3Shyam Telecom Ltd. vs Arm Ltd, 2 004 (3) ARBLR 146 Delhi, 2004 (77) DRJ 91 Para 17- “It is true
that 1996 Act does not prescribe any time limit for making and publishing the Award but that does not
mean that parties cannot by mutual agreement provide for a time limit for making the Award by the
Arbitrator and if so prescribed it would run contra to the provisions of the Act. This view appears to be
more plausible and acceptable having regard to the object of having Arbitration as the alternate mode
for settlement of disputes/differences between the parties.”
4 28. Power to Court only to enlarge time for making award.
(1) The Court may, if it thinks fit, whether the time for making the award has expired or not and whether the
award has been made or not, enlarge from time to time the time for making the award.
(2) Any provisions in an arbitration agreement whereby the arbitrators or umpire may, except with the
consent of all the parties to the agreement, enlarge the time for making the award, shall be void and of
no effect.
any time limit has given rise to another problem, namely, that
awards are getting delayed before the arbitral tribunal even
under the 1996 Act. One view is that this is on account of the
absence of a provision as to time limit for passing an award. 5
(3) Subject to section 33 and sub-section (4) of section 34, the mandate of the arbitral tribunal shall
terminate with the termination of the arbitral proceedings.
9 Section 6 of the Arbitration and Conciliation (Amendment) Bill, 2018-
“In section 29A of the principal Act,—
(a) for sub-section (1), the following sub-section shall be substituted, namely:—
"(1) the award in matters other than international commercial arbitration shall be made within a
period of twelve months from the date of completion of pleadings under sub-section (4) of section 23.”
10 Article 21. Commencement of arbitral proceedings- Unless otherwise agreed by the parties, the
arbitral proceedings in respect of a particular dispute commence on the date on which a request for that
dispute to be referred to arbitration is received by the respondent.
11 Jimmy Construction Pvt. Ltd. V UoI, 2008 (2) Arb LR 591 (Bom)
12 Haresh Chinnubhai Shah v Rajesh Prabhakar Jhaveri, 2004 (1) Arb LR 536 (Bom)
fails, then the date of appointment stands. 13 However, if the
challenge succeeds and a new arbitrator is appointed, then
s. 15 (4) comes into effect, which states-
“Unless otherwise agreed by the parties, an order or ruling of
the arbitral tribunal made prior to the replacement of an
arbitrator under this section shall not be invalid solely
because there has been a change in the composition of the
arbitral tribunal.”
Further, s. 15 (3) states-
“(3) Unless otherwise agreed by the parties, where an
arbitrator is replaced under sub-section (2), any hearings
previously held may be repeated at the discretion of the
arbitral tribunal.”
Thus, if an Arbitrator is substituted, then the previous
proceedings are not held to be void.
13 The Observations of the Delhi High Court in Newton Engineering and Chemicals v IOL 2006 (4) Arb LR
257 (para 24) -
“To conclude, I have no hesitation in holding that there is no provision in the Act empowering this
Court to terminate the mandate of the Arbitrator who has entered upon the reference and/or to
substitute the same with an Arbitrator appointed by this Court. The necessary corollary is that the
challenge to the appointment of the Arbitrator must be raised by the petitioner before the Arbitral
Tribunal itself. If such challenge succeeds, the petitioner shall have no cause for grievance left. If,
however, the petitioner is unable to succeed before the Arbitral Tribunal, it shall have no option except
to participate in the arbitral proceedings and if aggrieved by the arbitral award, to challenge the same in
accordance with the provisions of Section 34 of the Act.”
unsuccessful party, has compelled it to await an award. 1415 The
inclusion of this provision is also a departure by the legislature
from the old Act of 1940, where the Court was empowered to
remove arbitrators or umpire.16
In case the first time period of one year runs out and one or
both parties do not consent to the extension of the
proceedings, the Arbitrator / Tribunal shall terminate the
18 In The India Trading Company vs. Hindustan Petroleum Corporation Ltd. 2016 SCC Online Cal 479, a
Division Bench of the Calcutta HC has held-
"13. There is a difference between a decision which puts an end to the arbitral proceedings and a decision
whereby the arbitrator withdraws from the proceedings. Where the arbitrator withdraws from the proceedings, a
substitute arbitrator may appointed in accordance with the procedure, applicable to the appointment of the
arbitrator who is replaced, but where the arbitrator puts an end to the arbitral proceedings, the claimant cannot
pursue his claim.
14. The decision of the arbitral tribunal to put an end to the proceedings is a final award which can only
be challenged by way of an application for settling aside under Section 34 Sub-section (2) of the 1996
Act. Once the arbitral proceedings are terminated, the claimant cannot re-agitate the same claim by
initiation of fresh proceedings since the claim would be hit by principles of constructive res judicata.”
19 Angelique International Limited vs SSJV Projects Private Limited & Anr, O.M.P. (T) (COMM.)
91/2017 & I.A. Nos.13595/2017, 14086/2017
Section. 29A (2)
The language used here is, “as the parties may agree” and not
“as the parties have agreed”. This implies that there need be
no prior agreement of the parties to the Arbitration with regard
to the fee payable to the arbitrators if the award is made within
6 months. The parties are thus bound to, in concert, agree to
the additional fee payable.20
Further, the Court has a certain amount of discretion with regard to the
costs of arbitration.21
21 Section 39 (4)
“The Court may make such orders as it thinks fit respecting the costs of the arbitration where any
question arises respecting such costs and the arbitral award contains no sufficient provision
concerning them”.
22 S. 11 (14) as proposed in the 2018 Amendment bill-
“The arbitral institutions shall determine the fees of the arbitral tribunal and the manner of its payment to the
arbitral tribunal subject to the rates specified in the Fourth Schedule.
Explanation.—For the removal of doubts, it is hereby clarified that this sub-section shall not apply to
international commercial arbitration and in arbitrations (other than international commercial
arbitration) where parties have agreed for determination of fees as per the rules of an arbitral
institution.”
[THE FOURTH SCHEDULE]23
23
246thLaw Commission Report, Page 19, para 11, 12-
11.The model schedule of fees are based on the fee schedule set by the Delhi High Court International
Arbitration Centre, which are over 5 years old, and which have been suitably revised. The schedule of fees
would require regular updating, and must be reviewed every 3-4 years to ensure that they continue to stay
realistic.
12. The Commission notes that International Commercial arbitrations involve foreign parties who might have
different values and standards for fees for arbitrators; similarly, institutional rules might have their own schedule
of fees; and in both cases greater deference must be accorded to party autonomy. The Commission has,
therefore, expressly restricted its recommendations in the context of purely domestic, ad hoc, arbitrations.
Section. 29A (3)
25 The Arbitration Amendment Bill, 2018 proposes the following amendment to s. 29A (4)
“in sub-section (4), after the proviso, the following provisos shall be inserted, namely:—
"Provided further that where an application under sub-section (5) is pending, the mandate of the arbitrator
shall continue till the disposal of the said application:
Provided also that the arbitrator shall be given an opportunity of being heard before the fees is
reduced."
undue delay. This becomes amply clear upon an examination of sub-
section 6 of section 29A.26
It should be noted that once an arbitrator’s mandate has been
terminated, he may be appointed again. There is no specific
authority for this proposition, however, the Supreme Court has
decided a case where one of the Parties challenged the appointment
of the Arbitrator on the ground that he had decided a previous
dispute in a prior Arbitration proceeding arising out of the same
Contract, involving identical issues. The ground taken by the Party,
among others, was that the Arbitrator has had “The arbitrator has
previous involvement in the case.” 27
This is one of the grounds for
challenging the appointment of an Arbitrator.28 It is also a ground
which “gives rise to justifiable doubts as to the independence or
impartiality of arbitrators.”29 Another ground taken was that if
arbitrator has been appointed as an arbitrator on more than one
occasion by a party, such appointment falls afoul of Clauses 22 and
24 of the Fifth Schedule and therefore it is justified to doubt his
impartiality. It is worth noting that while the Fifth Schedule lays
down certain situations where an Arbitrator’s appointment may be
challenged, it is not an absolute rule. The Seventh Schedule,
however, lays down grounds that render a person “ineligible to be
26 “(6) While extending the period referred to in sub-section (4), it shall be open to the Court to
substitute one or all of the arbitrators and if one or all of the arbitrators are substituted, the arbitral
proceedings shall continue from the stage already reached and on the basis of the evidence and material
already on record, and the arbitrator(s) appointed under this section shall be deemed to have received
the said evidence and material.”
27Arbitration and Conciliation Act, 1996, Seventh Schedule, Clause 16
28 Section 12 (5) Notwithstanding any prior agreement to the contrary, any person whose relationship, with the
parties or counsel or the subject-matter of the dispute, falls under any of the categories specified in the Seventh
Schedule shall be ineligible to be appointed as an arbitrator:
Provided that parties may, subsequent to disputes having arisen between them, waive the applicability
of this sub-section by an express agreement in writing.]
29 See Clause 16, The Fifth Schedule, 1996 Act
appointed as an arbitrator”.30 This must be interpreted in light of
Explanation 3 to the Seventh Schedule which says-
30 See ibid, 22
31 HRD Corporation v GAIL India Ltd. (Civil Appeal no 11127 of 2017),
“The Arbitrator had a prior involvement in the dispute.”
24. On reading the aforesaid guideline and reading the
heading which appears with Item 16, namely “Relationship of
the arbitrator to the dispute”, it is obvious that the arbitrator
has to have a previous involvement in the very dispute
contained in the present arbitration.”32
“It has also been argued by learned counsel appearing on behalf of
the respondent that the expression “the arbitrator” in Item 16
cannot possibly mean “the arbitrator” acting as an arbitrator, but
must mean that the proposed arbitrator is a person who has had
previous involvement in the case in some other avatar. According to
us, this is a sound argument as “the arbitrator” refers to the
proposed arbitrator. This becomes clear, when contrasted with Items
22 and 24, where the arbitrator must have served “as arbitrator”
before he can be disqualified. Obviously, Item 16 refers to previous
involvement in an advisory or other capacity in the very dispute, but
not as arbitrator. 33
A combined reading of Sections 15(2) and 29A (4) tells us that if the
mandate of the Arbitrators terminates, then the rules applicable to
the appointment of the initial arbitrator shall be applicable. This, in
turn, means that if the Parties had decided upon the selection
criteria34 and procedure for Arbitrators, such rules and procedures
shall be followed here again. If there is no prior agreement, or the
parties do not agree again as to the procedure, then –
34 Section 11 (2) Subject to sub-section (6), the parties are free to agree on a procedure for appointing
the arbitrator or arbitrators.
35 Section 11 (3)
the appointment shall be made, upon request of a party, by [the
Supreme Court or, as the case may be, the High Court or any
person or institution designated by such Court];36
a party may request [the Supreme Court or, as the case may be, the
High Court or any person or institution designated by such Court] to
take the necessary measure, unless the agreement on the
appointment procedure provides other means for securing the
appointment.
36 Section 11 (4)
a delay of 6 months is 30% of the total fee. In such a case, the
cumulative deductions can be quite great. It is also worth observing
that the fee paid to an Arbitrator may be on more than one basis. It
may be fixed, per month, or per session. The imposition of a high
deduction can be especially severe and harsh where the Arbitrator
has agreed to a fixed fee. In such a situation, it is in his interest to
make an award as quickly as possible. It is hoped that the Court,
while imposing a deduction, shall both give a hearing to the
Arbitrator as to the quantum of deduction, as well as consider the
basis upon which his fee is paid. This is certainly the current position
of the law, which has also been made clear by the Legislature. The
2018 Bill includes an amendment which will add a Proviso to Section
29A (4) which specifies the right of the Arbitrator to be heard by the
court before his fee is reduced.37
The 1996 Act remains silent as to what happens when the time has
run out while an application for extension is pending with the court.
The 176th Law Commission in its Report, suggested that in such a
situation, Arbitration proceedings should be allowed to continue. 4243
Further, the Commission was of the opinion that if the proceedings
have not been concluded even after an extension by the Court, they
should be allowed to continue.44
It is not explicitly stated in the Act what would happen if no party
applies to the court to extend time. The 176th Commission’s view
was that In order that there is no further delay, after the period of
initial one year and the further period agreed to by the is over, the
arbitration proceedings will stand suspended and will get revived as
soon as any party to the proceedings files an application in the
Court for extension of time. In case none of the parties files an
application, even then the arbitral tribunal may seek an extension
from the Court.45 The Arbitration and Conciliation (Amendment) Bill
42 Page 124., Para 2.21.3
43 Proposed Section 29A (4)-
“Pending consideration of the application for extension of time before the Court under sub section (3),
the arbitration proceedings shall continue before the arbitral tribunal and the Court shall not grant
any stay of the arbitral proceeding”
44 176th Report, page 125, Para 2.21.5- there is no point in terminating the arbitration proceedings.
We propose it as they should be continued till award is passed. Such a termination may indeed result in
waste of time and money for the parties after lot of evidence is led. In fact, if the proceedings were to
terminate and the claimant is to file a separate suit, it will even become necessary to exclude the period
spent in arbitration proceedings, if he was not at fault, by amending sec. 43(5) to cover such a situation.
But the Commission is of the view that there is a better solution to the problem
45 This suggestion was formulated by the Commission in its proposed version of s. 29A (3)-
“If the award is not made within the period specified in sub-section (1) and the period agreed to by the
parties under sub-section (2), the arbitral proceedings shall, subject to the provisions of sub-sections (4)
of 2018 makes a very welcome improvement to the existing law by
stating that while the application for an extension is pending
decision by the Court, the Arbitration proceedings shall continue till
the application is disposed of by the Court.46
to (6), stand suspended until an application for extension is made to the Court by any party to the
arbitration, or where none of the parties makes an application as foresaid, until such an application is
made by the arbitral tribunal.
46 Section 6 of the Arbitration and Conciliation (Amendment) Bill, 2018-
“In section 29A of the principal Act,—
……………………..
(b) in sub-section (4), after the proviso, the following provisos shall be inserted,
namely:—
"Provided further that where an application under sub-section (5) is pending, the mandate of the
arbitrator shall continue till the disposal of the said application:”
Section. 29A (5)
Looking at the provision, it seems clear that the party applying for
extension must show that an extension of time should be granted.
The burden of proof is upon the applicant. “Party” has been defined
in the Act as “party” means a party to an arbitration agreement.
Therefore, the right to apply to a Court for the extension of time is
available only to the parties to the disputes, and not the Arbitrators.
It should be noted that the Law Commission, in its 176 th Report
stated that “if the parties do not apply, the arbitrators can also
apply for the same.”47
It should be noted that the phrases “may be granted” and “only for
sufficient cause” has also been used here. “Sufficient cause” has
also been used in section 5 of the Limitation Act.48 Thus, this
provision gives the Court a wide amount of discretion and places a
heavy burden upon the applicant. The use of the word “only”
ensures that the court can grant an extension under a limited set of
circumstances. It is possible that lengthy proceedings in courts may
The 176th Law Commission Report laid down the following things to
take into account while deciding upon the issue of time extension-
It is worth noting that the Act of 1940 also empowered the Court to
substitute Arbitrators when they were the cause of undue delay. This was
to be done upon an application made by a party. Thus, a Party could
initiate subsequent substitution of an Arbitrator, even if the appointment
was valid. Under section 11 (1) of the 1940 Act, it was stated-
“The Court may, on the application of any party to a
reference, remove an arbitrator or umpire who fails to use all
reasonable dispatch in entering on and proceeding with the
reference and making an award.”
Further, if the arbitrator was removed, he would not have been
entitled to any remuneration.54 Upon such removal, any party could
apply to have the vacant Arbitrator’s post filled.55
53 Section 2 (e)-
“Court” means—
(I) in the case of an arbitration other than international commercial arbitration, the principal Civil Court of
original jurisdiction in a district, and includes the High Court in exercise of its ordinary original civil
jurisdiction, having jurisdiction to decide the questions forming the subject-matter of the arbitration if the same
had been the subject-matter of a suit, but does not include any Civil Court of a grade inferior to such principal
Civil Court, or any Court of Small Causes;
(ii) in the case of international commercial arbitration, the High Court in exercise of its ordinary
original civil jurisdiction, having jurisdiction to decide the questions forming the subject-matter of the
arbitration if the same had been the subject-matter of a suit, and in other cases, a High Court having
jurisdiction to hear appeals from decrees of courts subordinate to that High Court;]
54 Section 11 (3) “Where an arbitrator or umpire is removed under this section, he shall not be
entitled to receive any remuneration in respect of his services”
55 Section 12 (1) Where the Court removes an umpire who has not entered on the reference or one or more
arbitrators (not being all the arbitrators), the Court may, on the application of any party to the arbitration
agreement, appoint persons to fill the vacancies.
(2) Where the authority of an arbitrator or arbitrators or an umpire is revoked by leave of the Court, or where the
Court removes an umpire who has entered on the reference or a sole arbitrator or all the arbitrators, the Court
may, on the application of any party to the arbitration agreement, either-
(a) appoint a person to act as sole arbitrator in the place of the person or persons displaced, or
(b) order that the arbitration agreement shall cease to have effect with respect to the difference referred.
Section. 29A (7)
56 This is similar to Section 15 (4) –“Unless otherwise agreed by the parties, an order or ruling of the
arbitral tribunal made prior to the replacement of an arbitrator under this section shall not be invalid
solely because there has been a change in the composition of the arbitral tribunal.”
Section. 29A (8)