradation of existing road to 2-lane with paved


shoulder from km 379.100 to km 380.275 of Gholteer landslide (Design km
378.900 to 380.075) of NH-07 under Chardham Paryojna on EPC basis in the
state of Uttarakhand (Design length-1.175 km)

MONTHLY PROGRESS REPORT


SR NO. DESCRIPTION PAGE NO.
1 SALIENT FEATURES OF THE PROJECT
2 PHYSICAL AND FINANCIAL PROGRESS
3 STATUS OF LAND ACQUISITION
4 STATUS OF DRAWING SUBMISSION
5 STATUS OF UTILITY SHIFTING
6 UNRESOLVED ISSUES
7 MOBILIZATION ISSUES
8 LOGISTIC PLANS
9 MILESTONES
10 SAFETY AND HEALTH
11 EXISTING ROAD MAINTENANCE
12 EPC COST BREAKUP
13 STATUS OF PERMISSION AND APPROVALS
14 PROGRESS LINEAR CHART OF HIGHWAY
15 ORGANIZATION CHART
16 QUALITY CONTROL/ASSURANCE MONTHLY PROGRESS REPORT
18 PHOTOGRAPHS
BHARAT CONSTR

Project - Construction and Up gradation of existing road to 2-


380.275 of Gholteer landslide (Design km 378.900 to 380.075) of
the state of Uttarakhand (Desig

LOGISTIC PLAN OF SITE

PROJECT START
8+900
8+975

9+050

9+125

9+200

9+275

9+350

9+425

9+500
378+900
378+975

RH S
379+050
PROJECT START

379+125

379+200

379+275

379+350

379+425

379+500
DESIGN CHAINAGE FROM KM 37
DESIGN CHAINAGE FROM KM 37
CONSTRUCTION

g road to 2-lane with paved shoulder from km 379.100 to km


380.075) of NH-07 under Chardham Paryojna on EPC basis in
hand (Design length-1.175 km)

LAN OF SITE ESTABLISHMENT

L H S
9+575

9+650

9+725

9+800

9+875

9+950

0+075
379+575

379+650

379+725

FROM KM 378.900 TO 380.075


379+800

379+875

379+950

380+075
PROJECT END
L H S
FROM KM 378.900 TO 380.075
BHARAT CONSTRUCTION
Project - Construction and Upgradation including specialized slope treatment of existing road to 2-lane with
paved shoulder from Exisiting Km. 458.900 to Km. 459.475 (Design Ch 456.200 to Ch 456.800) of Patalganga
Landslide of NH-07 under Chardham Pariyojna on EPC basis in the state of Uttarakhand. (Design Length =
0.600 km).

SALIENT FEATURES OF THE PROJECT


SCOPE OF HIGHWAY WORKS
LENGTH OF PROJECT : 1.175 KM
REALIGNMENTS : NIL
SERVICE ROADS : NIL
MAJOR INTERSECTIONS : NIL
MINOR JUNCTIONS : NIL
TRUCK LAY-BYES : NIL
BUS LAY-BAYS : NIL
TOLL PLAZA : NIL
SCOPE OF STRUCTURE
WORKS
ROB : NIL
MAJOR BRIDGES : NIL
MINOR BRIDGES : NIL
PEDESTRAIN UNDERPASS/ : NIL
CATTLE UNDERPASS
VEHICULAR UNDERPASS : NIL
SLAB/BOX CULVERT : 1
W- BEAM CRASH BARRIER, GABION WALL/ STRUCTUTE ON HILL SIDE/ VALLEY SIDE, ROPE
PROTECTION WORK : PANNEL ALONG WITH HIGH RESISTANCE GEOCOMPOSITE WIRE MESH WITH TOP , BOTTOM
& SURFACE ANCHORS, DYNAMIC ROCKFALL BARRIER
BHARAT CONSTRUCTION

Project - Construction and Upgradation including specialized slope treatment of existing


road to 2-lane with paved shoulder from Exisiting Km. 458.900 to Km. 459.475 (Design
Ch 456.200 to Ch 456.800) of Patalganga Landslide of NH-07 under Chardham
Pariyojna on EPC basis in the state of Uttarakhand. (Design Length = 0.600 km).

SAFETY & HEALTH


1 Nos. of Safety Officers along with support staffs are deployed at site to take care of safety
aspects and Traffic Management.

Safety and Traffic management systems are implimented at all required locations as per the safety
and traffic management plan finalized for execution of the project. Atmost care is being taken for
safety of the work force as well as road users while carring out the various activities.

Road work under construction are baricated with sand bags and deliniators, cuasion tape along the
stretch for affective night vision.

Identification of activity based PPE requirement and provided to all workman and enforced to use
it , like nose mask, spectacles, gumboots, Hard Hat, fluorescent jackets, safety belts, safety shoes
etc.

Provison of water tanker for sptinckling water to dust control in / along works on the highway,
access road, plant site and sprinkling system at cruesher sites.

Overall house keeping in the camp and plant site.

The awareness / tranning programme on HSE for workes, conducted periodically like fire safety /
Flagmen/ safe driving dra/traffic control & movement etc. and tool box talk conducted at site on
reguar bassis.

All the structural work / form work / scaffolding taken up as per approved drawing and
mathodology and being assured by concerened enginners.

Bushes has been removed from the road edge side to enhanced better visibility wherever is
required.

Use of Safety Jackets, Helmets, safety shoes is routine process of execution.


BHARAT CONSTRUCTION

Project - Construction and Upgradation including specialized slope treatment of existing road to 2-
lane with paved shoulder from Exisiting Km. 458.900 to Km. 459.475 (Design Ch 456.200 to Ch
456.800) of Patalganga Landslide of NH-07 under Chardham Pariyojna on EPC basis in the state of
Uttarakhand. (Design Length = 0.600 km).

SALIENT FEATURES OF THE PROJECT


INTRODUCTION
NAME OF PROJECT
Construction and Upgradation including specialized slope treatment of existing road
: to 2-lane with paved shoulder from Exisiting Km. 458.900 to Km. 459.475 (Design Ch
456.200 to Ch 456.800) of Patalganga Landslide of NH-07 under Chardham
Pariyojna on EPC basis in the state of Uttarakhand. (Design Length = 0.600 km).

NAME OF CLIENT : National Highways & Infrastructure Development Corporation Limited Ministry of
Road Transport & Highways
NAME OF EPC CONTRACTOR : BHARAT CONSTRUCTION

NAME OF AUTHORITY ENGINEER :


NAME OF DESIGN CONSULTANT : CIVIL MANTRA INFRACON PVT. LTD.
NAME OF PROOF CONSULTANT :
NAME OF SAFETY CONSULTANT :
TOTAL PROJECT COST : 37cr.
DATE OF SIGNING OF EPC AGREEMENT : 17th December 2018
APPOINTED DATE : 3th May 2019
DATE OF COMPLETION : Monday, May 04, 2020
CONSTRUCTION PERIOD : 12 Months
DEFECT LIABILITY PERIOD : 5 Years
BHARAT CONSTRUCTION

Construction and Upgradation including specialized slope treatment of existing road to 2-lane with
paved shoulder from Exisiting Km. 458.900 to Km. 459.475 (Design Ch 456.200 to Ch 456.800) of
Patalganga Landslide of NH-07 under Chardham Pariyojna on EPC basis in the state of Uttarakhand.
(Design Length = 0.600 km).

PHYSICAL AND FINANCIAL PROGRESS


PARTICULARS UPTO PREVIOUS THIS MONTH UPTO DATE
MONTH
PHISICAL PROGRESS UPTO 28 MAY 2019 FROM THE DATE OF 0.00% 2.18% 2.18%
START

FYNANCIAL PROGRESS UPTO 28 MAY 2019 FROM THE DATE OF 0.00% 0.00% 0.00%
START
BHARAT CONSTRUCTION
PROJECT: Construction and Upgradation including specialized slope treatment of existing road to 2-lane with paved shoulder from Exisiting Km. 458.900 to
Km. 459.475 (Design Ch 456.200 to Ch 456.800) of Patalganga Landslide of NH-07 under Chardham Pariyojna on EPC basis in the state of Uttarakhand.
(Design Length = 0.600 km).

FINANCIAL PROGRESS
UPTO PREVIOUS
BILL NO. DESCRIPTION AMOUNT (RS) THIS BILL UP TO DATE REMARK
BILL
Earthwork upto top of the Sub-grade 4,883,807.60 - - -
Non Bituminous base course 9,395,121.40 - - -
Road work Bituminous base course (DBM) 4,815,638.80 - - -
Bituminous Concrete 2,906,912.40 - - -
Culverts 2,344,519.80 - - -
Road Side drains 1,970,227.80 - - -
Other Engineering Utility Duct 172,827.00 - - -
Works W Beam Crash Barrier 3,110,886.00 - - -
Road Signs, Marking, Safety Devices etc. 1,278,919.80 - - -
Slope Protection including Secured Dapery 137,190,072.60 - - -
system on hill with Retaining wall
Protection work
Rockfall barrier 53,922,024.00 - - -
Cast- in- situ Arch Shaped Concrete Tunnel 148,009,042.80 - - -
PHYSICAL PROGRESS

Unit ofScope Percentage Upto This Upto


SL. No. PARTICULAR OF ITEMS Work Weightage Estimated Cost Previous %age
Month date

TOTAL ESTIMATED COST FOR 0.600KM 370,000,000

Road works including Culverts,


1 6.58% 24,346,000
Widening & repair of Culverts
Reconstruction / New 2-lane realignment
A (flexible pavements)
I Earthwork upto top of the Sub-grade Km 0.450 20.06% 4,883,808 0.000 0.080 0.080 17.78%
II Non Bituminous base course Km 0.450 38.59% 9,395,121 0.000 0.000 0.000 0.00%
III Bituminous base course (DBM) Km 0.450 19.78% 4,815,639 0.000 0.000 0.000 0.00%
IV Bituminous Concrete Km 0.450 11.94% 2,906,912 0.000 0.000 0.000 0.00%
B Reconstruction & New Culverts
I Culverts Nos. 1 9.63% 2,344,520 0.000 0.000 0.000 0.00%
2 Other Works 93.42% 345,654,000
I Road Side drains Km 0.450 0.57% 1,970,228 0.000 0.000 0.000 0.00%
II Utility Duct Km 0.450 0.05% 172,827 0.000 0.000 0.000 0.00%
III W Beam Crash Barrier Km 0.600 0.90% 3,110,886 0.000 0.000 0.000 0.00%
IV Road Signs, Marking, Safety Devices etc. Km 0.450 0.37% 1,278,920 0.000 0.000 0.000 0.00%
Special Land Slide Work
Slope Protection including Secured
V Dapery system on hill with Retaining wall Km 0.450 39.69% 137,190,073 0.000 0.056 0.056 12.44%
VI Rockfall barrier Km 0.200 15.60% 53,922,024 0.000 0.000 0.000 0.00%
VI Cast- in- situ Arch Shaped Concrete TunneKm 0.150 42.82% 148,009,043 0.000 0.000 0.000 0.00%
Total Amount in Rs. 370,000,000 2.18%
Monthly Progress Percentage 2.18%
BHARAT CONSTRUCTION
PROJECT: Construction and Upgradation including specialized slope treatment of existing road to 2-lane
with paved shoulder from Exisiting Km. 458.900 to Km. 459.475 (Design Ch 456.200 to Ch 456.800) of
Patalganga Landslide of NH-07 under Chardham Pariyojna on EPC basis in the state of Uttarakhand. (Design
Length = 0.600 km).

STATUS OF DRAWING SUBMISSION


D.Ch.
SR NO. DRAWING DESCRIPTION UNIT
Scope Submitted Approved Balance

ROAD WORK
1 0.600 _ _ 0.600
Plan & profile
km
2 0.600 _ _ 0.600
Typical cross-section
3 Dumpin Yard m _

STRUCTURE
1 Tunnel km 0.150 _ _ 0.150

2 Portal m _

3 Protection work km 0.450 _ 0.450

4 Culvert NOS. 1 _ _ 1

TOTAL>> 0.600 km
BHARAT CONSTRUCTION
PROJECT: Construction and Upgradation including specialized slope treatment of existing road to
2-lane with paved shoulder from Exisiting Km. 458.900 to Km. 459.475 (Design Ch 456.200 to Ch
456.800) of Patalganga Landslide of NH-07 under Chardham Pariyojna on EPC basis in the state of
Uttarakhand. (Design Length = 0.600 km).

STATUS OF MANPOWER DETAILS


SR NO. DESIGNATION MOBILIZATION STATUS REMARK
1 Project Manager 1 General duty
2 Billing Engineer/Planning 01No. 01 No.
3 Civil Engineers 01 Nos. 01 on each face
4 Foremen Civil 01 Nos. 01 on each face
Day night on
5 Supervisors (Civil) 01 Nos.
both face
6 Lab Technician 01 No. Q.C. laboratory
7 Safety Supervisor 01 Nos. 01 on each end
8 Foreman fabrication 01 No. Workshop
02 day & 02
9 Welders 01 Nos.
night
03 day & 03
10 Excavator operators 02 Nos.
night
06 day & 06
11 Tipper/Dumper operator 03 Nos.
night
01 day & 01
12 Concrete pump operator 01 Nos.
night
01 day & 01
13 HR 01 Nos.
night
01 day & 01
14 JCB operator 02 Nos.
night
04 day & 04
15 Mechanic 01 Nos.
night
05 day & 05
16 Skilled Labour 05 Nos.
night
17 Unskilled labour 20 Nos. 25 in each shift
01 day & 01
18 Electrician 01 Nos.
night
19 Surveyor with two helper 01 No. As required
20 Fabrication & Installation gang 04 Nos. As required
21 Flagman 02 Nos. As required
BHARAT CONSTRUCTION
PROJECT: Construction and Upgradation including specialized slope treatment of existing road to 2-
lane with paved shoulder from Exisiting Km. 458.900 to Km. 459.475 (Design Ch 456.200 to Ch 456.800) of
Patalganga Landslide of NH-07 under Chardham Pariyojna on EPC basis in the state of Uttarakhand. (Design
Length = 0.600 km).

STATUS OF MACHINERY MOBILISED


SR NO. DESIGNATION MOBILIZATION STATUS REMARK
1 Hydraulic Excavator with breaker 01 Nos.
Tippers/Dumpers (15Ton/18Ton)
2 02 Nos.
capacity
3 Diesel Air Compressor 600 CFM 01 Nos.
4 Water Tanker 01 No.
7 Concrete Pump 30 cum per hr 01 Nos.
Concrete Mixer 01 Nos.
8 JCB 01 Nos.
D.G. Set 500 KVA (stand by for
10 01 Nos.
power supply)
12 Inspection Vehicles 01 No.
13 Bolero Camper 01 No.
BHARAT CONSTRUCTION
PROJECT: Construction and Upgradation including specialized slope treatment of existing road to 2-lane with paved shoulder from
Exisiting Km. 458.900 to Km. 459.475 (Design Ch 456.200 to Ch 456.800) of Patalganga Landslide of NH-07 under Chardham Pariyojna on EPC
basis in the state of Uttarakhand. (Design Length = 0.600 km).

PROJECT COMPLETION MILESTONE

PLANNED
DAYS FROM SHEDULED PROPORTION OF
SR NO. MILESTONE DESCRIPTION REMARK
APPOINTED DATE MILESTONE DATE TPC TO BE
EXPENDED (%)

1 MILESTONE-1 120 31-Aug-19 10.00 _ _

2 MILESTONE-2 210 29-Nov-19 30.00 _ _

3 MILESTONE-3 300 27-Feb-20 60.00 _ _

4 MILESTONE-4 365 2-May-20 100.00 _ _


BHARAT CONSTRUCTION

PROJECT: Construction and Upgradation including specialized slope treatment of existing road to 2-lane with
paved shoulder from Exisiting Km. 458.900 to Km. 459.475 (Design Ch 456.200 to Ch 456.800) of Patalganga
Landslide of NH-07 under Chardham Pariyojna on EPC basis in the state of Uttarakhand. (Design Length = 0.600
km).

UNRESOLVED ISSUES

SR NO. ACTIVITY CONSTRAINTS REMARK

1 LAND ACQUISITION Dispute to be resolved toward Dhikol Village.

ELECTRICAL UTILITY
2 Yet to be shifted
SHIFTING

WATER PIPE LINE


3 Yet to be shifted
UTILITY

4 DISPOSAL OF MUCK Additional Dumping Yards required.

HT Tower no -7 (2200V) Yet to be shifted


5 Ch 64+773
BHARAT CONSTRUCTION

PROJECT: Construction and Upgradation including specialized slope treatment of existing road to
2-lane with paved shoulder from Exisiting Km. 458.900 to Km. 459.475 (Design Ch 456.200 to Ch
456.800) of Patalganga Landslide of NH-07 under Chardham Pariyojna on EPC basis in the state of
Uttarakhand. (Design Length = 0.600 km).

STATUS OF LAND ACQUISITION


SR NO. PARTICULARS AREA OF LAND IN HA. REMARKS

1
TOTAL LAND REQUIREMENT
2
LAND AVAILABLE EROW (Ha)
TOTAL LAND (Govt. & Pvt.) TO BE ACQUIRED AS PER
3 JMS (HA)

4
GOVT. LAND TO BE ACQUIRED AS PER JMS (HA)
5
PVT. LAND TO BE ACQUIRED AS PER JMS (HA)
6
3-D NOTIFIED (HA) (PVT. + GOVT. LAND)
7
3-D NOTIFIED (HA) (PVT.. LAND ONLY)
8
3-D NOTIFIED (HA) (GOVT. LAND ONLY)
9
3-G AWARD APPROVED
10 POSSESSION SLIP

11 TOTAL LAND IN POSSESSION W.R.T 3G AWARD


(S.NO. 2+4+9) (HA)
12 % OF LAND IN POSSESSION W.R.T 3G AWARD

13 TOTAL LAND IN POSSESSION W.R.T DISBURSEMENT


(S.NO. 2+4+10) (HA)
14
% OF LAND IN POSSESSION W.R.T DISBURSEMENT
15
ENUMBRANCE FREE LAND LENGTHWISE (KMS)
16
% OF ENCUMBRANCE FREE LAND LENGTHWISE
BHARAT CONSTRUCTION

PROJECT: Construction and Upgradation including specialized slope treatment of existing road to 2-lane with paved
shoulder from Exisiting Km. 458.900 to Km. 459.475 (Design Ch 456.200 to Ch 456.800) of Patalganga Landslide of NH-07
under Chardham Pariyojna on EPC basis in the state of Uttarakhand. (Design Length = 0.600 km).

STATUS OF UTILITY SHIFTING


SHIFTED TILL BALANCE TO BE REMARK
SR NO. DESCRIPTION UNIT TO BE SHIFTED DATE SHIFTED

1 ELECTRICAL UTILITY NOS. 0 0 0

2 TREES NOS. _ _ _

3 WATER SUPPLY LINE MTR. _ _ _

PERMANENT STRUCTURE
4 NOS. 0 0 0
(HOUSES & SHOPS)
__
BHARAT CONSTRUCTION

PROJECT: Construction and Upgradation including specialized slope treatment of existing road to 2-lane
with paved shoulder from Exisiting Km. 458.900 to Km. 459.475 (Design Ch 456.200 to Ch 456.800) of
Patalganga Landslide of NH-07 under Chardham Pariyojna on EPC basis in the state of Uttarakhand.
(Design Length = 0.600 km).

EPC COST BREAKUP


Road works including Culverts, Widening & repair of 6.58% -
Culverts
Reconstruction / New 2-lane realignment (flexible pavements) Unit Scope %age Amount
Earthwork upto top of the Sub-grade Km 0.450 20.06% 4,883,808
Non Bituminous base course Km 0.450 38.59% 1,884,661
Bituminous base course (DBM) Km 0.450 19.78% 966,017
Bituminous Concrete Km 0.450 11.94% 583,127
Reconstruction & New Culverts
Culverts Nos. 1 9.63% 470,311
Other Works 93.42% -
Road Side drains Km 0.450 0.57% 1,970,228
Utility Duct Km 0.450 0.05% 172,827
W Beam Crash Barrier Km 0.600 0.90% 3,110,886
Road Signs, Marking, Safety Devices etc. Km 0.450 0.37% 1,278,920
Special Land Slide Work
Slope Protection including Secured Dapery system on hill with Km 0.450 39.69% 137,190,073
Retaining wall
Rockfall barrier Km 0.200 15.60% 53,922,024
Cast- in- situ Arch Shaped Concrete Tunnel Km 0.150 42.82% 148,009,043
Total Amount in Rs. 370,000,000

Anda mungkin juga menyukai