This project is done as a part of the completion requirements for the above course.
DELIVERABLES:
• Update and complete the Design Basis for the third well. Show assumptions, be able
to explain your reasoning
• Evaluate tie-back options and recommend your proposed optimal tie-back option
based on economics, and ability to operate. Show your reasoning.
• Technical Deliverables
1. Create a seafloor layout of your recommended option specifically showing valve locations and tie in
points, controls and interface details as appropriate
2. Create a subsea equipment list identifying major components to be purchased, and any important
materials considerations or other interfaces.
3. Update the Red Hawk field P&ID to reflect the addition of this tieback, including details on valve locations,
connections, injection points
4. Prepare a block diagram control system sketch showing topsides to subsea end user control system
components, and describe the changes to topside equipment that need to be evaluated.
• List your top three uncertainties or areas of risk or concerns and how these should
be managed.
Index
• Introduction
• Updated Design Basis
• Viable Options Under Consideration
• Pros & Cons Of Each Option
• Specifics of the Selected Option
• Seafloor and Drill Center Plans
• Flowline Temperature Simulation
• Piping and Instrumentation Diagram (P&ID)
• Equipment List
• Block Diagram Of Control System
• General Operating and Control Procedures
• Top 3 Uncertainties and Possible Solutions
• References
Introduction
• The first two wells for the Red Hawk development in GB 877 are online and
flowing. A third exploratory well has been drilled and is planned for the
development. It is located about 1 mile due South and ½ mile East of the
current GB 877 Well #1 and still within block GB 877 but in 5260 ft of water.
• The Well can be marked up on the field to be at the edge of a Hazard mass.
• In this project we have looked at 3 possible options to tie back the well into
the SPAR.
• The first option is a tie back to the existing manifolds of Tree #1 and #2.
• The Second Option is a route through the Hazard mass directly into the
riser via an entirely independent flowline
• The third option considered are independent flowlines directly to the risers
via the same route as for Tree 1 & 2 flowlines.
• Note: There might be other options as well but the authors have selected
these 3 based on the most popular practices in the industry, and also
maintaining a practicality in approach.
Design Basis
Anadarko Red Hawk Design Basis
General Data Well 1&2 Well 3
Note: As the well production is yet to be started it can not be determined if the
Gas lift system is needed as the flowrates are undefined, but authors
recommend that design should be made considering the induction of a gas
injection system near the well if desired later on.
Wells Number of Production Wells 2 1
Number of Production Well Locations 2 1
Number of Water Injection Wells 0 0
Chemical Injection:
MEG Yes Yes
LDHI Yes Yes
Note: Since the 3rd well is predicted to be similar to the earlier ones, chemical and
pressure properties are assumed to be the same for the purpose of initial design.
Subsea, Umbilicals and Flowlines
Sub-Sea Wells Type Completion Horizontal Horizontal
Wellhead Flowing Pressure, psig 5000 5000
Maximum SITP, psig 6900 6900
Wellhead Flowing Temperature, oF 150 150
Flowline Arrival Temperature, oF 90 74.31
Riser Base Gas Lift Kickoff N/A N/A
Subsea Manifold Gas Lift N/A N/A
Downhole Gas Lift N/A N/A
Subsea Choking? yes Yes
Design Life, yrs 20 20
Design Pressure , psig TBD TBD
Subsea Metering No No
Subsea Boosting No No
Gas Production 4 - 6 in 4 - 6 in
2 installed, 2 spare
2 spare
\
PROS & CONS
PROS CONS
No complications of induction into 2x3=6 miles of new pipeline has to be
existing system laid, this adds to cost tremendously
while we are still unsure of the
profitability of the 3rd well
Independence from the other 2 wells 1 riser is lost for expansion
No constraint on flow rate New route has to be mapped and
explored in detail
Specifics Of Selected Option (Why and How)
• On comparing all the pros and cons of all the 3 options we have decided to go ahead with
the first option due to Pros outweighing the cons and less uncertainty in the option as we
have limited information about the geomorphology.
• We are using two flowlines going from the 3rd well to the existing 2 manifolds (PLEMs) to
ensure pigability of the flowlines which go to the 3rd well.
• At the 3rd well drill center we need 2 PLEMs or one PLEM and one PLET depending on the
cost difference between a PLEM & PLET.
• We can use the tree which we have in storage as per the design scenario background, as
the 3rd well is assumed to be similar to the previous 2.
• The 2 flowline design makes pigging possible for the flowlines.
• Pigging could have also been accomplished with a single flowline and a subsea pig
launcher but that increases the cost and complexity of the system.
• Also if the well turns out dry or produces less than predicted then a complex and costly
system will be a investment in futility.
• The most important consideration in selecting this design was the flexibility it offered in
terms of expandability while keeping the costs to a minimum.
• Another important advantage this design offers over the other 2 is that if the well turns out
to have excess production we can always reroute/reuse the existing pipelines to 2nd or 3rd
option but the vice versa is not feasible.
• NOTE: The design could be started with a single flowline to first ensure a feasible
production from the well and once that is established we could expand to the second
flowline as shown. We are going to present and examine the entire setup for the purpose of
this project.
Seafloor Layout
Drill Center Plan
Jumper
Flying Leads
Temperature Drop Simulation in Flowlines
• The simulation was carried out based on net heat content of natural gas
based on the formula:
• 𝑄𝑛𝑒𝑡 = 𝜌𝐶𝑣𝜋𝑅 𝑖𝑛 2 𝐿𝑇(𝐾)
• Cv for natural gas is 1.85 kJ/KgK
• The loss in heat per meter was calculated based on the following formula:
2𝜋𝑘𝐿∆𝑇
• 𝑄= 𝑅𝑜𝑢𝑡
ln 𝑅𝑖𝑛
• The value of K was calculated by applying the above equations to flowlines
of well 1 and 2 and was found to be 0.0295 which is close to the insulation
constant of polyurethane(0.0245). The variation can be attributed to the
steel inner lining, or concrete coating.
• Now equation 2 was used along with the value for K to calculate the heat
loss per meter for products from well 3.
• For ever meter of heat loss we use equation 1 to calculate temperature and
then repeat previous step. Result graph published on the next slide.
Simulation Result via MS Excel
Drop In Temp As Per Simulation
70
60
Temperature in Degree Celcius
50
40
30
20
10
0
0 1000 2000 3000 4000 5000 6000 7000 8000 9000
Length of Flowline in Meters
Final Predicted Temperature at SPAR for well #3: 23.51 Deg Celsius= 74.31F
The 3rd well is predicted to have lean gas. Based on the predicted value of temperature via
simulation and the graph above we can say that solely based on temperature and pressure
conditions hydrate formation is inhibited.
Note: This does not mean hydrates will not form under any conditions, inclusion of water or
change is gas composition might still lead to hydrates, MeOH and MEG injection systems
are to be installed on the 3rd well also for this reason.
P & ID: Manifold Connections Only
P & ID: 3rd Tree
Integrated with
manifolds
Manifold Configuration with 2 PLEMs at 3rd
Well
Preliminary Equipment List
S/N TYPE Q'ty
1 PLEM 1
2 PLET 3
3 SUTA 1
4 Umbilical 1
5 Electrical/Hydraulic Flying Leads 5
6 5" Hard Pipe Jumper 4
7 TREE 1
S/N Type Q’ty
1 PLEM 1 or 2
Manual Valves 3
Actuated Gate Valve 1
Transmitter 1
2 PLET 3
Manual Valve 1
3 SUTA 1
4 JUMPER 2
5 Tree 1
Valves 17
Actuated Valves 12
Manual Valves 3
Poppet Gate Valve 2
Transmitter 1
Block diagram of control system
Process Control
System
Master Control
Electrical Power Hydraulic Power Unit Chemical injection Unit
Station
TUTU
SUTA SUTA
PLET #1
Note: This block diagram is only specific and
limited to control systems (umbilical etc.) and
PLET #2 does not show flowlines etc.
Generic Operations & Controls Procedures
• Normal Operations
• Normal Shutdown/Planned Shutdown
• Hydraulic Shutdown/Emergency Shutdown
• Modes Of Operation (Start-up, Testing)
• Pigging
• Installation methods and requirements
Normal Operation
• In normal operation, the control system will provide several key information
for the operation and the production such as:
• Temperature/Pressure the flow rate
• Allow the subsea valve and choke to be operated
• Any specified status changes and alarms will display
• As soon as operation condition are outside pre-defined LoLo or HiHi
conditions or for any shutdown or safety event, action are required.
• Here are some of causes of shutdown:
• LoLo or HiHi pressures and temperatures in various part of the system eg
trees flowlines control fluid
• Loss of power or communications to MCS, drilling center or SCM
• Shutdown of process or injection equipment topside on installation
• Shutdown signal received by radio signal from MODU working at a drill
center
• We have to use the cause and effects chart to manage shutdown events. It
will specify how system reacts to specific events as shown ahead.
Normal Shutdown
• Definition: A normal shutdown is to shut-in the
tree by closing all or most of the valves on
the tree
A typical procedure is:
• Close the production insulation valve to
protect the USVs
• Close all the CIV and annulus Valves
• Close the choke (15% normally)
• Close the primary USV and lastly the SCSSV
• Planned Shutdowns
• We can plan that for well testing,
maintenance/repairs on tree or
long term subsea system
downtime.
• For short term well shutdown:
• While well still flowing, we inject
hydrate inhibitor at the tree until
whole jumper or flowline contain
protected fluid.
• Then we control the shutdown of
the well using choke. We close
then the FIV, PWV PMV and
SCSSV.
• If the period has to be greater
the process remains the same
but we have to inject Hydrate
inhibitor treatment at the tree
and the tubing.
Emergency Shutdown
• A hydraulic shutdown are used if there is a loss of
communication with the SCMs or there is a need
to depower the subsea system completely
• First, by activating the blow down valve (BDV) at
the HPU headers, all hydraulic pressure from the
SCM and umbilical will be released from the BDVs
and vented to the HPU return tank.
• Therefore, the Low pressure line will be vented
first to close all other subsea prior the SCSSVs.
Unplanned well shutdown
• It can be caused by:
• Failure of subsea equipment (Hydraulic leak, Electrical failure…)
• Pressure or temperature alarms
• Failure of subsea controls equipment
• As it is unplanned, we need to pay attention at the time line designed to release hydrate
mitigation in good time.
• Here is the time line:
• ‘No Touch time’: It is the time period immediately following a shutdown when no hydrate
mitigation is necessary.
• During this time the main focus is to get the plant re-started. But some preparation must be
done to ensure ‘light touch'
• Light Touch time: The time period between end of no tough time and start of displacement.
• During this period MeOH is injected into dead leg areas such as trees, well tubing and tree
jumpers. The time period needs to be sufficient so that all volumes are treated before
‘displacement’ has to start.
• So we will have a small volume for a shutdown less than 1 week. And we will inject below
SCSSV if it is superior to 1 week.
• Displacement: Time when live crude in the flowlines is displaced. Displacement must be
completed prior to the end of Cooldown time
Modes of Operation
• Well start-up
• During starting up a well, we need to pay
attention if the well and the flown are warm
or cold. The process is the same but it will
more or less time to warm up and
therefore more or less MeOH.
• We open PWV, PMV and SCSSV and
equalize differential pressure using MeOH
through Meg injection.
• We equalize and open the PIV and the
manifold header valves. We control the
flow using the choke.
• We have to check the sand detector and
the PT2 to ovoid the hydrate formation.
• During starting up a well we are injecting
Hydrate prevention chemical (MeOH)
continuously until arrival temperature
reaches pre-determined level.
• To test of flowline for our case, the single
well will flow into a test flowline usually its
own. The test flowline is directed to a test
separator. It should reflect actual normal
flow operation conditions.
Steps to Pig the 3rd well (Pigging)
1. Out of the two flowlines coming from well#3 one has to be
closed by shutting the respective PLEM/PLET.
2. Out of the 2 flowlines from well 1&2 one has to be shut.
3. Then a pig can be launched down one of the flowlines going
to the SPAR.
4. By keeping the jumper between well 1 & 2 closed we direct
the pig towards well 3.
5. Once the pig reaches well 3, we open the jumper between
the two PLEMs at well 3.
6. The pig flows into the actual production line and flows back
to the SPAR.
7. Note: Refer P & ID for better understanding.
Installation methods and requirements are to be directly referred
from API RP 17 and can not be changed for specific fields.
Top 3 Risks & Uncertainties
• List of top 3 areas of Uncertainties or concerns and intended plan to cope with them:
1. Not Enough Downhole Pressure: Although the well is assumed to be similar to the 2
others and designed accordingly. The downhole pressure during production might very
well turn out to be lower than anticipated for the flow to occur all the way to the SPAR
due to the addition of one mile of flowline length. The way to deal with this uncertainty
would be to have the extension of the umbilical designed for the inclusion of a gas
injector. Also it has to be ensured that the tree being used is capable of gas injection.
Also statistically, a gas injection system would boost the productivity of the well by 20%.
2. If the well is producing at a rate higher than what the planned tie back configuration is
capable of handling. In this case an alternative concept design has to be ready to be
implemented (option 3&2 etc.) for a direct tie back into the risers. Also the use of 2
PLEMs instead of PLEM and PLET near the 3rd well ensures the field expandability in the
future if needed.
3. The composition of products is far from anticipated. This would be a very serious concern
since it would throw all our insulation and hydrate mitigation calculations off the mark.
The first option would be to increase the MEG or MeOH injection if necessary,
adjustments for the same need to be incorporated into the design. If the inhibition is still
not effective a new pipeline with better insulation or PIP etc. might have to be applied at a
huge cost to the operator/Owner.
References
• Fundamentals of Subsea engineering notes &
Videos (TAMU)
• Prof. Dave Lucas (TAMU)
• www.Engineeringtoolbox.com
• Dr. M. Bramhi (Simon Frazier University)
• API
• PetroWiki
Thankyou!
Please mail any questions to:
ashwin.amrina@tamu.edu
thomasdelcourt@tamu.edu
byungjinzzz@tamu.edu